Professional Documents
Culture Documents
Risk Analysis Guide - EN 09.2019
Risk Analysis Guide - EN 09.2019
Guide
V1 – 09/2019
RISK ANALYSIS GUIDE
TABLE OF CONTENTS
Chapter Page
0 Guide for using the risk synthesis matrix..................................... 2
1 Commercial analysis......................................................................... 4
5 Sustainable development................................................................. 17
7 Contractual Analysis.......................................................................... 23
8 Financial Analysis.............................................................................. 28
10 Maintenance...................................................................................... 40
1
RISK ANALYSIS GUIDE
CHAPTER 0
GUIDE FOR USING THE RISK SYNTHESIS MATRIX
Bidder:
When it is a consortium or a JV, indicate its organisation, the participation percentage of each of its members and underline the
leader.
Country: If need be, also specify area or state (for a federal country).
Offer amount (Consortium) excl. Tax: total amount (excluding tax) of the offer presented by the bidding unit
Including own share: amount (excluding tax) of the offer for the VINCI Energies’ entity presenting the project
Comments: if needed, add a succinct explanation and the kind of risk treatment
- Blank: Risk is accepted without mitigation measures
- Q: Qualification
- P: Provision (amount in €, £, $ or %) to cover the risk
- R: Risk reduction by implementation of specific measures.
When appropriate, show the amount of the provision to cover the risk and/or the % computed on the entity’s own share.
This percentage is positive for a risk, negative for an opportunity.
After filling in the amount and percentage for each line, indicate at the bottom in the «summary» line the overall weighted
contingency amount and percentage taken into account.
2
RISK ANALYSIS GUIDE
CHAPTER 0
GUIDE FOR USING THE RISK SYNTHESIS MATRIX
The Risk Analysis Guide is a tool to analyze these risks and determine their criticality by proposing - in each chapter - a questionnaire
and related best practices.
The criticality will be reported in the Risks Synthesis matrix on the lines corresponding to the level 1 risks.
If necessary, level 2 risks (details of level 1 risks) will be explained to provide a better understanding of the project’s issues.
3
RISK ANALYSIS GUIDE
CHAPTER 1
COMMERCIAL ANALYSIS
Customer’s solvency
- Has the customer’s credit rating been checked (credit limit from COFACE or credit rating from another rating company, past
payments on time,…)?
- Are the funds necessary for the project available? Does the BU have to present a financial scheme?
- Is the customer’s budget or the project funds available sufficient to cover variation orders?
- What payment guarantee is requested by the BU (direct payment, bank guarantee, letter of credit, parent company guarantee, …)?
-R
eminder: Extending the benefit of the VINCI Energies insurance programme to third parties is prohibited unless a specific
authorisation is obtained from the legal department of the Division concerned
Note: if an alternative offer is significant, a technical analysis of such alternative must be presented (refer to Chap 4. Technical
analysis)
4
RISK ANALYSIS GUIDE
CHAPTER 1
COMMERCIAL ANALYSIS
Customer’s solvency:
Before the contract is signed, ask the finance department to check the customer’s credit risk: contact specialist
organisations and/or other VINCI Group companies already dealing with the customer. If applicable, check the
customer’s current outstanding balances with the Group and payment terms normally agreed with it
- Maintenance contracts: to create activity for VINCI Energies once the contract is finished (rather than a simple
warranty period)
- Complete turnkey packages
- Options to be decided by the customer at a later stage – for instance when it has an opportunity to increase its
budget
- VINCI Energies’ international network of subsidiaries and /or the proximity of our locations
- Following the customer in its relocation ventures
- Customized financing schemes: PFI, buyer’s credit, ...
5
RISK ANALYSIS GUIDE
CHAPTER 2
GEOPOLITICAL ENVIRONMENT / LAWS & STANDARDS
6
RISK ANALYSIS GUIDE
CHAPTER 3
PARTNERS (BIDDING CONSORTIUM, TWINNING, SUBCONTRACTORS, SUPPLIERS)
Bidding Consortium:
Description of the consortium / JV:
- Consortium members and share of each member:
• What is the current financial situation of the partners?
• What are the most recent references of the partners for the same scope of works and project size?
• Regarding ethics and the prevention of the risk of corruption: an analysis of the risk of corruption relating to the
consortium partners has been performed according to the procedure defined by VINCI Energies, the Division, the
Country or the Pole? Has this analysis disclosed any illegal past practice? If so, what measures have been taken to
manage the risk of corruption: (Awareness/ training of the project team personnel, etc. … see VINCI Anti-Corruption
Code of Conduct)
• Our partners have not been subject to international sanction or restrictive controls?
• Could we replace them in case of default?
- Leader:
• Are the role and responsibilities of the leader crystal clear?
