FUNCTION CHECK LIST


PROJECT :

SERVICE : MEP SYSTEM


LOCATION : Date : _____________
CHILLER NO.: FLOOR NO.:
MODEL: BRAND: S/N:
DRAWING REF:

Status
Recorded Acceptance
No Description Of Works Remarks
Parameters Range Passed Fail

A. MAIN DATA OF CHILLER


1 Chilled Water Set-Point Follow the Design
2 Evap. Entering Water Temp 9 - 17oC

3 Evap. Leaving Water Temp 5.5 - 12oC


4 Cond. Entering Water Temp 28 - 32oC
5 Cond. Leaving Water Temp 34 - 37oC
6 Each Stater Current Line Not more than 100%
7 Evap. Refrigerant Pressure [-68] to [-41] Kpa
8 Cond. Refrigerant Pressure 13,7 - 82,7 Kpa
9 Oil Tank Temp Running 35 - 72oC
10 Differential Oil Pressure 124 -151 Kpa
Interval upper and
11 Operate Oil Level
lower sign glass
12 Purge: Daily Pump Out 20 min/day
B. CONTROL PANEL
1 Voltage [V]
2 Ampere [A]
3 Check Contactors [Visual Check]
4 Check Panel Status [Visual Check]
C. MOTOR
1 Check Operation of Motor
2 Visual Check

D. COMPRESSOR
1 Compressor Ref. Discharge Temp
2 Oil Tank Pressure
3 Oil Pump Discharge Pressure
4 Oil Differential Pressure
5 Oil Tank Temp
6 Inboard Bearing Temp
7 Outboard Bearing Temp

1/2
Status
Recorded Acceptance
No Description Of Works Remarks
Parameters Range Passed Fail

E. OTHERS

1 Check the General Operation of the Unit


Check Operation of Lubrication System,
2
Verify the Oil Level
3 Check for Leaks [if any]
4 Check Purge
5 Check Oil Heater

6 Check Piping Lines [Visual Check]

7 Check Exchangers [Visual Check]


8 Check Evaporating Units [Visual Check]
9 Check Condensating Units [Visual Check]
10 Check Pumps [Visual Check]

NOTES:

Please follow symbol below to stick

[ √ ] : If "YES" [ X ] : If "NO"
Passed = Working Fail = Not Working

Report by: Witness by: Witness by:

Name: Name: Name:


Date: Date: Date: