Professional Documents
Culture Documents
Demolition RISK Assessment
Demolition RISK Assessment
Demolition RISK Assessment
Demolition plan
1. Unsafe Access/Egress
2. Lack of Planning and site Information.
3. Pre mature collapse/ collapse.
4. Erection and dismantle by incompetent person
5. Collapse of Scaffolding structure
6. Striking buried services.
7. Flooding.
8. Loading/Unloading (Lifting).
9. Collapse of adjacent structures.
10. Work at height.
11. Confined space.
12. Fire.
13. Defective Plant and machinery.
14. Movement of vehicles.
15. Noise and Vibration.
16. Manual Handling.
17. Biological hazard.
18. Slips trips and falls.
19. Hazardous substances.
20. Sharp objects.
21. Welfare facilities.
22. PPE.
Method Statement for
Demolition plan
CONSEQUENCE
1 2 3 4 5
A – Almost Certain
MODERATE HIGH EXTREME EXTREME EXTREME
> 1 per week
11 16 20 23 25
(>25%)
B – Likely
MODERATE HIGH HIGH EXTREME EXTREME
1/week – 1/month
7 12 17 21 24
(10-25%)
C – Possible
LIKELIHOOD
D – Unlikely
LOW LOW MODERATE HIGH HIGH
1/year – 1/10 years
2 5 9 14 19
(0.1-1%)
1 3 6 10 15
< 1/10 years
Method Statement for
Demolition plan
(0.1%)
RESIDUAL RISK
RESULT CONTROL LEVEL
RATING
(Authority)
(after controls in place)
TOLERABILITY CRITERIA
1 Access/ Egress Unsafe access/egress to worksite General workers, site 4 4 16 Mandatory PPE must be worn at site. 4 1 4
may lead to personnel injury and staff, members of the
TD induction completion.
property loss. public.
Driving with due care & attention.
Adherence to site safety signage
Never block access and egress routes
with materials and equipment.
Site tidiness maintained by cleaning up
during work, at end of day and(major)
weekly to avoid slips and trips – Clean
as you go.
No protruding nails allowed: all such
nails must be clawed out or hammered
flat so as to foot injuries.
Method Statement for
Demolition plan
3 Pre- mature Crushing injury, asphyxiation. General site Workers, site 5 4 20 Structural surveys to assess the 5 1 5
collapse/ collapse Pinch in of sharp objects, staff, site visitors and strength and stability of the structure
during demolition Financial loss equipment operators. and adjacent structures.
Careful assessment and planning of the
work to eliminate hazards.
Inspection should be done frequently.
Method Statement for
Demolition plan
maintained.
Frequent rest breaks should be
provided for the persons working in the
confined space.
Safety signages should be posted.
Fire Extinguishers should be available
at worksite.
Ground conditions established by a
survey to identify the type of ground in
which the excavation is to be carried
out; means of trench support
confirmed upon completion of trial
holes.
Permit should be obtained for
Excavation.
Remember that even work in shallow
trenches can be dangerous.
Provision of support if the work
involves bending or kneeling in the
trench.
No one should be in the trench unless
Excavation for different utilities it is safe to be there.
General workers, site
can result in cave in, people fall Where possible ensure that all water
14 Excavation staff, site visitors, 5 4 20 5 1 5
in, material fall in can cause sources are turned off before entering
multiple injuries asphyxiation members of the public. an excavation.
All the PPE must be worn at the site.
Safe Access and Egress should be
provided during the activity.
Do not go into unsupported
excavations that have not being
battered to a suitable slope.
Wall of the excavation should be
Excavation Safety shall be briefed to all
of the person involved.
Never work ahead of the support.
Regular inspection of the Excavations.
Inspection of adjacent structures,
buildings and stationary items.
Method Statement for
Demolition plan