• Amount (or %) of the leadership fees?
• Decisions for common expenses under leader’s responsibility only?
- Is the consortium joint and several?
- Is the leader joint and several?
- Have the consortium members / project team already worked together ?
- Are the scope limits and interfaces with the partners clearly defined?
- Do you have an in depth knowledge of the partners’ works ?
- Do the partners assume 100% responsibility for their scope of works?
Consortium agreement:
- Is the consortium agreement signed?
- Is it applicable to the tender only or to the tender and execution as well?
- Has it been checked by the legal department? What are the risk identified by the legal department?
- What clauses are different from the model provided by the Group?
- Is the allocation of risks and responsibilities crystal clear?
• Towards the customer?
• Between the members towards the other members
• Is there a risk allocation matrix?
- How are the delay penalties shared?
- How are the performance penalties shared?
- Is there a procedure to describe funding from the partners (for example to pay common expenses) and rules established to
split the customer’s payments?
- Is there a dispute resolution clause?
- Are the conditions to replace the defaulting leader by another member specified?
CHAPTER 3
PARTNERS (BIDDING CONSORTIUM, TWINNING, SUBCONTRACTORS, SUPPLIERS)
BIDDING CONSORTIUM:
Recommendations and best practices:
(Also refer to the Internal Control and Risk Management Manual: Process P 2.8)
Entities can work together in several ways to perform a project. Legal assistance should be sought to determine the
most appropriate form depending on the specific features of the project and country of performance.
Joint and several consortium: each member is responsible towards the customer for the performance of the whole value of
the contract.
Not joint consortium (several consortium): each member is responsible towards the customer only for its own
share of the contract.
Whether or not we are joint and several, a badly performing partner will endanger the smooth execution of the
contract. This may have consequences for the BU in terms of timetable, additional costs and customer relationship.
Therefore selected partners should have a strong performance record both technically and financially and the
consortium agreement should clearly state the respective roles and responsibilities as well as the interfaces.
Recommendations:
- Select the appropriate organisation based on the common objective (execution of distinct work packages or pooling
of resources), the maximum risks that the BU is willing to assume (joint and/or several liability) and the technical and
financial strength of the partners.
- Before committing to any form of consortium, joint venture or alliance, measure the real benefits and risks for the BU
compared with those that would exist in a subcontractor’s situation.
- Joint and several liability consortiums should be avoided.
- The responsibilities of the leader (or the head of the consortium) during the offer period include in particular the management
of the project, the relationship with the customer, and in some instances, the consistency control of the technical solutions and
timetables proposed by the partners. The leader is also in charge of the optimisation of the total consortium offer to meet the
target price. It is necessary to check that an insurance policy covers the liability of the leader of the Consortium.
- If VINCI Energies is the leader, then the leadership fees must be included in the « Engineering and project
management » rubric of the price breakdown.
- Restrict the expenses / decisions which could be committed by the sole leader (if it is not the VINCI Energies’ BU)
on behalf of the consortium.
- The consortium agreement must be signed before tender submission. Every time we are party to a complex
consortial operation, an organisation chart must be presented where the contractual links and liabilities of each
partner will be specified.
- The most usual rules for the allocation of the penalties between partners are the following:
2. The faulty party pays up to the contractual % cap applied to its share, then the balance is split between
the partners (including the faulty party) in proportion to their respective share
B/ If no single partner is identified as faulty, then the penalties are split in proportion to the share of each partner
- When the VINCI Energies BU’s share in the overall consortium is small, it is safer for the BU to mutualise the
penalties (option A2 above) to avoid the risk of having to pay the penalties computed on the total value of the
contract, should the BU be the only faulty party.
- If a BU that joins a consortium, Joint Venture or other arrangement gives commitments on behalf of companies
outside the Group, ensure that these commitments are passed on to these companies (on the same terms and in
the same amounts) and ask for them to be covered by a credit worthy counter-guarantee (e.g. bank guarantee, parent
company guarantee indemnity bond for example).
Reminder: the extension of VINCI Energies’ insurance programmes to Goup’s external partners, in particular in the context of
consortiums or joint ventures, is prohibited except express authorization from the legal department of the Division.
The fight against corruption: An analysis of the other partners in the consortium relating to the risk of corruption is
to be performed according to the procedure established by VINCI Energies, the Division, the Country or the Pole.
Human rights: Have the members of the consortium made commitments to respect human rights in accordance with VINCI’s
Guide on Human Rights?
