Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Temporary Works Guidance #3

Tower crane foundations and ties

Tower crane foundation and tie guidance


Tower cranes are one of the most high-risk elements of temporary works that ISG
manage on a project. This guidance document will help manage the process
around tower crane foundations through design, install and monitoring
Planning designs in place. This includes, but not limited to; mobile
crane working platforms, backpropping, and any
The planning stage of the project is where the Project modifications to permanent works.
team should determine the type, location, and lifting
capacity of the tower crane. Whilst also considering the The tower crane foundation designer, or 3rd party
access, over sailing, railways, de-rating, tying, and any 3rd independent inspector should inspect all tower crane
party approval requirements that are specific to the foundations and ties at installation stage.
project.

Any additional Temporary Works (TW) relating to the


construction, erection and dismantling of the tower crane The tower crane foundation
is to be considered at this stage too. designer, or a 3rd party
Design independent inspector
A detailed TW control sheet must be issued to the TW
should inspect all tower
designer by the PCTWC with all the relevant information crane foundations and
including; GI, utility plans, crane loads from supplier,
location plan, relevant permanent work drawings etc. ties at installation stage.
All tower crane foundations are to be categorized as
CAT 3 for engineering risk, and High-risk for
implementation risk, in line with the updated classification Consider an independent setting out engineer to validate
and categorization document. the crane base levels during installation, prior to
pour/crane erection.
The TW designer is to check the crane supplier loads
(using first principles) as part of the initial design process. See page 2 for the pre-erection inspection checklist table
taken from CIRIA Tower crane foundation and design.
The TW designer is to include testing and inspection This should be used as a point of reference when
criteria as part of their design package (cube, pile, weld, creating the ITP for the tower crane foundation and ties.
bolts testing etc.) This will form part of the Inspection test
plan for each individual tower crane foundation. Monitoring

Once the tower crane design is completed and issued to During the first week of crane operation, it is
the PCTWC and project team for ‘approval’ this should be recommended that daily TW inspections on levels and
distributed to the crane supplier and installation contractor conditions are completed by the PCTWC.
for their review/information. Comments should be
collaborated by the PCTWC and fed back to the designer Visual TW inspections should be carried out on a weekly
to amend/revise and re-issue for ‘construction’ issue. basis after this.

Installation and inspections More detailed examination of critical items such as; bolts
and welds should be completed at 3 monthly intervals by
Site specific inspection test plan (ITP) that recognises the a competent person.
type, complexity, and implementation of the tower crane
base should be included and understood by all parties See page 2 for the foundation monitoring checklist table
completing the relevant inspections, and where hold taken from CIRIA Tower crane foundation and design.
points are needed. This should be used as a point of reference when
creating the ITP and TW monitoring for the tower crane
Any additional TW relating to construction, erection and foundation and ties.
dismantling to be considered by all parties and approved

Construction | Engineering Services | Fit-Out 1


www.isgltd.com
Temporary Works Guidance #3
Tower crane foundations and ties

References
CIRIA C761 Tower crane foundations and ties design –
London, 2018

Construction | Engineering Services | Fit-Out 2


www.isgltd.com

You might also like