Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.

B
Package CP104 Request for Quotation (Major Subcontractor)

REQUEST FOR QUOTATION (MAJOR SUBCONTRACTOR)

Date: 15 August 2022


Our Reference: MMSP104-RFQ-3002
Kaufman Inc.
Unit C & D 865 A Mabini St. San Juan

Attention: Mr. David Edward C. Kaufman

Subject: Request for Subcontract Quotation – Stone/Granite Works

Construction of Metro Manila Subway Project Phase 1 – Package CP104

Dear Sir,
We (the “Main Contractor”) are currently engaged in construction contract for the Main Contract Works
associated with the Metro Manila Subway Project Phase 1 – Package CP104 and invite you (the “Bidder”
or the “Subcontractor”) to submit your best / keenest price for the above-referenced works
(“Subcontract Works”) in accordance with the enclosed documents and the requirements as set out
below in this letter.

Quotation(s) should be returned as follows:


1) Return of Quotation(s): 1.1) Date for return of Quotation(s): 24 August 2022
1.2) Quotation(s) to be delivered to:
Tokyu-Tobishima-Megawide Joint Venture
Commercial Department
3F #20 N. Domingo St. Brgy Valencia, Quezon City,
Philippines 1112
For the attention of Mr. Melvin Faustino

1.3) Quotation(s) to be sent by e-mail to (soft copy):


To:
Ms. Kristie Balandra: bkbalandra@megawide.com.ph
CC:
Mr. Yasuyoshi Nomura: nomura.yasuyoshi@tokyu-cnst.co.jp
Mr. Melvin Faustino: mfaustino@megawide.com.p
Mr. Kazuto Miyakage: miyakage.kazuto@tokyu-cnst.co.jp
Ms. Edith Davad: maeditha.davad@tokyu-cnst.co.jp
Ms. Rose Ann Calma: rcalma@megawide.com.ph

619527895.docx Page 1 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
2) Number of copies of Quotation(s): Original: 1
Photocopy: 1
Electronic copy (CD): N/A
3) Other requirements: N/A
The Quotation(s), including all correspondence and documents exchanged between the Bidder and
ourselves shall be written in the English language. Supporting documents and printed literature,
brochures, etc. that are part of the Quotation(s) may be in another language provided they are
accompanied by an accurate translation of the document (or relevant part(s) of the document) into
English.
You should note that all documentation (including, without limitation, all designs, drawings and pricing
data) provided to or produced by yourselves as part of this process, is to be treated with the utmost
confidentiality and is not under any circumstances to be divulged to any unauthorized third parties.

Should you have any questions in relation to the attached documents, then these should be submitted
progressively to the undersigned at the address noted in item 1.2) above, and not later than five (5)
working days before the date for return of Quotation(s) set out in item 1.1) above.

You are requested to acknowledge receipt of this Request for Subcontract Quotation and enclosures
and confirm by return that you are able to submit a Quotation(s) in accordance with our requirements.

Yours faithfully,

Yasuyoshi Nomura
General Manager/Chief Representative
On behalf of Tokyu-Tobishima-Megawide Joint Venture

Cc:

Encl.

619527895.docx Page 2 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

CONSTRUCTION OF METRO MANILA SUBWAY PROJECT PHASE 1


Manila, Philippines

SUBCONTRACT DOCUMENTS
FOR

CP104: TWO UNDERGROUND STATIONS (ORTIGAS NORTH AND SOUTH STATIONS)


AND TUNNELS

Tokyu-Tobishima-Megawide Joint Venture


3F #20 N. Domingo St. Brgy Valencia, Quezon City, Philippines 1112

August 2022

619527895.docx Page 3 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

CONTENTS
Section
A Relevant Particulars of Subcontract Works
B Relevant Particulars of Main Contract
Appendix 1: Quotation Format
1.1 Pre-qualification Proposal
1.1.1 Details of Completed Projects
1.1.2 Details of Current Projects
1.1.3 Plant, Equipment and Facilities
1.2 Technical Proposal
1.3 Price Proposal
1.3.1 Form of Quotation
1.3.2 Bill of Quantities
Appendix 2: Specifications
Appendix 3: Drawings
Appendix 4: Facilities, plant, equipment and other items
Appendix 5: Programmes
Appendix 6: Request for Clarification Format

