NUBI 2A PROJECT
DAILY ACTIVITY REPORT
MWPS Site Works
REPORTED DATE : 28‐Aug‐2011
CUT OF TIME : 6.00 PM (DAYSHIFT)

SAFETY MANPOWER WEATHER


DESCRIPTION TO DAY CUMM. NO. COMPANY SUM
Manhour 792 57624 1 TOTAL : SPU 6 6.00 PM Clear
CeRMAT 0 0 2 TOTAL : ENG/PJC 2
SAFETY STATUS

Nearmiss 0 0 3 EPC‐1 : PT Meindo Elang Indah 58 12.00 PM Clear


FAC 0 0 TOTAL : 66
RWDC 0 0 6.00 AM Clear
Material Damage 0 0 VESSEL/BARGE
Accident/Incident 0 0 NO. VESSEL/BARGE PAX/POB POSITION PURPOSE 12.00 AM Clear
SAFETY EVENT

HSE Induction 0 9 1 EB 507 202 / 250 MWPS Acc. Barge


Tool Box 1 54 2 Petrogas supply 01 16 / 20 MWPS AHT
Safety Talk 0 0 3 Pesut Mahakam 6 / 35 MWPS Crew Boat
HSE Drill 0 5 4 Logindo Sparrow 8 / 65 MWPS Crew Boat
HSE Observation 0 0 5 Elang Tangguh 101 8 / 50 MWPS Tug Boat
6 Surya Indah 7 / 25 MWPS Tug Boat
7 Surfer 201 4 / 20 MWPS Crew Boat
8 ASL Prima II 10 / 20 MWPS Tug Boat
9 Atlantic 9 ‐ / 50 Handil Crew Boat
10 Anggrek Bulan ‐ / 25 Handil Tug Boat

HIGHLIGHT ISSUE
Complete 7 of 8 anchor
AHT Petrogas having problem with the sling arrangement at winch during anchoring activity
Accident occurred at 17:30 at flowline mezzanine deck. Tip point finger of pipe fitter pinched by pipe wrench while doing spade reinstatement

ACTIVITY
NO. TO DAY ACTIVITY PROGRESS NO. TOMORROW PLAN
Night Shift 1 Continue anchoring job EB 507 
1 No Activity 2 Transfer material from tug boat to weather deck
3 Install scafolding at lower & mezzanine deck
4 Continue flushing remaining HHP flowline
Day Shift 5 Modification HHP flowline
1 Transfer material from tug boat to weather deck 6 Prepare hydrotest HHP flowline
2 Anchoring job EB 507 (7 of 8 completed) 7 Continue glanding at Choke Valve hydraulic panel
3 Install Padeyes for CP Guide Submerged Installation 8 Termination and glanding at TIT HP flowline (complete)
4 Install additional beam 16x45 9 Termination and glanding for PIT slot T2
5 Install 3 ea pipe support 10 Install support for ACS box and lighting cable tray
6 Flushing HHP flowline slot C, W, V, A2 & S
7 Install blind flange at slot C, W & A2
Install blind flange at slot C, W & A2
8 Install 2" HHP methanol line at slot U, S, R1, R2
9 Install spade at HHP flowline slot U
10 Install 10 ea thermowell at HHP flowline
11 Continue glanding at Choke Valve hydraulic panel
12 Termination and glanding at TIT HP flowline (complete)
13 Re‐tightening all transmitter cable gland
14 Pulling lighting cable

TYPE OF WORK PERMIT Night Shift Day Shift TYPE OF WORK PERMIT SUM


On Going Work Permit Hotwork Naked Flame 0 3 Planned  Hotwork Naked Flame 6
Hotwork Non Naked Flame 0 8 Work Permit Hotwork Non Naked Flame 8
Cold Work 0 14 Cold Work 14

PROGRESS
No. Scope Description Progress % Completed : Plannned 91.2% Actual 87.2%
Structural Completion Date : Baseline 15‐Sep‐2011 Forecast 15‐Sep‐2011
S001 Preparation work, scaffolding & install gusset plate for Module 2 & 3 100%
S002 Preparation work, scaffolding & install gusset plate for Module 1 100%
S003 Install Anode 0%
S004 CP Guide Under Water 0% S‐Curve Plan vs Actual Progress
S005 Protection Frame 55%
120% 20.00%
S006 CP Guide Above Water 100%
S007 Extension Deck Module ‐2 99% 18.00%
Plan Daily Progress Actual Daily Progress
S008 Extension Deck Module ‐3 100%
100%
S009 Extension Deck Module ‐1 99% 16.00%
S010 Appurtenances 100% Cummulative Plan Daily Progress Cum Actual Daily Progress
Cummulative Progress Value

Piping 14.00%
80%
P001 Lifiting & positioning WHCP 100%
Daily Progress Value

P002 Well Sevice 81% 12.00%


P003 Methanol Injection 100%
60% 10.00%
P004 Drain 99%
P005 Open Drain 100%
8.00%
P006 Hydraulic 99%
P007 Utillities 100% 40%
6.00%
P008 Sample Connection 98%
P009 Venting 99% 4.00%
P010 Fire Water 96% 20%
Electrical/Instrument 2.00%
EI001 Support Installation 95%
EI002 Tray Installation 95% 0% 0.00%
11‐Aug
14‐Aug
17‐Aug
20‐Aug
23‐Aug
26‐Aug
29‐Aug
9‐Jul

2‐Aug
5‐Aug
8‐Aug

1‐Sep
4‐Sep
7‐Sep
10‐Sep
13‐Sep
12‐Jul
15‐Jul
18‐Jul
21‐Jul
24‐Jul
27‐Jul
30‐Jul

EI003 Tubing Installation 99%


EI004 Electrical & Instrument Cable Installation 93%
EI005 Electrical & Instrument Termination 83% Date
EI006 WHCP 100%
EI007 Fire & Gas Detector Modification 50%
EI008 PCS & SSS 100% RFC Sub‐System
EI009 Precommissioning 96% No of Sub System Issued Awaiting Rejected Approved
EI010 Gas Detector Modification 83% Approval
EI011 Lighting Relocation 72%
30 11 0 1 10
EI012 Marine Latern 100%
EI013 Instrument & Electrical Installation 98%
EI014 Instrumentation 100%
Reported by Sisi Nubi 2a Site Planner