Biaya Reklamasi Tambang Baramarta (End of June 2009)

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 3

ACCRUE BIAYA REKLAMASI PER AKHIR JUNI 2009 - BLOK BARAMARTA (PIT SELATAN)

PTD PTD PTD PTD BIAYA YANG DIBUTUHKAN UNTUK REKLAMASI TAMBANG (USD/HA) TOTAL
End of End of End of End of ACCRUE
NO PERUNTUKAN LAHAN SAT. RESHAP. TOP SOIL. PLANTAT. PEMELIH.
April October Dec- Jun- BIAYA
2008 2008 2008 2009 @/Ha Amount @/Ha Amount @/Ha Amount @/Ha Amount REKLAMASI
1 Jalan/access road Ha 13.58 14.84 14.91 14.91 0 US$
2 Settling Ponds Ha 3.36 3.36 3.36 3.36 0 US$
3 Gudang Handak/Magazine Ha 5.6 5.6 6.17 6.17 0 US$
4 Pit Stop Ha 0.87 0.87 0.82 0.82 1,440 1,181 US$ 3,900 3,198 US$ 362 297 US$ 181 149 US$ 4,825 US$
5 Direksi Keet Ha 0.39 0.39 0.73 0.73 1,440 1,051 US$ 3,900 2,847 US$ 362 264 US$ 181 132 US$ 4,295 US$
6 Main Sump Ha 0.61 0.61 0.81 0.81 0 US$
7 Pos Security/Portal Ha 0.5 0.5 0.52 0.52 1,440 749 US$ 3,900 2,028 US$ 362 188 US$ 181 94 US$ 3,060 US$
8 Reklamasi & Re_vegetasi Ha 88.73 88.73 88.73 88.73 0 US$
9 Stock Top Soil Ha 3.13 3.87 4.06 4.06 1,440 5,847 US$ 3,900 15,834 US$ 362 1,471 US$ 181 736 US$ 23,888 US$
10 Pit Aktif (70%) Ha 15.3 11.66 11.81 11.81 1,440 11,906 US$ 3,900 32,241 US$ 362 2,995 US$ 181 1,498 US$ 48,641 US$
11 Outpit Dump Aktif (75%) Ha 16.86 20.26 0 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$
12 Inpit Dump Aktif Ha 18.21 23.83 27.33 27.33 1,440 36,260 US$ 3,900 98,190 US$ 362 9,122 US$ 181 4,561 US$ 148,133 US$
13 Wash Pad Ha 0.56 0.56 0.25 0.25 0 US$
14 Sleep Area (85%) Ha 79.28 76.1 91.68 91.68 1,440 112,233 US$ 3,900 303,919 US$ 362 28,235 US$ 181 14,117 US$ 458,505 US$
TOTAL 246.98 251.18 251.18 251.18 169,228 US$ 458,258 US$ 42,573 US$ 21,287 US$ 691,346 US$
KETERANGAN :
-TOTAL OUTSTANDING BIAYA REKLAMASI = 691,346 Usd
-TOTAL LUASAN YANG SUDAH DIREKLAMASI = 88.73 Ha
-OUTSTANDING LUASAN YG HARUS DIREKLAMASI = 117.50 Ha
-BIAYA REKLAMASI PER HA = 5,884 Usd/Ha

Kab. Banjar , 29 Juni 2009


PT. Pamapersada Nusantara PT. Prima Multi Mineral

Pajar Wahyudi Akhyar Tafly


Engineering Dept. Head Engineering Dept. Head
ACCRUE BIAYA REKLAMASI PER AKHIR JUNI 2009 - BLOK BARAMARTA (PIT UTARA)
PTD PTD PTD PTD BIAYA YANG DIBUTUHKAN UNTUK REKLAMASI TAMBANG (USD/HA)
End of End of End of End of
NO PERUNTUKAN LAHAN SAT. RESHAP. TOP SOIL. PLANTAT. PEMELIH. TOTAL
April October Dec- Jun-
2008 2008 2008 2009 @/Ha Amount @/Ha Amount @/Ha Amount @/Ha Amount
1 Jalan/access road Ha 20.49 24.89 19.47 40.31 0
2 Settling Ponds Ha 1.74 1.74 2.29 4.88 0
3 Gudang Handak/Magazine Ha 0 0 0 0 0
4 Pit Stop Ha 2.2 2.2 4.16 1.33 1,440 1,915 US$ 3,900 5,187 US$ 362 482 US$ 181 241 US$ 7,825 US$
5 Direksi Keet Ha 0.76 0.76 0.76 0.47 1,440 677 US$ 3,900 1,833 US$ 362 170 US$ 181 85 US$ 2,765 US$
6 Main Sump Ha 0.89 0.89 1.15 1.26 0 US$
7 Pos Security/Portal Ha 0 0 0 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$
8 Reklamasi & Re_vegetasi Ha 14.05 14.05 20.43 23.84 0 US$
9 Stock Top Soil Ha 11.65 14.16 14.96 12.06 1,440 17,369 US$ 3,900 47,034 US$ 362 4,370 US$ 181 2,185 US$ 70,957 US$
10 Pit Aktif (75%) Ha 53.77 52.59 58.22 49.71 1,440 53,695 US$ 3,900 145,402 US$ 362 13,508 US$ 181 6,754 US$ 219,359 US$
11 Outpit Dump Aktif Ha 70.7 91.35 92.8 109.72 1,440 158,021 US$ 3,900 427,908 US$ 362 39,754 US$ 181 19,877 US$ 645,559 US$
12 Inpit Dump Aktif Ha 18.05 23.17 26 32.26 1,440 46,461 US$ 3,900 125,814 US$ 362 11,688 US$ 181 5,844 US$ 189,808 US$
13 Wash Pad Ha 0 0 0 0 0 US$
14 Sleep Area (94%) Ha 18.57 36.36 37.45 76.03 1,440 102,930 US$ 3,900 278,726 US$ 362 25,894 US$ 181 12,947 US$ 420,497 US$