619527895.docx Page 4 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

A-I Relevant Particulars of Subcontract Works

619527895.docx Page 5 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
A1 Description of Stone/Granite Works
Subcontract Works:
A2 Subcontract Quotation Unit Price Contract, subject to adjustment for changes in
Price: legislation and cost in accordance with the provisions of the
Main Contract

VAT to be shown separately on Form of Quotation

All other taxes, duties, levies, custom fees and charges, tests
report & certifications, relevant permits & approvals, etc., cost
related to Factory Acceptance Test (FAT) where necessary to be
included in the Quotation Price.

Quotation validity 90 days


period:
A3 Subcontract Programme: Subcontract Period / Time for Completion: Refer to Appendix 5

A4 Performance security: Required 10% of the Subcontract Price excluding


VAT. Valid until Main Contractor
receives Performance Certificate.

A5 Advance payment: Amount / %: 15% of the Subcontract Price excluding


Provisional Sums & VAT
Repayment: Rate: 30%. All to be repaid when gross
value of works certified = 90%
Guarantee bond: Required

A6 Progress Payment: Payment Issued upon checking of progress billing


Certificates:
Period for payment: Within 56 days from date of Main
Contractor’s receipt of payment from
Employer.

Materials on Site: Paid in accordance with the Main


Contract
Retention amount: 10%

Limit of retention: 5% of Subcontract Price

A7 Liquidated damages (LDs) Amount of LDs per 0.05% of the Subcontract Price per day,
for the delay: calendar day: in the currencies and proportions in
which the Subcontract Price is payable

Limit of LDs: 10% of the Subcontract Price

A8 Law and language: Law: The Laws of the Republic of the


Philippines

619527895.docx Page 6 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
Ruling language: English

A9 Subcontract Conditions: Standard Subcontract terms and conditions to apply. Copy of


Main Contract Tender Documents available for inspection (refer
to item B7. below). Pdf version provided.

A-II Special Conditions

Any special conditions that are relevant to the Subcontract are to be listed here:

SC1 N/A

B Relevant Particulars of Main Contract

619527895.docx Page 7 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

B-I General

B1 Title of Main Contract: Metro Manila Subway Project Phase 1 –


Package CP104

B2 Employer: Department of Transportation (DOTr)


B3 Main Contract Works: Construction of Two Underground Stations
(Ortigas North and South) and Tunnels
B4 Main Contract: The contract to be entered into between the
Employer and the Main Contractor
B5 Date Main Contract Letter of Acceptance N/A
issued/received:
B6 Main Contract Agreement signed: N/A
B7 Main Contract Tender Documents: Available for inspection from DOTr website
B8 Requirements in the Main Contract for Main Refer to Section B-II
Contractor’s insurances:
B9 Main Contractor’s preliminary Programme Refer to Appendix 5
for Main Contract Works:
B10 Time for Completion: Two Hundred Ninety (290) weeks
B11 Defect Notification Period: Two (2) years
B12 Delay damages for the Works: Five hundredth of a percent (0.05%) of the
Accepted Contract Amount per day, for the
completion of the whole of the Works; and
One hundredth of a percent (0.01%) of the
Accepted Contract Amount per day, for delay
in achieving element of the work with
respect to each Key Date
B13 Maximum amount of delay damages: Ten percent (10%) of the final Contract Price

619527895.docx Page 8 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
APPENDIX 1 QUOTATION FORMAT

1.1 PRE-QUALIFICATION PROPOSAL (This PROPOSAL may be submitted earlier separately)

1. COMPANY BACKGROUND

Company
Name:

Business Address:
Telephone No:

Facsimile No:

Person to contact for further information:

Financial: Contact No:

Technical:
Contact No:

Legal Entity: ☐ Sole Proprietor ☐ Partnership ☐ Company ☐ Others

If Subsidiary Co., state name of Holding Company:

Business Registration No.: Date of


Registration:

Tax Registration No.: Date of Registration:

Nature of Business:

2. QUALITY, HEALTH AND SAFETY, AND ENVIRONMENTAL MANAGEMENT SYSTEM

Is your company certified by a recognised Certification Body for the following?

