1.0.M. Instructions
~ @cameron Heer
INSTALLATION
Drying of Coolers
(On compressors used in nitrogen and dry air service the following is recommended prior to
‘commissioning of machine.
4, Remove drain plug(s) from bottom of cooler shell and shell cover assembly, if
applicable. See cooler assembly drawing, in this section, for drain locations.
2. With drain plugs removed, purge machine with dry air for a minimum of 24 hours.
3. Remove purge from compressor and replace drain plugs.
Bundle Removal
Clearance must be provided at the water nozzle end of the cooler to remove the tube
bundle. Refer to the Compressor Installation Arrangement drawing for clearance
dimensions.
Water Piping
Ifthe cooler water manifold is not provided by Cameron, refer to the Water Schematic
drawing for recommendations and definition of Cameron’s scope of supply. Control valves
should be provided on the discharge line of each cooler. The manifold should include
‘couplings for temperature and pressure gauges on both inlet and discharge lines close to
the heat exchanger.
Drain piping should be isolated for each cooler and not piped to a closed manifold system.
Before connecting piping, inspect all openings of the coolers and piping for contaminants.
CAUTION
Piping should be suitably supported so that forces
are not directly applied to the heat exchanger.
Condensate Removal
Condensate will accumulate during normal operation of some heat exchangers. Refer to
the Condensate Flow Schematic drawing for recommendations and definition of
Cameron's scope of supply.
CAUTION
Condensate piping should drain to an open sump
and never piped to a closed manifold system.€ CAMERON Heat Exchanger
1.0.M. Instructions a
OPERATION
Start-Up
1. Check water piping system for cizanliness to prevent blockage of tubes.
2, Loosen water side vent plugs be‘ore admitting water to the cooler.
3. Check all flange bolting for tightness.
4. Start flow of water, gradually at frst. When the system is completely filled and all
air vented, tighten vent plugs.
WARNING,
Never operate the heat exchanger at pressures,
temperatures or flows in excess of those specified
on the nameplate.
‘Shut-Down
Caution must be taken to avoid subjectiig the heat exchanger or the compressor to
thermal shock. Excessive temperature could impose stresses resulting in catastrophic
damage to the heat exchanger and/or the compressor.
WARNING.
Never stop water flov to the heat exchanger before NS
shutting down the compressor.
Winter Protection During Shut-Down
Ifit becomes necessary to shut-down ths compressor in a location subject to freezing
conditions the following procedure must be implemented to prevent coil damage.
Thoroughly drain water by removing vent and drain plug from supply channel,
2. Replace drain plug,
3. Add two gallons (minimum) of antifreeze solution through vent in supply channel
4. Replace vent plugs.
Performance
When performance does not meet spec:fied requirements check the following:
1. Fouled tubes caused by sludge cr scale.
2. Incorrect piping connections. Refer to the Installation Arrangement and Water
Flow Schematic drawings.1.0.M. Instructions
. @ cameron Heat Exchanger
3. Airlocks caused by improper venting,
4, Operating at conditions other than design; refer to the Heater Exchanger
Specifications.
5. By-passing of either air or water. Check partition gaskets and seal strips.
MAINTENANCE
WARNING
Do not attempt to loosen any bolting unti all
pressures have been relieved and fluids drained
Cleaning
A regular inspection program is important to determine frequency of cleaning. A reduction
in performance and/or a marked increase of pressure drop usually indicates that cleaning
is required
NOTE
Cameron's heat exchangers are designed to be
mechanically cleaned without removing the bundle
from the shell.
‘Water Side. Interior surfaces of the tubes can be cleaned by back-flushing to remove
sludge and other soft deposits. A rotary brush with brass or nylon bristles will be more
effective. if more severe fouling exists, contact a Cameron Compression Systems
Representative.
Gas Side. The extended surfaces (aluminum fins) should only be cleaned with detergent
and high pressure steam,
CAUTION
If all tubes are not clean, flow may be partially
blocked in some tubes causing overheating or
cooling. This condition could develop severe
stresses that can loosen tubs joints and fracture
tubes.
Special Draining Instructions for High Pressure Heat Exchanger (Design Pressure 2
160 PSIG)
When fluid is added to the gas side of a fully assembled high pressure heat exchanger
‘some of the fluid will be trapped between the shell cover and retum channel. Itis
necessary to remove the vent and drain plugs located on the shell cover to insure
thorough draining. (See Heat Exchanger Assembly drawings for vent and drain locations.)€ CAMERON Heat Exchanger
1.0.M. Instructions ~~
Bundle Removal
1. Remove lantemn-ring (or shell cover) and O-ring from retumn water header O.D.
2. Remove return water header.
3. Remove supply water header.
4, Inspect for inoperative roller guices ~ replace if required.
