Professional Documents
Culture Documents
UAP Docs 301 Gen Condition Summary
UAP Docs 301 Gen Condition Summary
UAP Docs 301 Gen Condition Summary
General Conditions
A Summary
October 7, 2022
United Architects of the Philippines General Conditions October 4, 2022
The General Conditions herein defines the relationship between the Owner, Architects,
and the Contractor in performing the work. The given provisions are implemented to maintain
a high standard of professionalism in the execution of the construction, also to engage the
proper responsibilities that would be fair for all parties including payments and contract
documents. The General Conditions are based on the standard practice in the construction
industry, whereby the Architect provides his expertise as the primary professional hired by the
Owner to design and manage a project that will be carried out by a General Contractor.
SECTION I
DEFINITIONS AND DOCUMENTS
ARTICLE 1: DEFINITIONS
It is necessary to know and understand first the definition of terms to be used in the
contracts and construction process to prevent misconceptions and disagreement.
1. Contract Document – consists of the following documents: Agreement, General
Conditions, Special Provisions, Specification, and Drawings.
2. Owner – Person or user ordering the project.
3. Architect – Commissioned by the Owner, acting on his behalf.
4. Engineer – Named in contract documents
5. Project Representative – Full-time Construction Inspector hired by the Owner
6. Contractor – The one whose proposal has been accepted and the contract is awarded.
7. Sub-contractor – Have a direct contract with the Contractor.
8. Surety – Provides the guarantee for the Contractor’s bonds.
9. Proposal Bond – Cashier’s check or surety bond accompanying the proposal submitted.
10. Performance Bond – A guarantee to execute the work.
11. Payment Bond – A guarantee to pay all obligations.
12. Guaranteed Bond –A guarantee to the quality of the materials and equipment installed.
13. Agreement – A contract between the Owner and the Contractor undertaking the project.
14. Advertisement or Invitation to Bid – Notice made by the Owner to potential bidders
outlining the details of the planned project.
15. Bid Bulletin – Issued to bidders before the date of bidding.
16. Drawings – Graphical presentations of the project.
17. Special Provisions – Instructions issued prior to the bidding to supplement or modify
contract documents.
2
United Architects of the Philippines General Conditions October 4, 2022
with the contract documents. Both the Contractor and Architect shall collectively prepare a
schedule. Note that the Contractor shall not execute the work without the proper Drawings and
instructions.
ARTICLE 5: SHOP DRAWINGS
Two copies of all shop or setting Drawings and the schedule shall be prepared by the
Contractor promptly at his own expense and pass it to the Architect to make corrections. When
the Architect requires adjustments, the Contractor shall provide two corrected copies. Further,
the Contractor is required to check all the Drawings of the Sub-contractors to assure accuracy.
The shop drawing shall be dated and contain the name of the project; the descriptive names of
the equipment, materials, and item numbers; and the location where it is to be installed; which
are numbered consecutively and represent all working and erection dimensions, arrangements
and sectional view, necessary details, and kind of materials and finishes. These are
accompanied by a letter of transmittal in duplicate containing pertinent data. The Architect,
who is responsible for the accuracy, shall receive three sets of shop Drawings submitted by the
Contractor.
SECTION II
LAWS, REGULATIONS, SITE CONDITIONS, PERMITS, AND TAXES
certification shall be submitted upon completion of the work before final payment, as required
by the Architect.
SECTION III
EQUIPMENT AND MATERIALS
ARTICLE 8: GENERAL
All materials and equipment must conform to all laws, ordinances, regulations, and
building codes, including revisions or adjustments, and the Contractor shall obtain the
necessary permits and pay the required fees. If the work is delayed due to the Contractor's
failure to adhere to the terms of this section, he is responsible for all damages.
ARTICLE 9: EQUIPMENT
The Architect and the Engineer shall refer to certain equipment by name and catalog
number. Before the Contract is signed, the Contractor must provide a complete list of all
suggested substitutes. This list must be provided in writing. The Contractor shall furnish three
copies of the complete compilation of catalog data for every manufactured item of equipment
and all components to be used in the work, approved by the Architect and Engineer before the
equipment is ordered.
ARTICLE 10: MATERIALS, FIXTURES, APPLIANCES, AND FITTINGS
FURNISHED BY THE CONTRACTOR
The Architect must be given a list of the proposed manufacturers, material men, and dealers.