8
RISK ANALYSIS GUIDE
CHAPTER 3
PARTNERS (BIDDING CONSORTIUM, TWINNING, SUBCONTRACTORS, SUPPLIERS)
9
RISK ANALYSIS GUIDE
CHAPTER 3
PARTNERS (BIDDING CONSORTIUM, TWINNING, SUBCONTRACTORS, SUPPLIERS)
An industrial risk may arise with certain subcontracted or co-contracted items of equipment or concerning local
suppliers imposed by the Customer, or with untested technology transfers. Specific care should be taken with regards
to supplies which are critical in terms of delivery deadline or performance of the overall systems.
It is recommended to request guarantees to cover these risks.
Note: this risk coverage should not be mistaken with the error margin taken into account for the quantity estimates
(cables / number of I/O) or to cover nearly unavoidable expenses which can only be estimated as a % based on volume.
- Check the provider’s financial and technical soundness, as well as its ability to perform within the deadline
- In order to increase the BU’s overall competitiveness, special attention should be given to:
• Make or buy alternatives
• Procurement from low cost countries: ready to use equipment and supplies, manufacturing according
to the BU’s specifications, detailed design subcontracting, …
• Compliance with VINCI Energies’ procurement policy, in particular with regards to frame contracts,
payment terms and conditions.
- Involve the subcontractor during the bid period: appraise its proposals regarding alternative solutions, options
(which could be presented to the customer as alternatives), optimisation of the overall project cost, …
- Ensure that the subcontractor has properly understood the project constraints, particularly those relating to
technical issues and deadlines; insofar as possible, arrange for a worksite visit by the subcontractor.
- Draw up a comparative table of bids with quantifiable criteria to assess the proposals in a relevant and objective
fashion.
- Verify the subcontractor’s compliance with labour and tax requirements (e.g. in France, vigilance certifications …)
10
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
- Does the contract describe the customer’s approval process – phase after phase - of the BU’s basic design?
- Does the Customer’s basic design approval release the BU’s responsibility?
- What is the amount of the provisions included in the cost estimates for re-design (additional engineering, cost of equipment
modifications, supplies, …)?
If the customer (or a third party designated by the customer) is in charge of the basic design:
- Does the BU have the obligation to check the drawings, the quantities in the BOQ (Bill of quantities)?
- Have discrepancies been identified between the drawings and the BOQ?
11
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
If it does :
- What are the main performances stated in the contract?
- What are the significant pieces of equipment contributing to the achievement of the contractual performance?
- Is the BU responsible for the technical specification of the main pieces of equipment?
- Are the procedures for the acceptance and the methods for measuring the contractual performance (conditions, tests,
duration, …) described in the contract? If not, are they described in our offer?
Is a preliminary design phase (Ingéniérie Simultanée) planned? If not, has it been proposed to the customer?
Documentation :
- Any particular requirements with regards to documentation, administrative agreements or unusual technical norms?
Note: if the alternatives have a significant impact, a technical analysis has to be presented for each alternative.
- Is the scope of works (equipment and services) clearly defined in our offer? Quantities, main equipment specifications, civil
works, erection, supervision of erection, commissioning, warranty…
- Are there differences (related to the scope of works) compared to the customer’s expectations?
- Is the scope of works under the customer’s responsibility clearly stated?
- Are there technical interfaces which have not been verified?
- Has a site visit taken place?
- Has this site visit allowed full knowledge of the environment? Was it sufficient?
- Have the expected number of hours been checked by the departments in charge of execution (design office, site manager, …)?
- Are contingencies or provisions included in the project costs to cover identified risks or uncertainties in the contract
documentation?
- Is the total project’s budgeted cost consistent with that of the similar projects performed recently?
12
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
Methods / Innovation :
- Does the project include innovative components or new execution methods?
- Are non-conventional processes covered by a technical agreement from a recognised organisation?
- The legal safeguard of innovative components is envisioned?
Site conditions
- Any particular constraints related to security and safety?
- Any particular site or environmental issues or constraints?
• residential / industrial area
• underground networks
• access to site
• access or rights of way,
• risks related to works close to occupied or being currently built buildings
13
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
A “ lump-sum” contract should not be understood as an “all inclusive” contract. The stated price and timetable in our
offer must make reference to a precise list of supplies and services.
If the references mentioned above cannot be written in our offer, they should be kept in the contract file for future
reference when discussions for variation orders and claims will take place .
Erection, Commissioning
These services can be performed either entirely by VE (or by VE’s sub-contractors), or entirely by the customer (VE
having no responsibility whatsoever) or by the customer under VE’s supervision.
It is therefore important that each party’s responsibilities are precisely described and that the costs of these services
account for the risks borne by VE.