5. __ Insert eyebolt in tapped hole provided on top of front tube sheet.
6. Supporting bundle from eyebott, begin sliding bundle out of shell
WARNING. at
Do not completely remove bundle from shell. Do ee
not rest bundle on lower bypass seal.
7. After sufficient bundle is exposed, support and lift bundle with a nylon mesh sling
as its center of gravity.
WARNING
Protect bottom bypass seal (silicone) with 4x4
timbers on both sides.
NS
8. Complete removal from shell
Handling of Tube Bundles
Do not grasp bundles with hooks or other sharp tools which may damage the tubes or fins.
Nylon mesh slings or straps are suitable for lifting the bundles in a horizontal position.
Always take care to protect the lower bypass seal with 4x4’s in the area of the sling.
‘The bundles should not be dragged anc should only be moved about on cradles or skids.
Reassembly w
1. Inspect upper and lower bypass seals for possible damage. If replacement is
required, refer to Cameron Engineering Specification IL-2401
2. Spray top sheet of bundle and shell channel with silicone spray.
CAUTION
Failure to comply could destroy the bypass seals.
3. Position front tube sheet gasket on mating flange. Hold with tape or glue.
4, Remove top row of studs in rear tube sheet to prevent possible damage to upper
bypass seal.
+ we1.0.M. Instructions.
SN @ CAMERON Heat Exchanger
10.
"1
12.
13,
‘Support bundle with sling near its center of gravity. (Protect bypass seal with
4x4’s.)
Position bundle in shell. Align rollers on shell channel with guide legs on either
side.
Partially inert bundle to point of lft.
Transfer s
support to eyebolt on front tube sheet.
WARNING.
Do not reset bundle on lower bypass seal
Complete
Reinstall top row of studs in rear tube sheet.
Position return water header gasket and install return water header.
installation of bundie in shell
NOTE
Refer to Cameron’s Engineering Specification IL-
2401 for torque values and sequence.
Position supply header gasket and install supply water header. (Torque per IL-
2401)
Position o-ring on 0.D. of retum header and install lantem ring. (Torque per IL-
2401)Heat Exchanger
€ CAMERON .0.M. Instructions@ COOPER ENGINEERING SPECIFICATION
TURBOCOMPRESSOR
‘101 BROADWAY A 80% 208 12401
SULTS Ww eis 20 OSA
Assembly of Coolers
ISSUED: RAV-107 04/16/85.——_~D. Glauber
Rev. 1) RBL-236 01/16/92 K. Conroy
Rev. 2: RBL-981 03/24/92. -—-K. Conroy
Rev. 3 RBO-076 09/17/92‘. Conroy
Rev. 4: RBS-611 07/28/93 K. Conroy
Rev. 5: RDA-534 10/02/98 K. Conroy
‘Turbo Air® and MSG® Centrifugal Compressors
Genuine JOY® Pars GBSRevisions | ()RBL-236 | (@)RBL-981 | ()RBO.076 | (4)RBS-611 | (S)RDA-534
oii692 —_fosrae2 —[ocn7s2 | o7asies | 10/02/98
11-2401
Page | of 8
SCOPE:
‘This specification describes the procedure for properly assembling the following cooler
variations:
Standard Cooler
High Pressure Head Version
Double Tubesheet Design
Single Tubesheet Version of the Double Tubesheet Design
2BaH
NOTE
Interior (shell side) of cooler must be free of
dirt, glycol residue. and hydrocarbon
contamination.
DESCRIPTION:
I. Standard Cooler
1. Position by-pass seals on upper baffle and bottom sheets of bundle. Hold in
place with Dow Coming silizone adhesive or equivalent. Allow to set and cure.
NOTE
Seal should run frora outside front shell flange
to outside of rear skell flange at the top. At the
bottom, the seal should run from the inside of
the front tubesheet 10 1/16" beyond the outside
of the rear tubeshee:
2. Lubricate top of bundle casing and bundle support channel in shell with solution
‘of dish soap and water.
CAUTION
Failure to comply could damage the by-pass
seals.
3. Position front tubesheet gasket on front shell flange. Hold in place with tape.Revisions | (RBL-236 | @rBLos1 | @RBO.076 | (RBS611 | ()RDA-534
over —_foseas2 —_fosn7er omens | 10298
1L2401
Page 2 of 8
NOTE
Some designs use an o-ring rather than a front
‘ubesheet gasket. For these designs position
o-ring in o-ring groove on inside surface of
front tubesheet. Hold in place by applying a
thin coating of Dow Coming silicone adhesive
or equivalent directly to the o-ring. Allow to
set and cure.
4. Position foam gaskets over ends of bundle support channel. Hold with Dow
Coming silicone adhesive or equivalent, if necessary. Allow to set and cure.
