OFFICE BUILDING,CORE SHELL Workshop # 3_Adding Activities 26-Jul-21 11:57

Activity ID Activity Name Original Activity Type Calendar


Duration

OFFICE BUILDING,CORE SHELL 85 OB Calendar


MILESTONE 85 OB Calendar
M-1000 Issuance of NOA,NTP &P.O 0 Start Milestone OB Calendar
M-1010 Start of Contract Day 1 0 Start Milestone OB Calendar
M-1020 Kick Off Meeting 0 Start Milestone OB Calendar
M-1030 Ground Breaking Ceremony 0 Start Milestone OB Calendar
M-1040 Excavation Complete 0 Finish Milestone OB Calendar
M-1050 Concrete Topping Off 0 Finish Milestone OB Calendar
M-1060 Project Complete 0 Finish Milestone OB Calendar
PRE CONSTRUCTION 17 OB Calendar
General Requirements 17 OB Calendar
GR-1000 Securing Miscellaneous Permits 7 Task Dependent OB Calendar
GR-1010 Mobilization Works 6 Task Dependent OB Calendar
GR-1020 Construction of temporary facilities incl.utilities 7 Task Dependent OB Calendar
CONSTRUCTION 59 OB Calendar
Earthworks 24 OB Calendar
E-1000 Survey Works(Staking/layout) 1 Task Dependent OB Calendar
E-1010 Clearing/grubbing 3 Task Dependent OB Calendar
E-1020 Bulk/structural excavation 5 Task Dependent OB Calendar
E-1030 Hauling & Disposal 5 Task Dependent OB Calendar
E-1035 Manual Trimming 1 Task Dependent OB Calendar
E-1040 Backfilling/compaction 8 Task Dependent OB Calendar
Civil Works 50 OB Calendar
Sub Structure 29 OB Calendar
Footing Foundation 7 OB Calendar
SS-F-1000 Install formwork/rebar 5 Task Dependent OB Calendar
SS-F-1010 Concrete pouring 1 Task Dependent OB Calendar
SS-F-1020 Formworks stripping 1 Task Dependent OB Calendar
Footing Tie Beam 7 OB Calendar
SS-FTB-1000 Install formwork/rebar 5 Task Dependent OB Calendar
SS-FTB-1010 Concrete pouring 1 Task Dependent OB Calendar
SS-FTB-1020 Formworks stripping 1 Task Dependent OB Calendar
Page 1 of 2 TASK filter: All Activities
© Oracle Corporation
OFFICE BUILDING,CORE SHELL Workshop # 3_Adding Activities 26-Jul-21 11:57
Activity ID Activity Name Original Activity Type Calendar
Duration

Ground Floor 14 OB Calendar


SS-GF-1000 Subgarde preparation 1 Task Dependent OB Calendar
SS-GF-1010 Install underground utilities stubouts 2 Task Dependent OB Calendar
SS-GF-1020 Install vapor barrier&soil termite application 1 Task Dependent OB Calendar
SS-GF-1030 Install formworks/rebar 3 Task Dependent OB Calendar
SS-GF-1040 Concrete pouring at SOG 1 Task Dependent OB Calendar
SS-GF-1050 Install formwork/rebar_1st lift columns/RC Wall 5 Task Dependent OB Calendar
SS-GF-1060 Concrete pouring_1st lift columns/RC Wall 1 Task Dependent OB Calendar
Super Structure 27 OB Calendar
2nd Floor 15 OB Calendar
SS-2F-1000 Install scafolding system 3 Task Dependent OB Calendar
SS-2F-1010 Install formwork/rebar for slab 5 Task Dependent OB Calendar
SS-2F-1020 Concrete pouring at 2F 1 Task Dependent OB Calendar
SS-2F-1030 Install formwork/rebar_1st lift columns/RC Wall 5 Task Dependent OB Calendar
SS-2F-1040 Concrete pouring_1st lift columns/RC Wall 1 Task Dependent OB Calendar
3rd Floor 15 OB Calendar
SS-3F-1000 Install scafolding system 3 Task Dependent OB Calendar
SS-3F-1010 Install formwork/rebar for slab 5 Task Dependent OB Calendar
SS-3F-1020 Concrete pouring at 3F 1 Task Dependent OB Calendar
SS-3F-1030 Install formwork/rebar_1st lift columns/RC Wall 5 Task Dependent OB Calendar
SS-3F-1040 Concrete pouring_1st lift columns/RC Wall 1 Task Dependent OB Calendar
4th Floor 9 OB Calendar
SS-4F-1000 Install scafolding system 3 Task Dependent OB Calendar
SS-4F-1010 Install formwork/rebar/ for slab 5 Task Dependent OB Calendar
SS-4F-1020 Concrete pouring at 4F 1 Task Dependent OB Calendar
POST CONSTRUCTION 6 OB Calendar
PC-1000 Punchlisting Works 3 Task Dependent OB Calendar
PC-1010 Preparation & Submission of Close Out documents 3 Task Dependent OB Calendar
PC-1020 Demobilization Works 3 Task Dependent OB Calendar
PC-1030 Project Complete RFH 0 Finish Milestone OB Calendar