Yes No

ISO 9001 Quality Management System ☐ ☐

ISO 45001 (or OHSAS 18001) Occupational Health and Safety Management System ☐ ☐

ISO 14001 Environmental Management System ☐ ☐

Please attach a copy of the ISO Certificate.

619527895.docx Page 9 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

3. FINANCIAL CAPABILITY

Name of Major and Current Banker with full


address:

(Attach confirmation from banker on the financial

Stability of the organization, if required)

Financial Data for Previous 5 Years [USD Equivalent] Unit: thousands


Year 1: Year 2: Year 3: Year 4: Year 5:
FY20xx FY20xx FY20xx FY20xx FY20xx

Information from Balance Sheet


Total Assets
Total Liabilities
Net Worth
Current Assets
Current Liabilities

Information from Income Statement


Total Revenues
Profit Before Taxes
Profit After Taxes

☐ Attached are copies of financial statements (balance sheets including all related notes, and income
statement) for the last five years, as indicated above, complying with the following conditions.

 All such documents reflect the financial situation of the Bidder, and not sister or parent
companies
 Historic financial statements must be audited by a certified accountant.
 Historic financial statement must be complete, including all notes to the financial statements.
 Historic financial statements must correspond to accounting periods already completed and
audited (no statements for partial periods shall be requested or accepted).

Annual Turnover Data for the Last 5 Years


Year Year 1: Year 2: Year 3: Year 4: Year 5:
FY20xx FY20xx FY20xx FY20xx FY20xx
Currency and
Amount (millions)
Exchange Rate
USD Equivalent

619527895.docx Page 10 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
(thousands)
Average Annual Turnover (USD)
The information supplied should be the Annual Turnover of the Bidder in terms of the amounts billed to
clients for each year for work in progress or completed, converted to USD at the rate of exchange at the
end of the period reported.

4. DETAILS OF COMPLETED PROJECTS

Please provide particulars of relevant / similar projects undertaken and completed by your company as
a contractor (single entity, JV member, subcontractor or supplier) over the past 5 years in the attached
format (Appendix 1.1.1).

The below relevant / similar project experiences shall include the following key activities:

1) N/A

5. DETAILS OF CURRENT PROJECTS

Please provide particulars of projects undertaken currently by your company in the attached format
(Appendix 1.1.2).

6. PLANT, EQUIPMENT AND FACILITIES

Please provide particulars of the plant, equipment and facilities considered to be necessary for
undertaking the project whether owned / hired by your company in the attached format (Appendix
1.1.3).

7. COMPANY LICENSE / PERMIT

Issuing Authority License / Permit No. Expiry Date

8. LABOUR FORCE

On the basis of the information provided in the prequalification documents, please indicate the likely
source of the labour force required to undertake the works.

☐ Direct Labour ☐ Subcontracted

9. DESIGN ABILITY

Please indicate your design ability for temporary and / or permanent works.
619527895.docx Page 11 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
☐ In-house ☐ Subcontracted

10. KEY PERSONNEL

List information about key personnel who will be committed to the contract for its duration and attach
their respective CV’s.

Name Designation Years of Major project involved


experience
in the
industry

Please attach an organization chart showing the company structure including the positions of directors
and key personnel.

11. ARBITRATION AND / OR LITIGATION

Is your company currently involved (or has been involved over the past 5 years) in any arbitration and /
or litigation in relation to claims and / or disputes?

☐ Yes ☐ No

If yes, please provide a brief description of the nature of the dispute, the amount under dispute and the
parties involved. (Please include disputes / claims which are pending arbitration / litigation.)

Is your company currently involved in any adjudication and / or litigation in relation to labour disputes?

☐ Yes ☐ No

If yes, please provide a brief description of the nature and the parties involved.

12. DEBARMENT

☐ I certify that our Company has NOT been debarred by the World Bank Group and / or local
regulatory authorities for more than one year since the date of issuance of this request.

619527895.docx Page 12 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
☐ I certify that our Company has been debarred by the World Bank Group and / or local regulatory
authorities for a period more than one year BUT that on the date of issuance this request at least three
years had passed since the date of such debarment decision. Details of the debarment are as follows:

Name of authority Starting Ending Reason for debarment


date of date of
debarment debarment

TO BE COMPLETED BY PERSON COMPLETING THIS FORM

I am completing this document as an authorized agent of the company. All the above information are
accurate and correct at the time this form is submitted.

