HV CIVIL-MEP Work Activity and Plan 13-Oct-2022
HV CIVIL-MEP Work Activity and Plan 13-Oct-2022
HV – Civil Activities
1. Final coat of painting works in Plant Manager room (33KV Building)
2. Marble fixing for staircase-1 (33KV Building)
3. Staircase Handrails fixing (33KV Building)
4. Interlock tiles fixing for walkway around (33KV Building)
5. Housekeeping for Combo roof top coat painting works (33KV Building)
6. Fixing of kitchen cabinet (33KV Building)
7. Tapping and jointing works for false ceiling (Visitor center building)
8. Floor tiles fixing in staff room (Visitor center building)
9. Floor tiles fixing in Corridor Area (Visitor center building)
10. Interlock tiles fixing for walkways around (Visitor Center Building)
11. Epoxy painting works on ramp area (Workshop & Storage Area)
12. Tiles fixing in wet areas (workshop building)
13. Interlock tiles fixing for walkways (workshop building)
46. Concrete casting for chain link fence Foundations (Capacitor Bank)
47. Placement of precast cover slabs
48. Epoxy painting works on trenches in (Capacitor Bank Extension)
49. concrete for tie beams of chainlink fence (Capacitor Bank)
50. Backfilling works around foundations (Capacitor bank Extension)
51. Fixing of Gates for chainlink fence (Capacitor Bank)
52. Mesh Fixing for Chainlink fence foundations (Capacitor Bank)
53. Gravel filling
MEP Activities:
1. Duct Installation Works in (workshop Building)
2. Cable tray & Trunking (Workshop Building)
3. fire pump room switch & socket fixing
4. HV Area Earthing Works
5. Fire Sealant Works (Visitor center)
6. External Plumbing Works (Storm water/Drainage Etc.)
7. External cable pulling work near capacitor bank area to 33 kv building
8. installation of FAHU at Visitor Building chiller yard
9. Firefighting PIPE INSTALLATION & Supports Installation of final fix (33KV building)
10. Cable pulling for EMERGENCY LIGHT in (Gate house)
11. Glading & termination (Visitor building)
12. fire pump room External wall light fixture
13. installation of FM200 Detector & Nozzle devices in 33 KV switch gear building & admin building
Relay protection room below raised Floor
14. Installation of VESDA system
15. Functionality test & sequence of operation for FM200 system in 33 KV switch gear building & admin
building Relay protection room
16. Cable termination and ducting works (Chiller Yard)
17. Cable termination and ducting works (workshop & Storage Building)
18. installation of Exhaust fan along with ducting, necessary dampers & accessories at Workshop
building roof
19. installation of Exhaust fan at Workshop building roof
20. installation of fan control panel along with cable glanding & termination in Fire pump room roof
21. mock up installation of urinal in 33 kv building male toilet
22. mock up installation of Janitor sink in 33 kv building male toilet
23. mock up installation of WC in 33 kv building male toilet
60. Tapping and jointing for false ceiling system (Visitor center Building)
61. Floor Tiles fixing in conference room (Visitor center building)
62. Painting works on walls (Visitor center building)
63. Floor tiles fixing in VIP Lounge and corridor area (Visitor center building)
64. Painting works on walls (Visitor center building)
65. Epoxy painting works on ramp areas (Workshop & Storage Building)
66. Tiles fixing works in (workshop & Storage Building)
67. Completion of grid installation for false ceiling works (Guard House)
MEP Activities:
11. Installation of portable water tank (Near Pump Room)
12. Cable tray & Trunking (Visitor center & Workshop Building)
13. Main cable Pulling for HVAC (Visitor Center & Workshop Building)
14. Conduiting & Box Fixing (Workshop & Storage Building)
15. HV Area Earthing Works
16. Fire Sealant Works (33KV Building & visitor center building)
17. External Plumbing Works (Storm water/Drainage Etc.)
18. Fire Alarm Works (Transformer-3)
19. Installation of GRP water tank (Gate House)