When VE supervises the services performed by the customer, or if VE has to provide assistance, then it is
recommended to write in the contract the assumptions used for pricing these services: daily rate (or hourly rate),
monthly lump-sum amount for a given number of people assigned, who bears the travel and accommodation costs, …
Documentation
Ensure that the exhaustive list of the documentation to be provided to the customer is actually included in the contract
documents. This list should be completed with a timetable, in particular for the documents which have to be approved
by the customer before execution (approval of FEED, PRO, procedure for performance measurement, …)
14
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
Assess the costs arising from the project environment: project execution conditions, joint activity, lost time, logistics,
staff health and safety, insurance, environmental protection, waste collection and traceability, etc.
Once the cost of the various services has been calculated, the offer’s total cost should be optimized by seeking
synergies between the various cost components (do not just add them together).
Finally, the estimated total cost should be compared with that of similar projects (won or lost)
During negotiations:
- Recalculate costs, including contingencies, to take into account changes in the offer following clarifications received
- Anticipate customer’s expectations not stated in the contract and that cannot be invoiced additionally
15
RISK ANALYSIS GUIDE
CHAPTER 4
TECHNICAL ANALYSIS AND SITE CONDITIONS
The maximum variation of quantities (especially when it is a decrease) without unit price changes should be limited
(recommended: 10% maximum). If the threshold triggering the change in unit prices is higher than a given value (for
example 10%), then the unit prices should include a commensurate contingency.
The reference for VE’s unit prices also assumes specific work conditions and labour efficiency: clear instructions
(diagrams) from the customer to prevent re-work, unrestricted access to working areas, and a precise timetable to
execute the works.
This reference should also be stated in our offer together with the price list for deviations from this reference: monthly
site costs for extended timetable (project management, site management, rent of facilities, equipment, …) and hourly
rates of engineering, studies, … due to re-work at customer’s request or for completing specifications that should have
been provided by the customer.
Nota: although these recommendations aim at protecting VE’s interests, they should also be presented to the
customer as protecting its interests: indeed, if VE is not sure it will recover its costs if quantities increase or decrease,
or if the works last longer than anticipated, then we will include contingencies in our selling price, which in the end
may be more costly to the customer than a fair remuneration of the actual work done.
If the references mentioned above cannot be written in our offer, they should be kept in the contract file for future
reference when discussions for variation orders and claims will take place
16
RISK ANALYSIS GUIDE
CHAPTER 5
SUSTAINABLE DEVELOPMENT
Quality assurance
17
RISK ANALYSIS GUIDE
CHAPTER 6
PROJECT MANAGEMENT (SCHEDULE)
Organisation / interfaces
- Are interfaces « customer/BU » or « bidding consortium/other contractors » defined without ambiguity?
- Is a crystal-clear organisation planned, stating the interfaces with third parties as well as the internal operating mode
(roles and responsibilities) with the co-contractors, the Engineer, the General Contractor,…
- Is the design carried out by one Engineering firm or several ones? In the latter case, is there a design coordination cell?
- For comprehensive projects including all building activities (Tous Corps d’Etat - TCE) is there an integration cell with adequate
resources?
- Take-over conditions :
• Are the take-over procedures (FAT, tests, acceptance, …) described in the contract (duration, resources, authorisations, …)?
• Do we have control over the acceptance process?
• Are partial acceptances possible?
• Can the customer use the installation prior to acceptance?
• Have we allowed enough resources to clear the punch list items within a reasonable period of time?
• Is the training of customer’s staff a condition precedent to obtaining the take-over certificate?
18
RISK ANALYSIS GUIDE
CHAPTER 6
PROJECT MANAGEMENT (SCHEDULE)
Administrative agreements
- Are the permits and administrative authorisations under our responsibility exhaustively listed in the contract?
- Are the procedures to be granted permits and authorisations familiar?
- Are the difficulties for third parties to obtain permits and authorisations identified?
- Are recourses possible?
- Are the procedures for obtaining visas and work permits well known?
Resources (availability)
- Does the project fit into BU’s expected workload?
Site labor :
- Is there a group entity which can provide assistance locally?
- Are we familiar with local external subcontractors?
Transportation / Incoterm :
- Any particular issues related to procurement or transportation?
- Which is the contractual INCOTERM?
- Does the timetable show the period allocated to transportation?
19
RISK ANALYSIS GUIDE
CHAPTER 6
PROJECT MANAGEMENT (SCHEDULE)
Therefore, VE’s offer must include a timetable highlighting the milestones to be met by the other parties – including
the customer – so that it can meet its own deadlines.
Our offer must indicate the maximum period for customer’s approval of the drawings or of the changes proposed,
and the consequences of exceeding this period; for example: the documents (or the proposed change) are deemed
approved and VE is contractually allowed to execute them, or an extension of time is granted (with associated costs)
until the complete performance of the milestone by the customer.
The documents must be “deemed approved” when the customer has not answered within a reasonable period.
Organise an accurate follow-up of the customer’s late answers (backed up by documentation) to justify our potential
future claims on this matter.