Name: Signature:

Designation: Date:

Company Stamp or Seal:

619527895.docx Page 13 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

619527895.docx Page 14 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1.1.1 DETAILS OF COMPLETED PROJECTS

No. Name of Project Project Owner / Scope of Work / Location Start Date - Contract
Main Contractor Quantity of Supply Completion Value (USD)
Date
sample Tokyo MRT Project CP101 Tokyo MRT/ MEP works (AC, Tokyo, Japan 1/Jan/2021 – 50M USD
Tokyu Construction ventilation, 31/Dec/2022
plumbing)

*Please add pages if necessary.

619527895.docx Page 15 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1.1.2 DETAILS OF CURRENT PROJECTS

No. Name of Project Project Owner / Scope of Work / Location Start Date - Contract
Main Contractor Quantity of Supply Completion Date Value (USD)
<% completion>
sample Tokyo MRT Project CP101 Tokyo MRT/ Rebar supply / Tokyo, Japan 1/Jan/2021 – 10M USD
Tokyu Construction 14000 Tonnes 31/Dec/2022 < 60% >

*Please add pages if necessary.

619527895.docx Page 16 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

1.1.3 PLANT, EQUIPMENT AND FACILITIES

No. Plant & Equipment Quantity Unit Owned / Hired Capacity Location Remarks

No. Facilities & Storage (Disposal) Yard Quantity Unit Owned / Hired Capacity Location Remarks

619527895.docx Page 17 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)

*Please add pages if necessary.

619527895.docx Page 18 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
1.2 TECHNICAL PROPOSAL

Please attach method statement (including plant and equipment schedule).

619527895.docx Page 19 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
1.3 PRICE PROPOSAL

1.3.1 FORM OF QUOTATION


Notes on Form of Quotation:
a) The Quotation Price shall be quoted separately in the following currencies:
(i) For those inputs to the Works that are expected to be supplied from within the Philippines, in
Philippine Peso (referred to as Local Currency) and
(ii) For those inputs to the Works that are expected to be supplied from outside the Philippines
(referred to as Foreign Currency)
b) The Bidder may be required by the Main Contractor to justify, to the Main Contractor’s
satisfaction, their local and foreign currency requirements, and to substantiate that the amounts
included in the Subcontract Quotation are reasonable, in which case a detailed breakdown of the
foreign currency requirements shall be provided by the Bidder.
c) Subcontract Quotations are being invited for individual subcontracts for each contract packages.
Bidder who are submitting a Subcontract Quotation for more than one contract package shall be
required to offer a price reduction for the award of more than one Contract. The Bidder shall
specify on the Subcontract Quotation Form the percentage of price reduction that can apply to the
Subcontract Quotation Price in the case that more than one Contract is awarded.
d) Bidders are advised to visit and examine the Site of the Works and its surroundings and obtain for
themselves on their own responsibility all information that may be necessary for preparing the
Quotation and entering into a Subcontract for the performance of the Subcontract Works. The
costs of visiting the Site shall be at the Bidder’s sole own expense.
e) Notwithstanding item d) above, the Bidder shall be deemed to have inspected and examined the
Site and its surroundings and in regard to the execution of the Subcontract Works including for the
purpose of complying with his obligations, to have satisfied himself and taken account of it in his
offer before submitting his offer as to:
(i) the climatic, hydrological and general conditions relating to the Site and the Subcontract
Works;
(ii) the nature of the design (insofar as required in the Subcontract), temporary works, equipment
and materials necessary for the proper performance of the Subcontract;
(iii) the means of communication with and access to the Site including egress and ingress and the
entire Site logistical requirements;
(iv) the general availability of labour, all matters associated with the local skill and unskilled
labours including but not limiting to labour accommodations, transport, health & safety, etc.
and all things necessary to carry out the Subcontract Works at the Site;
(v) all necessary information as to risks, contingencies and all other circumstances influencing his
offer and his obligation to execute the Subcontract Works;
(vi) the nature, progress, extent and type of construction of the Main Contract Works and the
works of other contractors including all relevant and necessary interfaces; and
(vii) the programme requirements of the Main Contractor.
f) The Main Contractor and the Employer will have related Project works performed by other
subcontractors / suppliers and other contractors, or Employer’s agents or contractors and that it is
essential that the execution of the Subcontract Works is fully and completely co-ordinated with
these related works, the other subcontractors / suppliers and the other contractors in view of their

