PROJECT TITLE: PROPOSED TWO-STOREY RESIDENTIAL BUILDING

PROJECT LOCATION: LIONG, DUMANJUG, CEBU


OWNER: MS.MR.JENEVEB
PARK CHANYEOL
P. NEBATO

S.R. NO. NAME OF ITEM QUANTITY UNIT UNIT COST TOTAL


1 MOBILIZATION/DEMOBILIZATION 1 lot 7,000.00 7,000.00

2 EARTHWORKS 33,225.00
SITE CLEARING AND EXCAVATIONS 1 lot 12,000.00 12,000.00
GROUND LEVELING AND BACKFILLS 111 m3 175.00 19,425.00
LAYOUT AND BATTER BOARD STAKING 1 lot 1,800.00 1,800.00

3 CONCRETE WORKS 50 cu.m. 4,909.00 245,450.00


FOOTING
CEMENT PORTLAND 157.939 bags 230.00 36,326.02
SAND 6.581 cu.m. 1,800.00 11,845.44
GRAVEL 13.162 cu.m. 1,800.00 23,690.88
3.1 COLUMN
CEMENT PORTLAND 37.094 bags 230.00 8,531.71
SAND 1.546 cu.m. 1,800.00 2,782.08
GRAVEL 3.091 cu.m. 1,800.00 5,564.16
3.2 BEAM/GIRDER
CEMENT PORTLAND 98.250 bags 230.00 22,597.50
SAND 4.094 cu.m. 1,800.00 7,368.75
GRAVEL 8.188 cu.m. 1,800.00 14,737.50

3.3 SLAB
CEMENT PORTLAND 241.402 bags 230.00 55,522.37
SAND 10.058 cu.m. 1,800.00 18,105.12
GRAVEL 20.117 cu.m. 1,800.00 36,210.24
TOTAL
CEMENT PORTLAND 535.00 bags 230.00 123,050.00
SAND 23.00 cu.m. 1,800.00 41,400.00
GRAVEL 45.00 cu.m. 1,800.00 81,000.00

Prepared by: Approved by:

LEZIE A. TUMBIGA MR. PARK CHANYEOL