20
RISK ANALYSIS GUIDE
CHAPTER 6
PROJECT MANAGEMENT (SCHEDULE)
Warranty:
Insure that the BU can actually assume the warranty commitments undertaken, in particular with regards to equipment
life duration and availability of spare parts.
Request from suppliers warranty commitments (nature of risks and duration) matching VE’s contractual warranty. If
need be, include a provision in the project’s costs and / or estimate the cost of a technician remaining on site during
the whole warranty period.
Significant risks during the warranty period are those likely to result in the return to the factory of major items
of equipment constructed specifically for the project (transformers, turbines, etc.). It is very important to draft
maintenance and operating manuals and deliver them to the customer as early as the provisional acceptance stage,
given that such manuals discharge us from any liability in the event of operator’s default (unless specified otherwise in
the contract).
Resources (availability)
Management / Supervisory staff
It is of utmost importance to identify the project manager / project director as soon as bid stage.
It is recommended to select a project manager or a project team with a proven record of achievement in terms
of planning, works organization and coordination for projects of a similar size in identical environments (industry,
infrastructure, maintenance, export, …).
21
RISK ANALYSIS GUIDE
CHAPTER 6
PROJECT MANAGEMENT (SCHEDULE)
Therefore, the availability of contract management resources should be anticipated and their cost included in the
project’s costs.
Contract management should be performed throughout the contract term: it starts with the offer, then during
negotiation and continues notably during performance through to the term of any guarantee.
Note: Meetings with the customer for the negotiation of the contract documentation prior to order award give VE
the opportunity to:
- Clarify what is included in our scope of works and what is not
- Pintpoint what is still unclear or not agreed with the customer
and thus identify, as early as offer stage, potential additional works.
22
RISK ANALYSIS GUIDE
CHAPTER 7
CONTRACTUAL ANALYSIS
23
RISK ANALYSIS GUIDE
CHAPTER 7
CONTRACTUAL ANALYSIS
24
RISK ANALYSIS GUIDE
CHAPTER 7
CONTRACTUAL ANALYSIS
General recommendations :
- If the draft order/contract is imposed by the customer, ensure that all unusual or unbalanced clauses are fully
analysed and understood and, if necessary, negotiate adjustments or additional clauses
- Submit our General Terms and Conditions of Sale, for Services (see the models made available by the group
according to the nature of the works or services to be performed), possibly to be completed by specific terms and
conditions
- In the absence of any other solution, propose a model already validated by an in-house legal counsel or a
standard contract recognised in the industry (FFB/FNTP, FIDIC*, NEC **, ….) and adjust it to the project’s specific
features
- Letter of intent relating to an order/contract (or memorandum of understanding or any other document of the
same type): check the extent of commitments made and the BU’s real ability to further negotiate the contract
clauses that have not yet been finalised
- Framework agreement: in the case of an order made under a framework agreement, detail the specific terms
applicable to the order
- Multi-year contract: state the consequences of non-renewal or early termination of the contract, including the
transfer or redeployment of staff
- Draw up a complete list – by order of precedence – of the contractual documents and appendices and make
sure that all documents referred to in the contract are sent to you (e.g. drawings, particular technical
specifications, model bank guarantees, main contractor’s contract, etc.). Ensure consistency between indexes used
in the bid documents and the contract
- Before signing the final order, ensure that all the terms and conditions are fully understood by all parties and are
consistent with the outcome of negotiations
(*)FIDIC: International Federation of Consulting Engineers. (FIDIC best practices are available in the annexes of the Internal
Control and Risk Management Manual)
(**)NEC°: “New Engineering Contract”
- As a precaution, try to add a clause stating the consequences for VE should the advance payment not be
paid or the letter of credit not be opened before the agreed time limit: compensation for loss of opportunity,
reimbursement of the expenses already committed, …
Delay penalties
Firstly, try to obtain automatic extensions of the contractual deadlines in our favour, along with compensation in the event
of a delay that is not attributable to the BU (customer’s delay – in particular during the period for approving drawings or
for access to site -, delay due to another contractor, administrative delays, etc.).
Seek to obtain a bonus if the works/services are completed before the contractual date
25
RISK ANALYSIS GUIDE
CHAPTER 7
CONTRACTUAL ANALYSIS
Performance penalties
Same recommendations as for delay penalties. Special attention should be given to the criteria for measuring the
performance and to the performance level accepted in the past.
Indirect and consequential damages and losses, such as: economic losses, pure financial loss,
loss of profit or loss of production, loss of use, … should be clearly excluded. It should be stated that this list is not
exhaustive.
VE ‘s Overall liability
The cap on overall liability should be written in a specific clause so that it covers the whole contract. It is usually written
as “ notwithstanding anything to the contrary in the contract, VINCI Energies ‘ total aggregate liability to the customer
arising out of or in relation to the performance of the contract – all causes included - shall be limited to … “ .