619527895.docx Page 20 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
concurrent and sequential nature. The Subcontract Quotation Price shall be deemed to have
included adequate allowance for compliance with these obligations.
g) The Main Contractor reserves the right to accept or reject any Quotation received, to waive any
required formality in the Quotations received and to cancel the Quotation process and reject all
Quotations at any time prior to the signing of a Subcontract Agreement, without thereby incurring
any liability to any Bidders.
Bidders are solely responsible for all costs associated with the preparation and submission of their
Quotation. The Main Contractor shall not be liable for any of these costs, regardless of the conduct or
outcome of the Quotation process.

619527895.docx Page 21 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract

PRICE PROPOSAL

QUOTATION

for

EXECUTION AND COMPLETION

of

SUBCONTRACT WORKS

STONE/GRANITE WORKS

Date:

Reference:

To: TOKYU-TOBISHIMA-MEGAWIDE JOINT VENTURE

3F #20 N. Domingo St. Brgy Valencia, Quezon City, Philippines 1112

Gentlemen:

(1) We have examined the Subcontract Documents, and Addenda Nos. [ ] for the above named
Subcontract Works. We have examined, understood and checked these documents and have
ascertained that they contain no error or other defects. We accordingly offer to design (to the
extent required), execute and complete the whole of the said Subcontract Works and remedy any
defects therein, in conformity with these Subcontract Documents and the aforementioned Addenda
for the following separate Prices:

Stone/Granite Works for Package CP104


(a) [Currency 1] [Amount in words ]
[Currency 1 Amount in figures]
(b) [Currency 2] [Amount in words ]
[Currency 2 Amount in figures]
(c) VAT [Amount in words ]
[Main Currency Amount in figures]

(2) We agree to abide by this Quotation for the period of validity prescribed in the Subcontract
Documents, Section A, Item A2 and to extend same for a further period upon the same terms and

619527895.docx Page 22 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
conditions, if so called upon.

(3) If our Quotation is accepted, we will provide the Subcontract Performance Security, enter into a
Subcontract Agreement with Tokyu-Tobishima-Megawide Joint Venture (the Main Contractor),
commence and complete the Subcontract Works within the periods prescribed in the Subcontract
documents.

(4) We agree that in respect of the works, goods, materials or services included in the proposed
Quotation we shall undertake towards the Main Contractor such obligations and liabilities as will
enable the Main Contractor to discharge his own obligations and liabilities towards the Employer
under the terms of the Main Contract and we will save harmless and indemnify the Main Contractor
from and against the same and from all claims, proceedings, damages, costs, charges and expenses
whatsoever arising out of or in connection therewith, or arising out of or in connection with any
failure to perform such obligations or to fulfil such liabilities.

(5) Unless and until the formal Subcontract Agreement is prepared and executed, this Quotation
together with your Letter of Intent shall constitute a binding Subcontract between us.

(6) We understand that you have no obligation whatsoever to compensate or indemnify us for any
expense or loss incurred in the preparation of this Quotation and that you are not bound to accept
the lowest or any Quotation that you may receive.

Dated this [ ] day of [ ] [ ]

Signature ____________________________________________

In the capacity of __________________________________________________________ duly


authorised to sign the Quotation for and on behalf of

_________________________________________________________________________

Witness : ________________________________________________________________

Address : ________________________________________________________________

619527895.docx Page 23 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract

619527895.docx Page 24 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1.3.2 BILL OF QUANTITIES

