Professional Documents
Culture Documents
TWG#3 - Tower Crane Foundation and Tie Guidance
TWG#3 - Tower Crane Foundation and Tie Guidance
Once the tower crane design is completed and issued to During the first week of crane operation, it is
the PCTWC and project team for ‘approval’ this should be recommended that daily TW inspections on levels and
distributed to the crane supplier and installation contractor conditions are completed by the PCTWC.
for their review/information. Comments should be
collaborated by the PCTWC and fed back to the designer Visual TW inspections should be carried out on a weekly
to amend/revise and re-issue for ‘construction’ issue. basis after this.
Installation and inspections More detailed examination of critical items such as; bolts
and welds should be completed at 3 monthly intervals by
Site specific inspection test plan (ITP) that recognises the a competent person.
type, complexity, and implementation of the tower crane
base should be included and understood by all parties See page 2 for the foundation monitoring checklist table
completing the relevant inspections, and where hold taken from CIRIA Tower crane foundation and design.
points are needed. This should be used as a point of reference when
creating the ITP and TW monitoring for the tower crane
Any additional TW relating to construction, erection and foundation and ties.
dismantling to be considered by all parties and approved
References
CIRIA C761 Tower crane foundations and ties design –
London, 2018