Remember to limit your liability to damages or losses which the BU is fully responsible for (not “in the course of the
performance of the Works”).
The cap should not be higher than the contract price .
Note: if nothing is specified regarding the amount of our liability, our liability is therefore uncapped and potentially far
above the value of the contract.
Force majeure :
Specify the procedure applicable in case of Force Majeure and the contractual consequences: extension of time,
reimbursement of the mobilisation /demobilisation costs if any, duration of the suspension, termination of the contract.
Note: Force Majeure does not entitle the BU for all costs attached to the suspension. Force Majeure is normally solely
about time relief.
Hardship clause: right (for VE’s BU) to renegotiate the contract terms, for example: increase of raw materials
prices (copper, steel, …), change in applicable standards or codes, change in law (including tax laws), …
If an identified risk is not covered, it is the responsibility of the Project Manager to inform the BU Manager. The BU
Manager will be able to draw on recommendations made by the in-house lawyer, insurance manager, insurance adviser
and/or brokers in order to decide whether or not it is appropriate to take out a specific insurance.
26
RISK ANALYSIS GUIDE
CHAPTER 7
CONTRACTUAL ANALYSIS
Even if the contract may state that VE’s BU is co-insured by the policy taken out by the customer for the whole
project, it is recommended to ask VE’s brokers to check the conditions precisely, especially the deductibles.
b) For a non-French company, the “usual” risks of a BU: Certain policies have to be subscribed in the country where
the subsidiary is established or in the country where the services are performed (for example: employer’s liability,
vehicles and site equipment, damage to premises). Also, in some countries, the law provides the obligation to
subscribe all policies locally. This needs to be checked by the BU.
27
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
Nature of price :
- Nature of price (lump sum, bill of quantities, cost + fee, target cost, other, …)
Note: a summary of the purchases (supplies and subcontracting) and a staff mobilisation chart or project organisation chart may
be presented with the Risk File to describe the related costs
Cash:
Terms and schedule of payment
Conditions as per RFQ :
28
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
Down/Advance payment
Performance
29
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
Other costs to be included in the full cost: (refer to the Quotation sheet)
Warranty provisions are expected to cover the costs incurred during the warranty period, net of warranty costs
assumed by the suppliers/sub-contractors.
Financial costs should reflect realistic payment conditions and should be consistent with the cash curves.
Lost quotation costs and group fees should be those of the annual budget of the tendering BU.
Cash
Terms and schedule of payment :
(refer to the Internal Control and Risk Management Manual: Process P 2.7)
For obvious reasons, cash has to be collected as soon as possible and the stream of cash flows should ensure a positive
net cash position at all times during project execution.
To limit the risk of delayed payments, or even no payment, and their consequences, it is recommended to:
- Negotiate a significant advance/down payment, as many progress payments as possible, a short payment period,
and so on …
- For service contracts, negotiate payments in advance rather than in arrears
- Clarify with the customer the documents and information to be provided with the payment requests
- Obtain from the customer an exemption from any warranty retention in return for a bank guarantee
- Include a clause in the contract whereby the BU may suspend / terminate the execution of the works in case of
delayed payments
- If there is an insolvency risk, ask the customer for a payment guarantee (if not, request a parent company
guarantee) or a letter of credit for the total amount of the contract less the down payment
- If possible, request a direct payment from the final customer
- When needed, take out a specific credit insurance
Cash curves
The cash curves picture the projected cash flows over the life of the project. They are calculated before financing and
before tax. Several cash curves may be necessary to reflect the impact of changes in assumptions or when several
currencies are used (either for the payments or for the expenses).
30
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
and past experience with regards to the customer’s punctuality should be taken into account.
In some cases, for particularly risky projects, a cash flow based on the commitment of expenses (rather than cash
outflows) will be presented to better appreciate the risk of a contract interruption.
In most cases, a discount rate of 0,6% per month (in 2019) before tax is adequate. However, in risky countries or with
a risky customer, a higher discount rate should be used. The Pôle’s finance department is available to estimate this
additional percentage to take into account.
Reminder: Definitions :
Bid Bonds are requested from companies that participate in tenders (usually public tenders)
The bank issuing a bid bond undertakes to pay to the beneficiary (the customer), in principle upon first demand, all
or part of the guaranteed amount (usually 1 to 3 % of the contract price) in the event the bidder (Business Unit),
after having been awarded the tender, were to refuse or were unable to sign the contract or to issue the guarantees
requested in the RFQ.
The customer sometimes pays part of the contract price in advance and wishes to obtain reimbursement of the
advance payment if the contractor (e.g. Business Unit) wholly or partially fails to perform its obligations. In view hereof,
the customer will request a guarantee, which is called an advance payment bond.
