Professional Documents
Culture Documents
JSA For Cutting, Grinding and Welding in Atmosphere
JSA For Cutting, Grinding and Welding in Atmosphere
1.
Mobilizati 1.1.1. Ensure the access and egress are not
obstructed.
on
1.1.2. All unwanted material must be removed
1.1. Slips, trips
tools/equi from site.
& Falls, 1.1.3. Maintain comfortable body position Supervisor
pment, Bodily injury B 2 2B B 1 1B
falling 1.1.4. Ensure all hand tool are secured by Workers
remove lanyard when working at high and
object
insulation platform.
1.1.5. Ensure barricaded and warning sign are
and set working area and ground floor
up fire 2.1. Boom truck, Burn injury / C 2 2C 2.1.1. All vehicle & Equipment’s must be NSRP C 1 1C Task
forklift hit property damage. inspected & have a valid sticker. supervisor /
blanket worker,
onto 2.1.2. Only trained and authorized operator/ boom
Normally Work/Job shall be allowed to start if the Risk after applying control measures equal or smaller/less than “Moderate” as per “04-HSE-HS-PD-022; Hazard
Identification, Risk Management and Control Procedure”
PEC TECNICIAN
Prepared by Work Execution PIC PEC
LEADER
x Electricity x Weather □ Excavations/Earthworks x Struck – by, against boom truck & forklift.
x Hot/Cold surface □ Insect/Animal Bites x Fire/ explosion □ Contact with
x Rotating Equipment □ Lighting □ Pyrophoric material □ Contacted by
Collision of vehicles,
□ x Driving Hazards □ Harm to Flora/Fauna □ Caught – in, on, under, between, against
equipment
x Muscular Stress x Falling Objects □ Pyrophoric deposit □ Exposure – temperature, chemicals, noise, dust
□ Mental Stress x Noise □ Inert atmosphere x Slip, Trip or Fall – from heights, same level
□ Repetitive Work □ Radiation x Spills/Leaks □ Complete Manual Handling Risk Assessment attached
x Heights □ Hydrocarbon/Gas Release □ Other Mobile/Stationary/Equipment x Overexertion/Excessive force – lifting, pushing, pulling,
□ Underground facility □ Open edge x Pressure (Stored Energy) □ Escape of Material – oil spill, gas release, light spill
□ Vibration x Tools/Equipment Failure x Fumes/Vapor/Dust □ Human Factors
□ Depths □ Human Factors □ Catalyst □ Overload of lifting equipment
□ Confined Spaces □ Off Road □ Toxic gas □ Suspended load
□ Asbestos □ Chemicals □ Trip process □ Crane/ boom truck collapse
(B) Personal Protective Equipment
x Eye/Face protection x Hearing protection x Respiratory protection x Weather conditions
x Head protection □ Safety/Rescue line □ Safety harness • hot/dry
• wet
x Foot protection x Hand protection x Gas detector • windy
• cold
□ Body protection x Spill prevention and clean up □ Light shields
□ Other □ □
Discussions / Feedbacks (Be specific on what is the output of SWMS/JSA meting and update required in SWMS/JSA)
1.0 Scope 1.1 Cutting, welding for repair leakage at flange and alignment for piping warm up line at 023-P-605B
MD-04-HSE-HS-PD-003 Rev 09 PTW Procedure
MD-04-HSE-HS-PD-012 Rev 03 Lock Out Tag Out Procedure.
MD-04-HSE-HS-PD-004 Rev 03 Job Safety Analysis (JSA) and Safe Work Method Statement (SWMS).
2.0 References 2.1
MD-04-HSE-HS-PD-048 Rev 02 Hot work Procedure
MD-04-HSE-ES-PL-007 Waste Management Plan.
MD-04-HSE-HS-PD-059 Rev. No.00 Manual Handling Procedure
NSRP HSSE PIC
3.0 Responsibilities 3.1
Periodic check to ensure Contractor personal attended fully training and qualified for these jobs.
To ensure all related HSSE document are at place for implement work safety.
Supervise the site work activity and ensure Contractor are conduct work safety follow HSSE procedure.
NSRP Supervisor.
Develop this SWMS and JSA and review periodically to update the requirement to follow procedure.
To ensure Contractor check the site condition carefully and apply control measure to minimize risk.
PTW Requester.
To prepare and understand the SWMS and JSA documents
To prepare tool, equipment, material and check actual conditions on the site
To prepare PTW documents
PTW Issuer.
To review SWMS and JSA and ensure Contractor apply adequate countermeasure to control all associated
hazards.
To apply and control the PTW system "SIMOPS" to control work safety.
Hand tools, grinder, cutting machine, welding machine, generator, DB box, boom truck, forklift, fire extinguisher,
4.0 Equipment / Tools 4.1
argon cylinder
5.0 Materials 5.1 Guide, shim plate, pipe, cutting/ grinding disc welding rod,
Resources (Manpower
6.0 6.1 PEC Supervisor, Workers,
& others)
Work steps:
7.0 Work Steps 7.1
1. Mobilization tools/equipment, remove insulation and set up fire blanket
2. Use plant power / generator to perform jobs
3. Cutting and prepare surface by grinding machine
4. Fit up and weld for piping, guide, shim plate.
Manual Handling.
Pinch points.
Fire Hazard
Electric shock
8.0 Safety 8.1
SWMS and JSA shall be discussed in START meeting.
Access ways must be cleared from obstructions and marked clearly where possible.
Heavy loads by manual one person not excess of 40 kg
Body parts should not be in line of fine.
PTW, JSA, SWMS, PLOT PLAN, P&ID, Hot work check list, Hot work certificated, Cold work certificated,
10 Attachment 10.1
Isolation certificated