All transactions with manufacturers are all through the Contractor, including the imported
materials. The manufacturer to be approved shall have a good reputation and the materials to
be furnished shall be properly coded in accordance with the given standards, all new, and of
the best grade.
For the sample of materials, three labeled samples shall be submitted and are adequate
in size together with three copies of the letter of transmittal. Materials shall not be ordered until
the written approval of the Architect is provided. If a substitution is needed it shall have written
approval from the Architect. However, no extension of time or substitution of materials shall
be allowed due to the negligence of the Contractor. The Contractor must provide the Architect
with as many samples of the materials to test. The Contractor shall bear the cost for shipment,
handling, and testing of samples.
A suitable space for storage shall be provided by the Contractor, and platforms and
weather protection are required especially for materials affected by moisture.
5
United Architects of the Philippines General Conditions October 4, 2022
SECTION IV
PREMISES AND TEMPORARY STRUCTURES
with a wooden floor raised above the ground, windows, doors and locks, tables, closets,
blackboard, tack board, benches, and racks for Drawings. Approximately 12 square meters
of room shall be provided for the Architect’s use.
2. Temporary Housing for Workers – The location of temporary housing shall be permitted
and designated by the Owner and Architect. Nobody is permitted to sleep or prepare food
inside the premises.
3. Temporary Sanitary Facilities and First Aid Station – Ample sanitary toilets and other
conveniences with water connections for the use of personnel and laborers on the work.
4. Temporary Barricades and Guard Lights – It is necessary for the protection, proper
prosecution, and completion of work.
5. Temporary Water, Power, And Telephone Facilities – The Contractor shall make all
necessary arrangements, and pay them, to the local utility companies in the provision of
such facilities.
6. Temporary Signs – No signs or advertisements will be allowed to be displayed without the
Architect’s approval.
7. Temporary Roadways – These shall be within and adjacent to the site to provide access to
the building.
8. Temporary Stairs, Ladders, Ramps, Runways – All such apparatus, equipment, and
construction shall meet all requirements of Labor Law and other local laws applicable.
9. Temporary Elevators and Hoists – No hoists shall be constructed at such locations as will
interfere with or affect the construction.
10. Temporary Enclosures – All exterior doors shall be equipped with self-closing hardware
and padlocks, and temporary sash frames.
11. Temporary Or Trial Usage - The Owner has the privilege of such temporary or trial usage.
SECTION V
PROTECTION OF WORK AND PROPERTY
7
United Architects of the Philippines General Conditions October 4, 2022
fire extinguishers for fire protection thus, smoking is prohibited too. Further, old materials shall
be carefully piled to minimize hazard areas.
As for existing trees and plants, they shall be boxed to protect them from damage. There
shall be approval from the Owner or the Architect if cutting and removing trees and plants are
needed and are replaced by the Contractor at his own expense. Those trees that need to be
transplanted within 50 meters of the building lines shall be done by the Contractor. Providing
natural or artificial drainage is necessary too, especially when the work obstructs the natural
flow of any bodies of water.
ARTICLE 17: PROTECTION OF ADJACENT PROPERTY AND EXISTING
UTILITIES
It is the Contractor’s sole responsibility to protect adjacent property and existing
utilities as provided by law and the Contract Documents. If damage happened because of his
negligence, he shall be liable and bear all the cost of his doing.
ARTICLE 18: PROTECTION OF LIFE, WORK, AND PROPERTY DURING AN
EMERGENCY
In case of an emergency affecting the safety of life, work, or the adjacent property, the
Contractor is authorized and permitted to act, even without instructions from the Architect, to
prevent loss or injury. Any compensation claimed by the Contractor on account of emergency
work shall be determined by the agreement of arbitration.
SECTION VI
LABOR, WORK, AND PAYMENTS
completion. The Owner, Architect, and representative shall have access to and inspect the work
site while the Contractor provides proper facilities for the said activity. In case of defective
work, it may be condemned by the Architect at any time before the final acceptance of the
work. Whenever there is an increase or decrease in quantities in the work, it shall not exceed
5% of the discrepancy.
