MINESCAPE REPORT - VOLUME CUTFILL

PEROJECT ID: KMP_PRG_0922 05 October 2022


POLY CUTFILL VOLUME AREA RECOVERY
KMP_BB5 CUT 104,420.29 14,061.97 100
KMP_BB5 FILL 286.4 195.92 100
KMP_BB7 CUT 29,322.56 4,518.23 100
KMP_BB7 FILL 65.5 136.14 100
KMP_BB9 CUT 484,828.32 49,639.26 100
KMP_BB9 FILL 451.65 530 100

PERIOD CUM. SEPT-2022 CUM. AUGUST-2022 CUM.THIS MONTH


KMP_BB5 NETT 104,133.89 93,279.51 10,854.38
KMP_BB7 NETT 29,257.06 - 29,257.06
KMP_BB9 NETT 484,376.67 461,617.52 22,759.15
SUM.TOTAL 617,767.62 554,897.030 62,870.590

COAL BB9 MT 5,042.335


BCM 3,878.719
OB BB9 BCM 18,880.431
OB BB5 BCM 29,257.060
OB BB7 BCM 10,854.380
SUM.TOTAL 58,991.871 BCM

COAL BB9 MT 3,878.719 5,042.335 MT


COAL BB5 MT -
COAL BB7 MT -
5,042.335 MT
STRIPPING RATIO TOTAL 11.70 SR