Professional Documents
Culture Documents
2 Site Possession - Insurance & Bonds
2 Site Possession - Insurance & Bonds
2 Site Possession - Insurance & Bonds
TEKNOLOGI MARA
UiTM Cawangan Perak,
Kampus Seri Iskandar
Bandar Seri Iskandar, 32600
Bota, Perak
POST-CONTRACT ADMINISTRATION
PRACTICE
(DQS 359)
GROUP 2
1.SITE POSSESSION
2. INSURANCE AND BONDS
NAME STUDENT ID
FADHLI ZIL IKRAM BIN NAZARI 2017204986
SYED AMEEER BIN SYED ABDUL 2017202158
HAMID
DEFINITION
Possesion of site • Access to the Site for the Employer, his professional team and necessary
contractors employed by the Employer.
Duration of • Starts from the date for possession of site to completion date and inclusive
of extended time if the contractor is granted extension of time.
posession
Contract period • Possession will usually provide the contractor with such exclusive
occupation and use the site as required constructing the works
RELATED CLAUSE
c)The extent and nature of the works, materials and goods necessary for the completion of the works
d)Means of communication with and access to the site
e)Accommodation he may require
f) Contractor responsible for all the information that affects the tender
• 11.2 any information or document forwarded by the government to the contractor shall not relieve the contractor of his obligations
under the provisions of this clause
PROCESS OF SITE POSESSION
• The contractor must provide performance bond or performance guarantee sum on the date of
possession of site (clause 13)
• 5% from contract sum to secure the due performance of the obligation under this contract by the
contractor – no work under this contract shall commence if
• Employer is obligated to give possession of site to allow contractor to carry out his work.
• The date of possession is stated in letter of acceptance sent to contractor and appendix of condition of
contract in contract documents.
• Usually the date of submission of the construction site is 2 weeks after the date (la)
• Within 2 weeks - the purpose to provide opportunities for the contractor to provide necessary
preparations before starting work on site
CONT’D
• The extent of possession that must be given to the contractor is not necessarily to be
the whole site. (clause 38.1)
• Employer is not deemed to guarantee possession due to events outside his control. For
example, employer is not liable if contractor is prevented from gaining access by third
party such as unlawful picket.
CONT’D
Nobody else has the right to access the site except for:
• S.O or his representative who have the rights to access the site at any time (clause
46.1(a)),
• Other contractors engaged by government and their workers executing works on or
near the site (clause 46.2),
• Employer and any authorized persons to investigate causes of accident, failure or other
events connected with the works (clause 45).
DELAY IN GIVING SITE POSSESSION
• S.O has the power to defer/change the giving of possession of site for whatever reason
• There are two situations of duration ; not exceeding 90 days or exceeding 90 days from
the date for possession fixed in the Letter of Acceptance.
• If delays is not exceeding 90 days ( clause 38.4) :
Original date of New date of site
site possession <90 days possession
CONT’D
• If delays in giving possession of the whole site has exceeded 90 days (clause 38.5) :
S.O obliged to notify Contractor has to
the contractor in 14 days reply within 14 days
writing of the causes from the datereceiving
of delay notice of S.O
If delays in giving possession for part of the site exceeded 90 days (clause 38.6) :
-contractor have 2 option
Option 1 :
To request for the affected
Option 2
part to be omitted from the
contract
• Contractor is obligated and could be compelled to surrender possession of the site upon the
completion of the works or when the contract is rescinded or terminated.
• The S.O will give written to the contractor specified such as default and requiring the contractor to
remedy such as default with 14 days of the receipt of the default notice or any period determined by the
officer named in appendix .
• Events of default
Clause 51.1 (a) (i) contractor fails to commence work within two (2) weeks after date of site possession.
Clause 51.1 (a) (iii) fails to proceed regularly and diligently with the performance of his obligation of
contract.
PAM CONTRACT
• The insurer agrees to give the insured some benefit (usually financial
compensation) if a specified event occurs. The event must involve some
uncertainty about whether or when it will happen.
WHY INSURANCE IS IMPORTANT?
RESPONSIBILITY
Property Insurance
Liability Insurance
PROPERTY INSURANCE
Liability = Responsible
LIABILITY INSURANCE ( CONT’D )
Indemnity = protection
SALIENT FEATURES OF AN INSURANCE
CONTRACT
Surety Bond = A
contract between
both parties
BID BONDS
Usually a percentage of the contract price used to
guarantee that if a contractor does not accept a bid
that is awarded to them that the owner will be
compensated by the surety for an amount up to the
amount of the second lowest bidder.
PERFORMANCE BOND
Ifa contractor defaults the surety is obligated to
complete the project up to the original value plus the
value of any change orders that were approved by
the surety