Bata Balegzihar Edir To Adis Abeba Aspalt Road
Bata Balegzihar Edir To Adis Abeba Aspalt Road
Yitayal Wodaje
Septemberr, 2022
Debre Markos
1
TABLE OF CONTENT
TITLE PAGE
1. Introduction------------------------------------------------------------------------------------------- 1
3. Methodology----------------------------------------------------------------------------------------- 2
6. Conclusion ------------------------------------------------------------------------------------------ 6
2
1. Introduction
Debre markos town has planned different infrastructure and service delivery projects under its
capital investment projects. Those projects will finance by world bank /ULGDP/, city
administration and other development partners. Constructing from Enatenesh residence to Bebizu
mill gravel project one from the projects which the town has planned in different kebeles of the
town administration. The implementation of this project will create employment opportunities.
However the project may have negative environmental and social impacts. Therefore before
implement the proposed project considering/take it in to account/ environmental issues through
environmental and social impact assessment/ESIA/, it is mandatory to conduct ESIA, every
project passes through screening process which provide basic information about the project
whether the project need EIA or not and to determine the schedule of the project. The screening
conducted based on environmental and social management guide line/ESMG/. To indicate the
risk of causing undesirable environmental and social effects by rating the sensitivity of the
proposed site, using impact identification and classification, checklist of impacts and detailed
questionnaires are important.
The project is located at 05 kebele administration. The city administration has a plan to
construct 1000M length gravel road in order to improve road passage condition and m-----------
width.. The project benefits the surrounding community.
3. Objectives
The objectives of the screening process of the project is to determine whether the project need
EIA or not and to know the level at which the project fall.
4. Methodology
The methodology used to carry out this screening process includes site visit, ULG report,
reviewing of guidelines.
According to environmental and social guideline the screening process has two components.
Environmental screening and social safeguard screening, the screening process help to
determine the schedule of the project. The project is evaluated based on the screening form.
3
5.1 Environmental screening
The screening determine the schedule of the project whether the project needs EIA or not by
using different checklist.
4
Roads Potential for adverse impacts
None Lo Medium high unknown
w
Soil erosion or flooding concerns/ e.g, highly
erodible soil or steep gradients/
Number of stream crossings disturbances
Wet season excavation
Creation of quarry sites or borrow pits
1.Preminary environmental information : yes/no answers and bullet lists preferred except
where descriptive detail is essential
State the sources of information available at the stage /ULG report, ULG report and
ESIA or other environmental study/ observation
Has there been litigation complaints of any environmental nature No
directed against the proponent or ULG construction works project
2. identify type of activities and likely Yes/no answers and bullet lists preferred
environmental impacts: except where descriptive detail is essential
What are the likely environmental impacts, Environmental impact
opportunities, risks and liabilities associated *soil erosion
with the project Opportunity
*employment opportunity
3. Determine environmental screening category: Yes/no answers and bullet lists preferred
except where descriptive details essential.
After compiling the above, determine which category the ULG 2
construction works falls, based on environmental impact categories 1
,2, and 3.
4. Mitigation of potential pollution: Yes/no answers and bullet lists preferred except where
descriptive details essential.
5
Does an ULG construction works project have potential to pollute the No
environment, or contradict any environmental laws and regulations?
Will the ULG construction works project require pesticides use? NO
If so, then the proposal must detail the methodology and equipment -
incorporated in the design to constrain pollution within the laws and
regulations and to address pesticide use, storage and handling
Does the design adequately detail mitigating measures -
5. Environmental Assessment Report or environmental studies required: Yes/No answers and bullet lists
preferred except where descriptive detail is essential
If Screening identifies environmental issues that require an ESIA or a study, No
does the proposal include the ESIA or study?
Indicate the scope and time frame of any outstanding environmental study. September
Required Environmental Monitoring Plan: No
If the screening identifies environmental issues that require long term or No
intermittent monitoring (effluent, gaseous discharges, water quality, soil
quality, air quality, noise etc.), does the proposal detail adequate
monitoring requirements?
6. Public participation/information requirements: Yes/No answers and bullet lists preferred except
where descriptive detail is essential
Does the proposal require, under national or local laws, the public to be Yes
informed, consulted or involved?
Has consultation been completed? Yes
Indicate the time frame of any outstanding consultation process. -
Refer to relevant legislative acts in Ethiopia. -
7. Land and resettlement: Yes/No answers and bullet lists preferred except where descriptive detail is
essential.
What is the likelihood of land purchase for the ULG construction works No
project?
How will the proponent go about land purchase? No
Will people’s livelihoods be affected in any way, therefore requiring some No
form of compensation?
Will people need to be displaced, and therefore require compensation and No
resettlement assistance?
Are the relevant authorities aware of the need for a Resettlement Process, No
involving a census, valuation, consultation, compensation, evaluation and
monitoring?
What level or type of compensation is planned? -
Who will monitor actual payments? -
6
Categorization and recommendations
Schedule 1 Project to be fed into the standard ESIA process determined by MEF
Schedule 2 Project will not require an ESIA, but will necessitate the inclusion of
environmental and social mitigation and enhancement measures in the
design and implementation of the project through the use of standard
construction contract clauses and an environmental management plan
Schedule 3 Project is not subject to environmental assessment as no potential
impacts are anticipated.
Sign -------------------
Date ------------------------
7
5.2 Social safeguards screening
The social impact screening using checklists gives us general information about the project
social impact.
Site Sensitivity
Issues
Low Medium High
Involuntary resettlement
Checklist of impacts
8
New settlement pressures created
Other (specify):
Recomondation
Requires an RAP is to be submitted on date
9
Sign ------------------
Date ---------------------
6. Conclusion
Different infrastructure and service delivery projects planned by Debre Markos city
administration and from those projects from Enatenesh residence to Bebizu mill is one of them.
The implementation of the project will have positive impact and it may also have negative impact
on the environment. Considering environmental and social impact assessment is important and
mandatory before implementing the project using environmental and social management
guideline. According to the guideline every project should pass through screening process which
determines the schedule of the project and the process has two components environmental and
social screening having different checklists. According to the screening process the proposed
drainage project falls under schedule 2, Project will not require further environmental studies.
REVIWED BY:
Name ------------------------------
Signature------------------------
Date-------------------------------
10