A performance bond protects the customer against damage caused by the non-performance or improper
performance of the main agreement by the contractor (e.g. Business Unit).
A warranty retention bond has the purpose to allow the performance of work covered by reserves made by the
customer at reception. The warranty retention bond is secured by fractions of the down-payment, partial definitive
payments and of the balance (e.g. in French public contracts, the retention is capped at 5%, possibly 3%).
In the event that the amounts due to the contractor are insufficient to allow the deduction of the warranty amount,
a first demand guarantee is to be made, alternatively a bond. In commercial contracts, the bond should have been
provided for in the contract for it to be applied (also capped in France at 5% for commercial contracts).
31
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
Note: Any parent company guarantee issued within VINCI Energies requires the prior formal agreement of senior
management (within the parent company reporting line; e.g. for a VINCI Energies SA guarantee, the Chairman and
Chief Executive Officer of VINCI Energies SA). This guarantee will be invoiced to the BU on the terms set out in the
memo issued by VINCI Energies’ Finance Department
- Systematically negotiate a bank guarantee instead of retention money or early payment (advance rent, for example)
- When the wording of the bond is not imposed by the Customer, it is the Unit’s responsibility to propose a Group
model, the “softest” possible to start with.
- For the expiry date, state a specific calendar date rather than an event over whose timing the BU does not have
full control (e.g. provisional acceptance) . This will protect the BU if the timetable slips for reasons that it is not
responsible for
- Try to negotiate an automatic reduction of the guarantee amount as the project progresses (in particular down
payment guarantee)
- Avoid unconditional or «first demand» guarantees by inserting within the text conditions for calling the guarantee.
This will help prove – if needed – the unfair nature of the calling of the bond. Always favour bonds, alternatively
simple letters of comfort
- Seek to limit the extent to which guarantees stand separately from the contract and ask for the criteria for calling
the guarantee to be made explicit
- Try to include an automatic release clause and state that the deed does not need to be returned to confirm the
termination of the commitment
- Strictly limit the provision of “performance bonds” due to the significant risks that they represent for the guarantor
- Avoid assignment clauses, which are often refused by banks. Where this is not possible, seek to limit their extent and
check the integrity and respectability of the clause’s beneficiary
- Check whether it is worth taking out an insurance against the “unfair calling of bonds”. Indeed, compensation terms
almost always require that there is no commercial dispute with the customer
32
RISK ANALYSIS GUIDE
CHAPTER 8
FINANCIAL ANALYSIS
- In a consortium – even if VINCI Energies is the lead company – limit our commitment in proportion to our obligations
under the contract
- If the BU that joins a consortium, joint venture or other arrangement gives commitments on behalf of companies
outside the group, ensure that these commitments are passed on to those companies (on the same terms and in the
same amounts) and ask for them to be covered by a suitable counter-guarantee (e.g. bank guarantee)
- State in the terms of the contract – particularly for export contracts – that the bonds or guarantees will be provided
by a top-tier bank, preferably one of the group’s usual banks. Try to avoid the guarantee being re-issued by a local
bank
- As far as possible, replace bank guarantees or bonds to be provided to another VINCI Group company as part of a
contract, with a unilateral letter of commitment to honour obligations upon first demand (see the model for this kind
of commitment on the VINCI intranet)
33
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
Technical particularities
- What are the main standards and norms specified in the contract? Have we used them before?
- Are the procedures for mandatory external controls well known?
- Are we fluent in the language to be used for the local works, technical documentation, training?
- Does the contract specify the details of land availability?
- Is the land free of inhabitants?
- Is the customer in charge of providing supplies (for example equipment, concrete, …)
- Has the risk of vandalism been assessed?
34
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
EXPORT FINANCIAL ANALYSIS (in addition to the analysis of the domestic part) :
Credit insurance
For risky customers or in risky countries, is the contract insured against:
- Political risk?
- Commercial risk?
• Is the unfair calling of bonds covered?
• Is the breach of contract covered?
- What are the residual risks not insured?
35
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
Tax exposure :
- Have all the recommendations from the finance department been taken into account?
- Is there a signed tax agreement with the country of the company?
- Is a permanent establishment necessary?
- Are all the taxes and duties properly estimated and provided for (import taxes, export taxes, VAT, custom duties, company’s
income tax, personnel income taxes and salary taxes, overhead expenses deductible, withholding taxes,…)
- Is the tax clearance certificate necessary before the last payment can be received?
- Are tax controls foreseeable?
Insurance
- Are transportation and the local portion of the contract covered by the Group’s policies?
- Are specific insurance policies needed to protect personnel, site works, local facilities?