Please be informed that the attached BOQ (Bill of Quantities) is for reference only.
Please provide cost breakdown for the following BOQ item as part of your proposal.
BILL No.4A STATION ARCHITECTURE WORKS - ORTIGAS NORTH
Pay
No. Description UoM Qty Material Labour Equipment Unit Rate Total Price
Item no
Wall Finishes
1018 (3) Granite Stone Honed Finish –
1018 m2 1,934.25
a1 600x1200x30
1018 (3) Granite Stone Honed Finish –
1018 m2 472.68
a2 1200x150x30
1018 (3)
1018 Granite Stone Polished – 1200x600x30 m2 485.59
b1
1018 (3)
1018 Granite Stone Polished – 1200x150x30 m2 166.61
b2
1018 (3)
1018 Granite Stone Polished – 1200x800x30 m2 1,157.15
b3
Floor Finishes
1018 (3)
1018 Granite Stone Flamed - 600x600x25 m2 5,659.00
c1
1018 (3)
1018 Granite Stone Flamed - 600x300x25 m2 403.00
c2
1018 (3)
1018 Granite Stone Polished – 1200x80x25 m2 30.31
b4
1018 (3)
1018 Granite Stone Polished - 1200x150x25 m2 59.00
b5
1018 (3)
1018 Granite Stone Polished - 1200x600x25 m2 6.00
b7

619527895.docx Page 25 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1018 (3)
1018 Granite Stone Polished - 600x150x25 m2 176.10
b6
1018 (3) In-laid Granite Stone Directional Symbol
1018 m2 35.87
b11 and trim
1203 1203 (1) Granite Flooring; to Elevator m2 10.00
Baseboards, thresholds & Nosing Finish
1018 (3)
1018 Granite Stone Polished - 30mm thk lm 1,712.51
b9
1018 (3)
1018 Granite Stone Polished - 20mm thk lm 128.34
b10
1018 (3) Granite Stone Honed Finish - 200mm
1018 lm 30.20
a3 Threshold
Miscellaneous
1822 1822 (1) Quartz Countertop m2 18.59
1822 1822 (2) Quartz Ledge m2 23.62

SUB TOTAL BILL No. 4A (PHP)

BILL No.4B STATION ARCHITECTURE WORKS - ORTIGAS SOUTH


Pay
No. Description UoM Qty Material Labour Equipment Unit Rate Total Price
Item no
Wall Finishes
1018 (3) Granite Stone Honed Finish –
1018 m2 2,494.30
a1 600x1200x30
1018 (3) Granite Stone Honed Finish –
1018 m2 543.96
a2 1200x150x30
1018 (3)
1018 Granite Stone Polished – 1200x600x30 m2 609.06
b1

619527895.docx Page 26 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1018 (3)
1018 Granite Stone Polished – 1200x150x30 m2 182.50
b2
1018 (3)
1018 Granite Stone Polished – 1200x800x30 m2 1,058.66
b3
Floor Finishes
1018 (3)
1018 Granite Stone Flamed - 600x600x25 m2 5,170.00
c1
1018 (3)
1018 Granite Stone Flamed - 600x300x25 m2 370.00
c2
1018 (3)
1018 Granite Stone Polished - 1200x80x25 m2 31.37
b4
1018 (3)
1018 Granite Stone Polished - 1200x150x25 m2 39.00
b5
1018 (3)
1018 Granite Stone Polished - 1200x600x25 m2 3.00
b7
1018 (3)
1018 Granite Stone Polished - 600x150x25 m2 146.85
b6
1018 (3) In-laid Granite Stone Directional Symbol
1018 m2 35.87
b11 and trim
1203 1203 (1) Granite Flooring; to elevator m2 10.00
Baseboards, thresholds & Nosings Finish
1018 (3)
1018 Granite Stone Polished - 30mm thk lm 1,134.83
b9
1018 (3)
1018 Granite Stone Polished - 20mm thk lm 137.73
b10
1018 (3) Granite Stone Honed Finish - 200mm
1018 lm 11.58
a3 Threshold
Miscellaneous
1822 1822 (1) Quartz Countertop m2 14.02

619527895.docx Page 27 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
1822 1822 (2) Quartz Ledge m2 20.94

SUB TOTAL BILL No. 4B (PHP)

BILL No.6A STATION PLAZA - ORTIGAS NORTH


Pay
No. Description UoM Qty Material Labour Equipment Unit Rate Total Price
Item no
Finishes
1018 1018 Granite Stone m2 187.64

SUB TOTAL BILL No. 6A (PHP)

