Progress on PCIs

Cost
Sr. No. MC Name Consultant Sector Million
PKR

Roads  300
JERS
Vehicle Parking Shed 80
1 Jhelum
Water Supply  400
MMP
Street light 104
Water Supply 500
MMP
Street light 100
2 Wazirabad
Roads 400
JERS
Vehicle Parking Shed 70
Roads & Drainage system 1446
MMP Street light 95
3 Daska
Concrete Pavers in streets 81
JERS Vehicle Parking Shed 36
NESPAK Sewerage 3000
4 Hafizabad Roads 400
JERS
Vehicle Parking Shed 35
Roads & Drainage along
M/S JERS 232
roads
Water Supply  700
5 Muridke NESPAK Main GT roads along Storm
700
drainage
M/S JERS Vehicle Parking Shed 54
NESPAK Water Supply 387
6 Kamoke Roads 450
M/S JERS
Vehicle Parking Shed 80
M/S JERS Roads 528
Water Supply 500.00 
7 Jaranwala MMP
Sewerage 2300
M/S JERS Vehicle Parking Shed 85
MMP Water Supply 600
8 Gojra Roads 400
M/S JERS
Vehicle Parking Shed 80

M/S JERS Vehicle Parking Shed 80


9 Jhang
9 Jhang
MMP Sewerage 2100

Chowks 110
M/S JERS GBS 112
Vehicle Parking Shed 50
10 Kamalia
Water Supply 400
MMP
Sewerage 1400

M/S JERS Vehicle Parking Shed 75


11 Burewala
M/S Asian Roads 1574
Roads 610
M/S JERS
12 Vehari Vehicle Parking Shed 80
M/S Asian Water Supply 1000
Roads 700
M/S JERS
13 Bahawalnagar Vehicle Parking Shed 80
M/S Asian Water Supply 631
Roads 365
M/S JERS
Vehicle Parking Shed 82
14 Okara Concrete Pavers in streets 287
MMP
Sewerage 3250
Roads 255
M/S JERS
Vehicle Parking Shed 80
15 Khanewal Street light 100
MMP Water Supply 27
Sewerage 1600
M/s JERS Roads 400
M/S JERS Vehicle Parking Area 44
16 Kot Addu
MMP Sewerage 1000
Progress on PCIs
Planned
Targeted
submission of
Timeline for Competent
Status of PC-1 PC-I to
Submission of forum
Competent
PC-Is
forum
DDSC
Design under preparation 22-08-22 31/08/22
DDWP
PC-I under preparation 25.08.22 30/08/22
DDSC
Design under preparation 20.09.22 25/09/22
DDWP
PC-1 completed 15.07.22 15/08/22
Design under preparation 10.09.22 20/09/22 PDWP
PC-1 completed 05.09.22 10/09/22 DDWP
DDSC
PC-I under preparation 15.09.22 20/09/22
22.08.22 DDWP
PC-1 completed 05/09/22
PC-1 completed 02.09.22 20/09/22 PDWP
PC-1 completed 01.08.22 20/08/22 DDWP
PC-1 completed 01.08.22 15/08/22 DDWP
PC-I under preparation 22.08.22 05/09/22 DDC
Design, Cost estimate & Drawings Completed - - -
DDSC
PC-I under preparation 10.09.22 20/09/22
DDWP
PC-I completed 12.08.22 20/08/22

PC-1 submitted 27.07.22 01/08/22 DDSC

Design under preparation 10.09.22 15/09/22 PDWP 

Initial design & estimate finalized 02.09.22 10/09/22 PDWP

PC-1 submitted 15.08.22 22/08/22 DDWP


Initial design & estimate finalized. MC is finalizing T/W
25.08.22 05/09/22 DDSC
& OHT Sites
PC-1 finalized & wait for updation of MRS 30.08.22 10/09/22 DDSC
PC-1 finalized & wait for updation of MRS 02.09.22 08/09/22 DDWP
PC-1 already submitted for DDSC Submitted Submitted PDWP
Design under preparation 15.09.22 25/09/22 PDWP
Land has been demarcated, MC has been requested
- - -
to start procurement of land
Design under preparation 12.09.22 20/09/22 DDWP
PDWP
Design under preparation 10.09.22 17/09/22
DDSC
Design under preparation 30.09.22 06/09/22
Design under preparation 22.08.22 05/09/22 DDWP

Design Completed, Cost estimation under preparation 30.08.22 06/09/22 DDWP


MC has been asked to provide land inside Bund. MC
is trying to find out land as indicated by consultants in - - -
western area
PC-1 completed 22.07.22 05/08/22 DDWP
PC-1 completed 27.07.22 05/08/22 DDWP
PC-1 completed 27.07.22 05/08/22 DDWP
DDSC
Design under preparation 25.09.22 30/09/22
Land is available but MC has no funds for its
- - -
procurement

