Demolition RISK Assessment

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 15

Method Statement for

Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T

1 Risk Classification Scheme

The following risk assessment is aligned to the requirements of RAC.

1.1 Hazard Consequences.

Level Descriptor Health & Safety Environment

Massive pollution with significant


Multiple fatalities or multiple
recovery work lasting more than 12
5 Catastrophic permanent disabling injuries
months. Global media interest.
or disease.
Significant permanent damage.

Significant pollution with offsite


Fatality or permanent impact and recovery work requiring
4 Major disablement from injuries or 6 – 12 months to fix. Some
disease. Long term absence. permanent damage. National and
regional media interest

Life threatening injury/major Pollution with some offsite impact


health affect to individual and recovery work lasting 1 – 6
3 Serious requiring medivac to hospital months. Possible outside assistance
facilities. Short term absence required to contain. Some local
from work. media interest

Injury and illnesses requiring Minor pollution, slight or negligible


treatment by medically impact, negligible remedial /
2 Medium
qualified person. Complete recovery work lasting less than 1
recovery. No lost time. month. Full recovery possible.

Injury which may or may not


require first aid treatment. Minimal pollution affect contained
1 Minor Slight health effect not locally. Complete recovery possible
affecting performance or immediately.
causing absence.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T

1.2 Hazard Probability

Level Descriptor Health & Safety Environment

5 Almost > 1 per week


Continuous or will happen frequently
Certain >25%

4 1 per week – 1 per month


Likely 5 – 12 times per year
10-25%

3 1 per year – 1 per years


Possible 1 – 5 times per year
1-10%

2 1 per year – 1 per 10 years


Unlikely Once every 5 years
0.1-1%

1 < 1/10 years


Rare Less than once every 5 years
0.1%

2. Risk Classification, Mitigation and Calculation of Residual Risk


The following table details standard construction risks that are applicable to working at the
Metro link project site and that are valid for this activity:
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
2.2 Hazard Identification:
The following hazards were identified for this activity:

1. Unsafe Access/Egress
2. Lack of Planning and site Information.
3. Pre mature collapse/ collapse.
4. Erection and dismantle by incompetent person
5. Collapse of Scaffolding structure
6. Striking buried services.
7. Flooding.
8. Loading/Unloading (Lifting).
9. Collapse of adjacent structures.
10. Work at height.
11. Confined space.
12. Fire.
13. Defective Plant and machinery.
14. Movement of vehicles.
15. Noise and Vibration.
16. Manual Handling.
17. Biological hazard.
18. Slips trips and falls.
19. Hazardous substances.
20. Sharp objects.
21. Welfare facilities.
22. PPE.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
3.3 Risk level Matrix

CONSEQUENCE

1 2 3 4 5

Minor Medium Serious Major Catastrophic

1st Aid MTI RWI LTI Fatality

First Aid Injury Medically Restricted Lost Time Injury


Treated Work Injury
Injury SAR100k –
SAR20k – SAR500k
1 < SAR10k SAR10K - SAR100k > SAR500k
SAR20k

A – Almost Certain
MODERATE HIGH EXTREME EXTREME EXTREME
> 1 per week
11 16 20 23 25
(>25%)

B – Likely
MODERATE HIGH HIGH EXTREME EXTREME
1/week – 1/month
7 12 17 21 24
(10-25%)

C – Possible
LIKELIHOOD

LOW MODERATE HIGH HIGH EXTREME


1/month – 1/year
4 8 13 18 22
(1-10%)

D – Unlikely
LOW LOW MODERATE HIGH HIGH
1/year – 1/10 years
2 5 9 14 19
(0.1-1%)

E – Rare LOW LOW LOW MODERATE HIGH

1 3 6 10 15
< 1/10 years
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T

(0.1%)

RESIDUAL RISK
RESULT CONTROL LEVEL
RATING
(Authority)
(after controls in place)
TOLERABILITY CRITERIA

EXTREME Unacceptable Fahad Al Malki

HIGH Undesirable Construction Manager

Tolerable, but risk should be reduced if


MODERATE Site Coordinator, Site Engineers
reasonably practical

LOW Broadly acceptable Site supervisors, Forman


Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T

4. Risk analysis and risk assessment sheets

Risk Classification, Mitigation and Calculation of Residual Risk


The following table details standard construction risks that are applicable to working at the Metro link TR01 & TR02 site and that are valid for this activity:

4.1 Risk Assessment

Initial Risk Resultant Risk Rating


Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

1 Access/ Egress Unsafe access/egress to worksite General workers, site 4 4 16  Mandatory PPE must be worn at site. 4 1 4
may lead to personnel injury and staff, members of the
 TD induction completion.
property loss. public.
 Driving with due care & attention.
 Adherence to site safety signage
 Never block access and egress routes
with materials and equipment.
 Site tidiness maintained by cleaning up
during work, at end of day and(major)
weekly to avoid slips and trips – Clean
as you go.
 No protruding nails allowed: all such
nails must be clawed out or hammered
flat so as to foot injuries.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 2 Routes delineated with barriers;


barriers secured with sandbags where
necessary
 Excavations backfilled as soon as
possible
 Barriers erected around unattended
excavations Access to the site must be
controlled to ensure the safety of site
employees and visitors.
 Ensure all plant is secured against
unauthorized operation; removed the
keys & prevent access to the cabin.

 All the activities should be planned and


Risk assessments should be briefed to
all personnel.
 All visitors and now workers shall be
safety inducted before entering to the
Personnel injury/financial loss actual worksite.
Lack of planning and General workers, site
2 may happen due to lack of 4 3 12  Safety signage shall be posted to the 4 1 4
Information staff site visitors.
information and planning. site.
 TBTs shall be conducted on regular
basis.
 Unauthorized entry shall not be
permitted to the worksite and shall be
controlled by access controller.

3 Pre- mature Crushing injury, asphyxiation. General site Workers, site 5 4 20  Structural surveys to assess the 5 1 5
collapse/ collapse Pinch in of sharp objects, staff, site visitors and strength and stability of the structure
during demolition Financial loss equipment operators. and adjacent structures.
 Careful assessment and planning of the
work to eliminate hazards.
 Inspection should be done frequently.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 Prevent unauthorized entry to the


workplace by installing hard barriers.
 competent scaffolding supervisor shall
 Scaffold collapse
General site Workers, be appointed
Erection/dismantle Personal injury due to falls
 Only competent personnel shall be
and impact of falling
4 of scaffold by site staff, 4 4 16 permitted to erect / dismantle scaffold 4 1 4
objects
incompetent person  Competence requirements shall be in
Damage due to falling
Site visitors, line with the Metro Link Project
objects leading to
requirements.
financial / production loss.
 Area should be barricaded.
 Scaffold shall be designed to meet
loading and stability requirements.
Heavy duty scaffold designs shall be
submitted for review and approval
Personal injury due to falls General site Workers, (Heavy duty shall be those designed for
and impact of falling loading in excess of 240 Kg/m2
Collapse of scaffold
5 objects site staff, 4 4 16 (2.4kN/m2). Light duty scaffold shall be 4 1 4
structure.  Damage due to falling up to 120Kg/m2 and medium duty up
objects leading to Site visitors, to but not exceeding 240 Kg/m2).
financial / production loss.  Scaffold shall be designed to resist
adverse environmental conditions such
as high winds.
 Scaffold shall b erect at firm place.
 Exclusion zone should be maintained.
6 Work at height Personnel fall, material fall General site workers, site 5 4 20  Identify leading edges. 4 1 4
from height. staff and site visitors.  Install signage and illumination /
lighting where necessary to highlight
and warn of hazard.
 Install edge protection (ideally
guardrails at 1m with mid-rail and toe-
boards).
 Ensure fall protection is provided for
those installing guardrails.
 Install crash decks over entrances /
access routes where there the risk of
falling objects is significant.
 Fall protection / prevention shall be in
line with the requirements of RAC
Metro link project.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 Full body harness shall be used for


work at height activity.
 Safe working platform shall be
provided for the workers.
 TBTs shall be conducted about work at
height safety.
 Al the lifting equipment and lifting
accessories should be third party
certified.
 Third party certified operator and rigger
should do the lifting operations.
Collision with other stationary  Lifting plan should be submitted.
objects, fallen of the lifted load General workers, site  Exclusion zone should be maintained.
7 Lifting operations and equipment failure may staff members of the 5 4 20  Flagman should be appointed. 5 1 5
happen while performing lifting public.  Safety Signage should be posted.
operations can lead to personnel  Daily Equipment Inspection should be
injury/financial loss. conducted by the operator and
Checklist of the equipment should be
updated.
 TBTs and In-House trainings for safe
Lifting Operations should be conducted.
 Safety Signage should be installed.
 Avoid manual handling where
applicable.
 Use Engineering control (e.g. use of
Ligament strains, handling aids trolleys etc.
Muscle strains, Fatigue General workers/logistic  Asses the workers physical condition is
8 Manual Handling 4 3 12 suitable for manual handling or not. 4 1 4
Abdominal hernias team  TBTs shall be conducted about Manual
Prolapsed/herniated discs, and handling.
Paralysis  Manual handling should not exceed for
the material weighing more than 20KG.
 In-house training about manual
Handling shall be conducted.
9 Striking buried Electrocution, fire, and rapid General site workers, site 4 4 16  Careful Survey of the underground 4 1 4
services flooding may occur by hitting the staff, members of the utilities by calibrated and certified
underground services. survey equipment.
public  Operators and surveyors should be
competent.
 Work permit should be obtained from
the concerned department.
 All the underground utilities should be
clearly marked.
 All the underground utilities should be
disconnected in the worksite area.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 Path should be changed if utilities