BILL No.7A PEDESTRIAN BRIDGE 1 - ORTIGAS NORTH


Pay
No. Description UoM Qty Material Labour Equipment Unit Rate Total Price
Item no
    Floor Finishes    
    Granite stone tiles    
600x600x20 mm Jetblack Granite, Flamed
       
Finish - Stair Landing
1018 (5)
1018 to floor m2 213.10
a
1018 (5)
1018 to landing m2 58.33
a
1018 (5) 110x600x20 mm Jetblack Granite, Flamed
1018 m2 49.37
d Finish - Stair Riser
1018 (5) 250x600x20 mm Jetblack Granite, Flamed
1018 m2 105.33
b Finish - Stair Run/Tread

619527895.docx Page 28 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
C70x600x20 mm Jetblack Granite Anti-slip
1018 (5)
1018 Chamfered Nosing, Flamed Finish - m2 231.11
c
Stair Nosing
SUB TOTAL BILL No. 7A (PHP)

BILL No.7B PEDESTRIAN BRIDGE 2 - ORTIGAS NORTH


Floor Finishes
600x600x20 mm Jetblack Granite, Flamed
Finish - Stair Landing
Granite stone tiles
1018 (5)
1018 to floor m2 96.48
a
1018 (5)
1018 to landing m2 71.19
a
1018 (5) 110x600x20 mm Jetblack Granite, Flamed
1018 m2 37.79
d Finish - Stair Riser
1018 (5) 250x600x20 mm Jetblack Granite, Flamed
1018 m2 80.62
b Finish - Stair Run/Tread
C70x600x20 mm Jetblack Granite Anti-slip
1018 (5)
1018 Chamfered Nosing, Flamed m2 272.00
c
Finish - Stair Nosing
SUB TOTAL BILL No. 7B (PHP)

GRAND TOTAL PRICE (PHP)

619527895.docx Page 29 of
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
APPENDIX 2 SPECIFICATIONS

Refer to the link below:

https://megawideph-my.sharepoint.com/:f:/g/personal/racalma_megawide_com_ph/
EjGFeMtHUktGkHR6TRWMYEcBkAVH43fikhV3zRKyASoYAw?e=9iWf9l

This Specification link contains the following:

1. CP104_TS_Civil_718 Granite Tiles


2. MMSP104_TS_AR_1018 Granite Tiles
3. MMSP104_TS_AR_1815 Sealants
4. MMSP104_TS_AR_1822 Quartz Countertop

Notes:

1) If the link does not connect after clicking the web page address above, please try copying the
link and paste into your browser.

APPENDIX 3 DRAWINGS

619527895.docx Page 30 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract

Refer to the link below:

https://megawideph-my.sharepoint.com/:f:/g/personal/racalma_megawide_com_ph/En-
R7zTmvixBlWiJZDeGb5kBK0gGiLo8FcJveLga_VCv5w?e=OCcKM1

This Drawing link contains the following:

1. 8_CP104_P2_S(VI)_(WR)_6(ED)_21Aug2020_14_Arch_ON
2. 8_CP104_P2_S(VI)_(WR)_6(ED)_21Aug2020_15_Arch_OS
3. 8_CP104_P2_S(VI)_(WR)_6(ED)_8Apr2020_20_Ped_ON
4. 8_CP104_P2_S(VI)_(WR)_6(ED)_11Aug2020_21_SPL_ON
5. 8_CP104_P2_S(VI)_(WR)_6(ED)_11Aug2020_22_SPL_OS
6. 8_CP104_P2_S(VI)_(WR)_6(ED)_5Feb2021_14_Arch_ON_only revision extracted_r
7. 8_CP104_P2_S(VI)_(WR)_6(ED)_5Feb2021_15_Arch_OS_only revision extracted_r

Notes:

1) If the link does not connect after clicking the web page address above, please try copying the
link and paste into your browser.

APPENDIX 4 FACILITIES, PLANT, EQUIPMENT AND OTHER ITEMS

619527895.docx Page 31 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
Facilities, plant, equipment and other items

a) The following facilities, plant, equipment and other items shall be provided to the Subcontractor
(SC) by the Main Contractor (MC) for the due performance of the Subcontract Works. These
facilities, etc. shall not be used for any other purpose other than the performance of the
Subcontract Works.
b) The facilities, etc. are not provided on an exclusive usage basis but in a manner that will support
the Main Contract Programme and the Subcontract programmes. For the effective and timely
usage of the facilities, etc. the Subcontractor will be proactive in the notification and planning of
such facilities with the Main Contractor, other subcontractors and other contractors.