36
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
The most often encountered difficulties which have turned out to be very costly indeed stem from :
- Underestimated complexity of the customer’s decision process: number of meetings, number and motivation
of people involved,
- Productivity of local labour: not only pace of execution but delays to get work permits, authorisations for
overtime work, safety issues, availability of skilled labour for specialised works, language barrier
- Applicable norms and standards, approval procedures by control authorities
- Availability of handling equipment, ad-hoc vehicles
- State of access roads and working sites
- Weather conditions
- Cost of providing security to our personnel
- Language of the contractual documents and technical documentation to be issued
- Different appreciation of time constraints, deadlines, commitments, …
If the involvement of an agent is necessary, please refer to the best practices listed in Process P2.10.2 “ Agents and
commercial intermediaries” of the Internal Control and Risk Management Manual.
37
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
Letter of credit
- The letter of credit’s confirmation is necessary only when the L/C is not issued on a first class bank. Check with
the Pôle’s finance department the credit worthiness of the issuing bank (Note: confirmation means additional
costs)
- Request the exhaustive list and an accurate description of the documents to be presented to be paid with the
L/C: have their suitability checked by a financial institution before signing the contract.
The group’s policy is to hedge all currency exchange risks, except in exceptional cases duly authorised by VINCI
Energies’ Finance Department.
The most commonly used exchange risks covers are the following :
1 . Contract payments in several currencies, so that the breakdown of the selling price matches the expenses to be
incurred in the same currency
2. Subscribe an exchange rate cover, after approval by the Pôle ‘s Finance Director
Remark: If the offered price can only be presented in one currency – thus generating a currency exchange risk – it may
be possible (to be checked in the RFQ documents) to indicate a « reference currency exchange rate » for the exchange
rate. However, it is then essential to state that the final contract price will be updated at a later stage with the forward
currency exchange rate prevailing on the date of updating.
In this instance, no costs are incurred for hedging during the offer period as long as there is no certainty that we will be
awarded the order.
The Pôle’s Finance Director must be kept informed during the final negotiations (as well as during the execution period)
of all potential changes so that the currency exchange risk cover is adapted accordingly as soon as possible.
38
RISK ANALYSIS GUIDE
CHAPTER 9
EXPORT ISSUES (INCLUDING FINANCE)
VINCI Energies’ tax department or the Pôle’s Finance Director must be informed as soon as it is decided to bid for an
offer and before a decision is made on the terms of the offer and the contractual organisation. The tax issues must also
be analysed before any consortium agreement is signed.
(See also Process P2.10.1 Permanent Establishment in the Internal Control and Risk Management Manual)
Insurance
(See also Process P6.3 Insurance in the Internal Control and Risk Management Manual)
- Have the Pôle’s Finance Director of the group’s insurance brokers analyse whether specific insurance policies
should be taken out.
39
RISK ANALYSIS GUIDE
CHAPTER 10
MAINTENANCE
- Single-site or multi-site?
- Sedentary or itinerant?
- Single-technique or multi-technique?
- Posted? Stand-by?
Start-up period :
- Is the start-up period contractually defined?
- Are the commitments during the start-up period clearly defined?
- What will be the transition process between the project team and the execution team?
- What resources are mobilised for implementing the contract?
- Are the resources needed for the start-up available?
Operating period :
- What are the expected changes in the scope of works? increase, decrease, additional flow business?
- How are we protected against changes in economic conditions or regulations during the execution of the contract? is there a
clause allowing the BU to terminate the contract?
End of contract :
- What are the conditions at the end of the contract if it is not renewed?
• State as new or in good working conditions?
• Timetable for the transfer?
• Inventory of the premises expected? subject to customer’s agreement?
• Are the control tests specified?
• Personnel
• Resale of inventories
• what are the contractual guarantees to be given?
40
RISK ANALYSIS GUIDE
CHAPTER 10
MAINTENANCE
Spare parts :
- Are they free-issued by the customer, included in the lump-sum or paid on cost + fee?
- Create or buy existing inventory? for what amount?
- Is the customer obliged to buy back the inventory at the end of the contract?
- Provision for obsolescence included in our costs?
Personnel :
- Average number of employees for regular operations?
- What are the critical skills needed for execution?
- Is there an obligation to take over existing personnel?
If existing personnel must be taken over :
- Is the take-over imposed by law, by the customer or is it negotiable?
- Number of persons to take over, seniority, protected employees, …
- Do we have to assume pension rights for prior service?
- Protected personnel and collective agreements :
- Redundancies anticipated?
- Is the customer (or the following contractor) legally bound to take back the staff at the end of the contract?
If not, how will the BU assign the employees?
41
RISK ANALYSIS GUIDE
CHAPTER 10
MAINTENANCE
42