cannot be disconnected.
 Safety Signage shall be posted at
worksite.
 TBT shall be conducted about the
Excavation Safety.
 Permit should be obtained from the
authorities.
General workers, site  All the underground utilities should be
10 Rapid Flooding Rapid flooding may occur due to staff, site visitors, 4 3 12 marked. 4 1 4
striking to underground utilities. members of the public.  All the underground utilities should be
disconnected.
 Submersible pumps should be
available.
 For all the critical activities including
HOT work a permit to work must be
obtained prior to start of the activity.
 For hot work activity area shall be free
of any flammable material.
 If a flammable material cannot be
removed shall be covered with fire
blanket.
 All the equipment including grinders,
speed cutters, welding machines shall
be in good condition and with all the
applicable guards.
Performing cutting, grinding and General workers, site
 Only trained operators shall perform
11 Fire welding may lead to fire and staff, site visitors, general 5 4 20 5 1 5
hot Work activity.
result in burn, fire and multiple public.  Firefighting equipment including fire
injuries.
extinguishers, hose reel and sand
buckets shall be at site.
 TBT shall be conducted about the fire
safety.
 Fire watcher shall be appointed.
 All the Additional PPE including face
shield, leather apron, and leather
gloves and welding face shield required
for hot work shall be worn along with
mandatory PPE as required.
All the Emergency access routes shall
be kept free from any obstruction.
12 Electrical Multi Personnel injuries may General Workers, site 5 4 20  All the Electrical Installations e.g. 5 1 5
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

electrical rooms must be secured and


should not have access for any
unauthorized personnel.
 All the Electrical Installations and
power sockets and cable drums must
be in good condition.
 All the electrical tools and equipment
must be inspected regularly by a
staff, visitors and general competent electrician.
public.  All the electrical cables must be
occur if exposed to live electrical
secured and free from any defects and
source.
wear and tear.
 RCDs should be installed.
 No faulty cable should be used.
 Only three pin plug should be used for
electrical l connections.
 Lock out Tag out system should be
implemented for any repairing activity.
 Electrical Hazards signs shall be posted.
 TBT shall be conducted about electrical
Hazard.
13 Confined Space Toxic Atmosphere, Oxygen Workers, site staff, 5 4 20  Activity should be properly planned 5 1 5
deficiency, Oxygen enrichment, visitor. before start.
presence of flammables, and  A permit to work should be
difficulty in rescue operations implemented for that critical activity.
may lead to multiple injuries to  All the personnel in the team should be
the personnel. trained for the confined space activity.
 Trained Top man should be appointed
for the activity.
 Emergency rescue measurements
should be taken including, tripod,
stature, etc.
 Gas test should be done (if applicable).
 Ventilation and lighting measurements
should be taken.
 Safe access/egress should be provided
for the personnel.
 Area should be secured from any
unauthorized entry.
 Confined space entry/exit log should be
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

maintained.
 Frequent rest breaks should be
provided for the persons working in the
confined space.
 Safety signages should be posted.
 Fire Extinguishers should be available
at worksite.
 Ground conditions established by a
survey to identify the type of ground in
which the excavation is to be carried
out; means of trench support
confirmed upon completion of trial
holes.
 Permit should be obtained for
Excavation.
 Remember that even work in shallow
trenches can be dangerous.
 Provision of support if the work
involves bending or kneeling in the
trench.
 No one should be in the trench unless
Excavation for different utilities it is safe to be there.
General workers, site
can result in cave in, people fall  Where possible ensure that all water
14 Excavation staff, site visitors, 5 4 20 5 1 5
in, material fall in can cause sources are turned off before entering
multiple injuries asphyxiation members of the public. an excavation.
 All the PPE must be worn at the site.
 Safe Access and Egress should be
provided during the activity.
 Do not go into unsupported
excavations that have not being
battered to a suitable slope.
 Wall of the excavation should be
 Excavation Safety shall be briefed to all
of the person involved.
 Never work ahead of the support.
 Regular inspection of the Excavations.
Inspection of adjacent structures,
buildings and stationary items.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 Site should be inspected and surveyed