Design Completed, Cost estimation under preparation 05.09.22 10/09/22 DDWP

PC-1 completed 03.09.22 10/09/22 PDWP


PC-1 completed 05.09.22 10/09/22 PDWP
Design Completed, Cost estimation completed 22.08.22 05/09/22 DDWP
PDWP
Design under preparation 15.09.22 20/09/22
PDWP
PC-1 completed 30.08.22 05/09/22
PC-1 completed 30.08.22 05/09/22 DDWP
PC-1 completed 05.09.22 15/09/22 PDWP
PC-1 completed Submitted - DDSC
PC-1 completed 01.08.22 22/08/22 DDWP
DDSC meeting
PC-1 completed Submitted DDSC
was postponed
Govt Land is available. MC is trying to get
- - -
NOC/Lease from BOR.
PC-1 completed 15.07.22 01/08/22 DDSC
Design under preparation 02.09.22 07/09/22 DDWP
PC-1 completed 29.08.2022 05/09/22 DDWP
PC-1 completed 29.07.22 05/08/22 DDC
PDWP
Design under preparation 01.09.22 10/09/22
Design Completed, Estimation under process 07.09.22 15/09/22 DDSC
PC-1 completed 22.08.22 02/09/22 DDC
DC has promised to demarcate the land within One
- - -
week
PC-I Preparation Performance Guarantee,
Technical Bidding
Approval of Bidding Mobilization, and other
Scrutiny Procedure
Date Documents Activities

21-09-22 06-10-22 12-10-22 11-12-22 26-12-22


20-09-22 05-10-22 11-10-22 10-12-22 25-12-22
16-10-22 31-10-22 06-11-22 05-01-23 20-01-23
05-09-22 20-09-22 26-09-22 25-11-22 10-12-22
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
01-10-22 16-10-22 22-10-22 21-12-22 05-01-23
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
10-09-22 25-09-22 01-10-22 30-11-22 15-12-22
05-09-22 20-09-22 26-09-22 25-11-22 10-12-22
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
- - - - -
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
10-09-22 25-09-22 01-10-22 30-11-22 15-12-22

22-08-22 06-09-22 12-09-22 11-11-22 26-11-22

06-10-22 21-10-22 27-10-22 26-12-22 10-01-23

01-10-22 16-10-22 22-10-22 21-12-22 05-01-23

12-09-22 27-09-22 03-10-22 02-12-22 17-12-22


26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
01-10-22 16-10-22 22-10-22 21-12-22 05-01-23
29-09-22 14-10-22 20-10-22 19-12-22 03-01-23
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
16-10-22 31-10-22 06-11-22 05-01-23 20-01-23
- - - - -
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
08-10-22 23-10-22 29-10-22 28-12-22 12-01-23
27-09-22 12-10-22 18-10-22 17-12-22 01-01-23
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22

27-09-22 12-10-22 18-10-22 17-12-22 01-01-23


- - - - -

26-08-22 10-09-22 16-09-22 15-11-22 30-11-22


26-08-22 10-09-22 16-09-22 15-11-22 30-11-22
26-08-22 10-09-22 16-09-22 15-11-22 30-11-22
21-10-22 05-11-22 11-11-22 10-01-23 25-01-23

- - - - -

01-10-22 16-10-22 22-10-22 21-12-22 05-01-23

01-10-22 16-10-22 22-10-22 21-12-22 05-01-23


01-10-22 16-10-22 22-10-22 21-12-22 05-01-23
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
11-10-22 26-10-22 01-11-22 31-12-22 15-01-23
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
06-10-22 21-10-22 27-10-22 26-12-22 10-01-23
- - - - -
12-09-22 27-09-22 03-10-22 02-12-22 17-12-22

- - - - -

- - - - -
22-08-22 06-09-22 12-09-22 11-11-22 26-11-22
28-09-22 13-10-22 19-10-22 18-12-22 02-01-23
26-09-22 11-10-22 17-10-22 16-12-22 31-12-22
26-08-22 10-09-22 16-09-22 15-11-22 30-11-22
01-10-22 16-10-22 22-10-22 21-12-22 05-01-23
06-10-22 21-10-22 27-10-22 26-12-22 10-01-23
23-09-22 08-10-22 14-10-22 13-12-22 28-12-22

- - - - -
Commencement
Dates

25-01-23
24-01-23
19-02-23
09-01-23
14-02-23
04-02-23
14-02-23
30-01-23
14-02-23
14-01-23
09-01-23
30-01-23
-
14-02-23
14-01-23

26-12-22

09-02-23

04-02-23

16-01-23
30-01-23
04-02-23
02-02-23
#VALUE!
19-02-23
-
14-02-23
11-02-23
31-01-23
30-01-23

31-01-23
-

30-12-22
30-12-22
30-12-22
24-02-23

04-02-23

04-02-23
04-02-23
30-01-23
14-02-23
30-01-23
30-01-23
09-02-23
-
16-01-23

-
26-12-22
01-02-23
30-01-23
30-12-22
04-02-23
09-02-23
27-01-23