1.

Clearance between the cable tray and the ceiling must be less than 25
cm.
2. The distance between each two cable supports must not be less than
120cm
3. For every 1.5-meter, support is needed for flexible conduit.
4. Complete dressing of the cables with proper spacings coming in ladder
and ensure 20% spare ladder capacity.
5. Ensure 20% spare tray capacity and proper cable spacing while pulling
other cables.
6. Provide permanent tagging on cables.
7. Bonding Jumpers must be firmly fixed
8. Use Zinc Spray to avoid corrosion
9. R05 socket outlet height should be 300mm from FFL except which
coming above the counter.
10. For home runs pull boxes should be separate for normal and emergency.

THHN (Thermoplastic High Heat-resistant Nylon coated),

XLPE, THHN (The


the cei XLPE, TH
than 25cm