General workers, site before start of the activity.
During demolition can also effect
adjacent structures and buildings staff, Visitors  All the adjacent structures shall be
Collapse of adjacent
15 that can result in collapse of the 4 4 16 regularly inspected. 4 1 4
structures adjacent structures and lead to Members of the public.  Excavation and demolition of
personnel injury and property structures should be planned.
loss.  All the Mandatory PPE must be worn

 Workplace tidiness maintained by


cleaning up during work, at end of day
to avoid slips and trips – Clean as you
go.
 Vigilance from employees as to the
Workers, site staff, dangers from slips trips and falls.
16 Slips, Trips & Falls Cuts and bruises, Laceration and Visitors and members of 3 3 9  Designated a team for housekeeping. 3 1 3
Serious bodily injury. the public  Awareness Signage shall be posted.
 Access/Egress should always clear from
obstructions.
 All the access routes should well
maintained lit and tidy.
 All the Mandatory PPE must be worn at
all times at the site.
17 Dust, Noise,  Construction dust can Workers, Site staff, 4 3 12  Dust suppression measures like water 4 1 4
Vibration and cause lung cancer, visitors and members of sprinkling should be done regularly.
Biological hazards. asthma, Chronic the public.  Dust mask e.g. N-95 should be worn at
Obstructive Pulmonary worksite specially exposed areas to
Disease (COPD) and dust.
silicosis.  Workers shall be briefed in TBTs about
 High noise more than dust, noise, vibrations and biological
limit 85 dBA can cause hazards.
hearing loss.  Full body Coverall shall be used for
 Continuous exposure to asbestos related activity.
the vibrations can lead
 Ear plug should be used for the areas
to blood vessels, Hand
exposed to the high noise i.e. more
Arm Vibration Syndrome
than 85 dBA.
(HVAS).
 Equipment should me in good
 Stagnant water can
condition and free from any defects.
cause mosquitoes, fungi
and other harmful  Sound guards should be installed if
biological practicable.
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

 Job rotation shall be implement for the


continuous vibration related activity.
 Faulty equipment should be replaced.
microorganisms.  Removal of stagnant water
immediately from the site.
 All the Mandatory PPE must be worn.
 Safety awareness signage shall be
installed.
 All the equipment procured should be
in good condition.
 Plant and equipment should be 3rd
party certified.
 All the operators of plant & equipment
should be 3rd party certified.
 Daily inspection should be carried out
by operators and should be verified by
supervisors/safety officer.
Hit to the adjacent structures,  Plant and Equipment should run at safe
Movement/working Workers, supervisors,
18 persons working. Unauthorized 5 4 20 distance from adjacent structures. 5 1 5
Plant and Equipment visitors.
operators. Working faulty  Exclusion zone should be maintained.
equipment,  Trained Flagman should be appointed
with the equipment.
 Yellow Beacons should be installed at
the equipment.
 Only suitable equipment should be
used for the task.
 Warning signs should be posted across
the site.
 TBT should be conducted about MEPI
hazard.
19 Flying Objects During Demolition Flying objects General workers, Site 5 4 20  Exclusion zone shall be maintained for 5 1 5
can hit the personnel and may Staff, Visitors and general the activity.
cause multiple injuries. public  Unauthorized entry shall be prevented.
 Tools and equipment shall be used in
good condition.
 Mandatory PPE must be worn at all the
time.
 Only designated routes should be
Method Statement for
Demolition plan

Orig. P.O Div Type Disc Number Rev


Issue Date: 17/08/2021 TD 1892 Q MST ME 0002 00 Revision Date:
T
Initial Risk Resultant Risk Rating
Hazard Potential ES&H Effects Affected Proposed Control Measures Likelihoo
#
Severity Likelihood Result Severity d Result

followed for access/Egress.


 Safety net should be installed to block
the flying objects.
 Only certified and trained Operators
should perform the activity.
 Safety Signage shall be posted at
workplace.
General workers, site
 Welfare facilities should be provided
Unavailability of welfare facilities
20 Welfare facility 3 3 9 for the personnel reasonably 3 1 3
may result in diseases and health staff, visitors.
practicable including, drinking water,
problems to the personnel.
rest area, washing facility.
 Only standardized ANSI or ASTM
approved PPE should be used.
 Damaged PPE must be replaced.
General workers, site
21 PPE Unavailability of damaged PPE 3 3 9  Wear all the mandatory PPE at all the 3 1 3
may lead to personnel injury. staff, Visitors
times at worksite.
 Wear all the Additional PPE as per job
requirement.
 Store the PPE at safe area after use.

You might also like