TOTAL 212.87 262.16 277.69 351.87 381,068 US$ 1,031,904 US$ 95,866 US$ 47,933 US$ 1,556,771 US$

KETERANGAN :
-TOTAL OUTSTANDING BIAYA REKLAMASI = 1,556,771 US$
-TOTAL LUASAN YANG SUDAH DIREKLAMASI = 23.84 Ha
-OUTSTANDING LUASAN YG HARUS DIREKLAMASI = 264.58 Ha
-BIAYA REKLAMASI PER HA = 5,884 US$/Ha
-RENCANA TOTAL LUAS DI REKLAMASI & RE_VEGETASI = 288 Ha

Kab. Banjar , 29 Juni 2009


PT. Pamapersada Nusantara PT. Prima Multi Mineral

Pajar Wahyudi Akhyar Tafly


Engineering Dept. Head Engineering Dept. Head
ACCRUE BIAYA REKLAMASI PER AKHIR JUNI 2009 - BLOK BARAMARTA (PIT BARAT)
PTD PTD PTD PTD BIAYA YANG DIBUTUHKAN UNTUK REKLAMASI TAMBANG (USD/HA) TOTAL
End of End of End of End of ACCRUE
NO PERUNTUKAN LAHAN SAT. RESHAP. TOP SOIL. PLANTAT. PEMELIH.
April October Dec- Jun- BIAYA
2008 2008 2008 2009 @/Ha Amount @/Ha Amount @/Ha Amount @/Ha Amount REKLAMASI
1 Jalan/access road Ha 1.65 2.69 3.25 3.07 0 US$
2 Settling Ponds Ha 0.45 0.98 0.98 1.25 0 US$
3 Gudang Handak/Magazine Ha 0 0 US$
4 Pit Stop Ha 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$
5 Direksi Keet Ha 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$
6 Main Sump Ha 0 0 US$
7 Pos Security/Portal Ha 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$
8 Reklamasi & Re_vegetasi Ha 0 0 US$
9 Stock Top Soil Ha 1.88 1.88 2.08 1.57 1,440 2,261 US$ 3,900 6,123 US$ 362 569 US$ 181 284 US$ 9,237 US$
10 Pit Aktif (75%) Ha 8.58 14.88 13.60 14.34 1,440 15,903 US$ 3,900 43,063 US$ 362 4,001 US$ 181 2,000 US$ 64,967 US$
11 Outpit Dump Aktif Ha 12.82 19.9 20.19 19.36 1,440 27,883 US$ 3,900 75,504 US$ 362 7,014 US$ 181 3,507 US$ 113,908 US$
12 Inpit Dump Aktif Ha 0 1.22 2.66 3.17 1,440 4,565 US$ 3,900 12,363 US$ 362 1,149 US$ 181 574 US$ 18,651 US$
13 Wash Pad Ha 0 0 US$
14 Sleep Area Ha 0 1,440 0 US$ 3,900 0 US$ 362 0 US$ 181 0 US$ 0 US$

TOTAL 25.38 41.55 42.76 42.76 50,612 US$ 137,053 US$ 12,733 US$ 6,366 US$ 206,764 US$

KETERANGAN :
-TOTAL OUTSTANDING BIAYA REKLAMASI = 206,764 Usd
-TOTAL LUASAN YANG SUDAH DIREKLAMASI = 0.00 Ha
-TOTAL LUASAN YANG BELUM DI REKLAMASI = 35 Ha
-BIAYA REKLAMASI PER HA = 5,884 Usd/Ha
-RENCANA TOTAL LUAS DI RE_VEGETASI = 35 Ha
Kab. Banjar , 29 Juni 2009
PT. Pamapersada Nusantara PT. Prima Multi Mineral

Pajar Wahyudi Akhyar Tafly


Engineering Dept. Head Engineering Dept. Head