5. Remove top row of studs in rear tubesheet to prevent possible damage to upper
by-pass seal
6. Place studs in front and rear shell flanges. End of studs stamped B-7 to face
out
7. Protect bottom seal with 4 x 4 timbers on both sides of seal. Support bundle
with sling near the bundle’s center of gravity.
8. Position bundle in shell. Align rollers on bundle support channel, with guide
legs on either side of the channel.
WARNING
Do not rest bundle on lower by-pass seal.
9. Partially insert bundle to point of Lif.
10. Insert eye bolt in tapped hole provided on top of front tubesheet.
11, Transfer support to eye bolt of front tubesheet.
12. _ Insert bundle completely.
WARNING
Front tubesheet should be positioned with lifting
hole at 12 o'clock location (ie. straddling the
top two water channel studs). Failure to
comply with requirement will result in
interference between the water channel bypass
partition and the tubes.Revisions | C)RBL236 | @RBL981 ) @RBO.076 | (RBS-6II | (RDA SH
bine |osanr —_fosr7io2 | ovaeiss__| 1002/98
12401
Page 5 of 8
NOTE |
In some designs a rear shell flange gasket is
‘used rather than an o-ring. For these designs,
position gasket on rear shell flange. Hold with
‘Dow Corning silicone adhesive or equivalent.
Allow to set and cure. |
Install packing plate over rear tubesheet with packing plate o-ring towards shell
flange.
‘WARNING
Do not rip rear tubzsheet o-ring while installing
acking plate.
5, Torque packing plate nuts to level liste in Table 1, Column 1 Page 6).
6. Position supply channel gasket and install supply channel.
7. Torque supply channel nuts to level listed in Table 1, Column 1 (Page 6).
8. Position return channel gasket and install return channel.
a ‘Torque nuts on inner, rectangular stud pattern on return channel to level listed in
Table 1, Column 1 (Page 5) in sequence illustrated in Figure 1.
10. Position flat washers, spring washers and nuts on cuter bolt circle of rerum
channel, where applicable.
11, Hand tighten nuts, plus 1/8 turn, in sequence illustrated in Figure 2.
12. Follow steps 21-28 of standard cooler procedure.Revisions | ()RBL-236
ov1692
Q)RBL-981
oseai | 09/17/92
@)RBO-076 | (MRBS-611
07/2893
(RDA-S34
10/02/98
IV. Single Tubesheet Version of Double Tubesheet Design:
1L2401
Page 6 of 8
Follow procedure for double tubesheet cooler design, however, prior to placing the
water channels on the cooler, perform a shell side pressure test.
‘This is in order to
verify leak-tight tube to tubesheet joints. The shell should be pressurized to the shell
side design pressure of the cooler or 150 PSIG, whichever is less.
RECOMMENDED TORQUE VALUES FOR
SA-193 GRADE B7 STUD MATERIAL
COLUMN 1 COLUMN 2
Cc Gasketed Joint Non-Gasketed Joint
Tensile Torque (Ft-#) Torque (Ft-#)
Nominal ‘Stress Area
Bolt Size (Sq. In.) | Minimum | Maximum | Minimum | Maximum
1/4-20 UNC 0.0318 & 10 3 4
$1618 UNC_| 0.0524 a 19 6 1
3/8-16 UNC 0.073 30 33 u 12
7/16-14 UNC 0.1063 47 53 17 19
1/2-13 UNC 0.1419 7 80 26 28
9/16-12 UNC 0.1820 105 us 37 41
pee UNC 0.2260 145, 160 SL 57
3/4-10 UNC 0.3340 255 280 90 100
I 718-9 UNC 0.4620 380 420 140 155
1-8 UNC 0.6060 570 630 210 230
L-V8, 8UNC | 0.7630 765 845 270 300
1-1/4, 8 UNC 0.9690 1075 1195 385 420
1.3/8, 8 UNC 1.1550 1410 1565 500 isostaceilRevisions | (1)RBL-236 | @)RBL-981 | (3)B0-076 | “RBS-611 | (S)RDA-534
ovies2 —_fosras2 former | ores | 1002/98
Page 7 of 8
eB 8 4 2 22 18
ot TTT
24-O— -o—10
ab ~bo6
a. _$- 2
io 9-29
ae —
o~$- el 23
3-4 ae eee eae a
+o—e—€—6—0—0—0+
7 4 2d | | 4 i
FIGURE_1: EXAMPLE OF RECTANGULAR
TORQUING SEQUENCERevisions | (RBL-236 | @RBL-981 | (3)RBO-076 | (RBS-611 | (S)RDA-534
oe oiies2 fosaase | oors2 [areas | owe
IL-2401
Page 8 of 8
4 10
\ !
|S. 6
FIGURE 2: EXAMPLE OF CIRCULAR
TORQUING SEQUENCE