Professional Documents
Culture Documents
SITE PROGRESS MEETING 53 20220902 Minute
SITE PROGRESS MEETING 53 20220902 Minute
AOB
1 To improve the casting workmanship. ALL agree DINGXIN first 2sty slab surface
Present 2sty casted surface powerfloat not workmanship not to standard,
well done, may incured additional works to it will involve redo and re
redo retouchup. touch up works.
2 To use the floor harderner according to ALL agree Any wastage to charge
expired date accordingly
3 wheel stopper welding starter bar ALL agree NO WELDING NO CASTING
4 To use drop in anchor for column ALL agree
5 Workers cannot stand at trailer while ALL agree
hoisitng in progress
6 drop in anchor for façade & column ALL agree
installation
7 To use bracket for façade, rebar close to ALL agree
cover, cover facing façade to be accurte.
8 steel plate mould for façade starter bar ALL agree No steel plate no casting
9 table form 50% retain for upper floor casting ALL agree
10 toilet kerb & riser kerb by SingXin & SMG ALL agree
11 genset tap to column rebar ALL agree
12 wheelstopper to be cast insitu, cost include ALL agree
plastering
13 broom quality to improve ALL agree
14 Table form to dismantle in 28 days ALL agree
15 Crawler crane to share between CHB& SX ALL agree
20 For the starter bar for facade, lower the top wall DING XIN
top rebar for future adjustment and recess the & SMG
top cover for future rebar bending. please submit
the MOS for rectification if the starter bar out of
alignment.
21 All to ensure no flammable chemical in their ALL
storage, and ensure cable and tool in proper
condition
Ding Xing to rectifiy comment of QPS, and re ALL Need to bear the abortive
arrange for inspection, cannot direct proceed works if QPS as to hack
casting after rectifying
1no. 18m boom lift and 12m scissor lift had DING
passed to Ding Xin for structure touch up on XING
27/6/22
SMG DING XING to continue put workers to ALL
clear the structure for archi works
Safety Dont use absorber harness during façade ALL
installation. Use fix harness.
Safety 9th Sept 22 to have safety time out. All ALL
subcons to present
Safety Please check if any lower trade works at ALL All subcon to highlight to
buiilding perimeter, espciallly external maincon before proceed the
plaster works, all subcon is not allow to works.
works above other trade works or vice
verse.
Safety All subcon to be more vigilant on safety as ALL
fatality rate keep on rising.
Safety The damage scaffolding retun from ZULIN to DING
be deducted from Ding Xing and SMG XING
separately. SMG