Item Description MC SC N/A Notes

Site Fencing ☐ ü ☐
Offices Construction / rental ☐ ü ☐ If necessary
Power supply ☐ ü ☐
Electricity
Power consumption ☐ ü ☐
Cabling and main panel ☐ ü ☐
Subcontractor's
Office Sub-cabling and phone
Telephone ☐ ü ☐
sets
Consumption ☐ ü ☐
Main piping  ☐ ☐
Water
Consumption ☐  ☐
Labour Camp: ☐  ☐ If necessary
Main cabling & main
 ☐ ☐
distribution board
Temporary
electricity for small Secondary
tools panel/distribution ☐  ☐
boards
Consumption ☐  ☐
General safety/access  ☐ ☐
Temporary lighting
Working area/task ☐  ☐
Working Site Main water piping  ☐ ☐
Water storage tanks ☐  ☐
Temporary water Secondary water piping ☐  ☐
Secondary pump ☐  ☐
Consumption ☐  ☐
Provide site toilets ☐ ☐ ☐
Toilets Maintain & clean
☐  ☐
toilets
Lifting equipment ☐  ☐ If necessary

619527895.docx Page 32 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
Main access to the
☐  ☐
working site
Temporary road
Access within the
☐  ☐
working area
Working area ☐  ☐
Rubbish & Cleaning
Subcontractor's offices ☐  ☐
waste control
Disposal To off-Site ☐  ☐
Main gate  ☐ ☐
Security guards Around Subcontractor's
Security ☐  ☐
facilities
Gate pass Issuing  ☐ ☐
  Main access  ☐ ☐
Safety Working area   ☐
First Aid & nurse ☐  ☐
MC to provide
Monthly fossil fuel Reporting monthly the
☐ ü ☐ the template
consumption report usage of fossil fuel for the report
Soil Quality Monitoring ☐ ☐ ☐
Ground level
☐ ☐ ☐
Environment monitoring
Environmental Water quality
☐ ☐ ☐
monitoring monitoring
Air quality monitoring ☐ ☐ ☐
Noise level monitoring ☐ ☐ ☐
Vibration monitoring ☐ ☐ ☐
Method statements ☐  ☐
Inspection and test
☐  ☐
plan
Documentation Manufacturing plans ☐ ☐ 
Management plans ☐  ☐
Material approvals ☐  ☐
Sample submissions ☐  ☐
Test and Testing ☐  ☐
Inspection Inspection ☐  ☐
Factory
Transportation,
Acceptance Test Cost related to FAT ☐ ☐ ☐
Accommodation, etc.
(FAT)
Design drawings  ☐ ☐
Drawings
Structural drawings  ☐ ☐

619527895.docx Page 33 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
Shop drawings ☐  ☐
As-built drawings  ☐ ☐
Construction All Risk
☐ ☐ ☐
(CAR) Insurance
Workmen's
Compensation ☐ ☐ ☐
Insurance
Vehicles Insurance
for Physical Damage
☐ ☐ ☐
& Third Party
Insurances Liability
Main Contractors’
Plant, Machinery &
☐ ☐ ☐
Equipment
Insurance
Marine Cargo
☐ ☐ ☐
Insurance
Professional
☐ ☐ ☐
Indemnity lnsurance

APPENDIX 5 PROGRAMMES
5.1 Main Contractor’s Preliminary Programme
619527895.docx Page 34 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Re
Package CP104 Request for Quotation (Major Subcontract
N/A

5.2 Subcontractor’s Preliminary Programme


Please attach your construction programme.

619527895.docx Page 35 of 36
Metro Manila Subway Project Phase 1 MMSP104-COM-PRO001-FM004 Rev.B
Package CP104 Request for Quotation (Major Subcontractor)
APPENDIX 6 REQUEST FOR CLARIFICATION FORMAT

Sr. Vol Sec Clause Description Bidder’s Question Main Contractor’s Answer
No.
<Subcon/Supplier’s name>

*Please add pages if necessary