The Owner may at any time order extra work or make changes in writing yet, it shall
be validated in the contract and with notice of sureties. If there is a change in sub-surface
conditions, the Architect shall be called immediately. With the adjustment of the contract
document, the Contractor shall modify it in writing and furnish a proportionate additional
performance bond. The value of extra work or change shall be determined in any one of the
following: by estimate and acceptance in a lump sum, by unit prices stipulated in the Contract
which do not exceed 25% of the original contract, or by actual direct cost plus 15% for
Contractor’s profit, overhead, and tax. Any claim for adjustment must be asserted within 15
days of the date the change is ordered unless the Architect requires an extension. Also, the
Architect has the authority to make minor changes to the work which does not involve extra
cost and is consistent with the design. Moreover, the Owner reserves the right to have such
extra work done by any other person, firm, or corporation. If the Contractor claims for an extra
cost, he shall give the Architect written notice within fifteen days after the receipt of such
instruction, except in an emergency.
At the completion of work, the Contractor has responsibility for cleaning up and
keeping the premises free from waste materials or rubbish. The Owner has the right to take
possession of any completed portions of the work. Neither shall it be deemed a waiver by the
Owner of the rights to claim for damages due to delays in the completion of the work. Upon
due notice from the Contractor that he has completed the work, the Architect shall inspect the
project. Substantial completion shall mean that the value of the work completed shall not be
less than 98% of the contract amount. The Architect shall issue a Certificate of Completion
with respect to the work and to any substantial part of the work which has been completed to
the satisfaction of the Architect and occupied by the Owner.
After the issuance of the Certificate of Completion, or within 15 days after its
expiration, a Period of Making Good of Known Defects or Faults is executed by the Contractor
at his own expense in a period of not more than sixty calendar days. In this period, the
Contractor shall search for the cause of any defect, unless such fault is not liable under the
Contract. The Owner shall provide written notice to the Contractor to carry out such work.
9
United Architects of the Philippines General Conditions October 4, 2022
filed, failure of the Contractor to make payments, reasonable doubt that the Contract can be
completed for the balance then unpaid, and/or damage to another Contractor.
The Breakdown of Work and Corresponding Value serves as the Architect's guide for
estimating the value of the work completed by the Contractor. Within 15 days from the date of
approval of a Request for Payment or of issuance of a Certificate of Payment by the Architect,
the Owner shall pay the amount. The Owner’s failure to pay the amount involved would be
subject to payment of interest based on banking loan rates. The Contractor shall punctually pay
all costs obliged to him. If required, he shall furnish the Owner with a statement that all
payments under this Contract have been duly paid. No payment shall be made on contracts
more than 65% of the Contract Price.
There are other requirements needed before the final payment including a Certificate of
Final Building Occupancy, Certificate of Final Inspection of the utilities, Original and 3 sets
of prints of “As-Built Drawings”, 3 copies of Directory of Panel Boards and a list of circuits,
3 copies of Instruction and Manual for operating and maintaining fixtures and equipment, 3
copies of Keying Schedule, and a Guarantee Bond equivalent to 30% of the Contract Price.
The Architect shall proceed and verify the work, create the final estimates, certify the
work has been completed and accept it before acceptance and final payment. The Owner shall
pay the Contractor promptly, provided that final payment on the contract shall not be made
until the Contractor has submitted a statement showing that all taxes due and all obligations for
materials used and labor employed in connection with this contract have been duly paid; and
provided, further. If correction of work after final payment is needed, the Contractor shall
remedy any defects and pay for any damage to other work resulting which will appear within
a period of one year from the date of acceptance of work by the Owner. Within three months
of the date of final payment, the Owner's retainer under the terms of the contract must be
released.
SECTION VII
CONTRACTOR – SEPARATE CONTRACTORS – SUB-CONTRACTORS
RELATIONS
11
United Architects of the Philippines General Conditions October 4, 2022
The Contractor shall afford other Contractors’ reasonable opportunity for the
introduction and storage of their materials and the execution of their work. He is also
responsible for all cutting, fitting, or patching of his work that may be needed to receive or be
received by work of other Contractors. If any part of the Contractor’s work depends on any
work of the other Contractor, the Contractor shall inspect and promptly report to the Architect
any defect that renders. Whenever the Contractor causes damage to any separate Contractor on
the work, the Contractor agrees to settle with the other Contractor by agreement or arbitration
and to relieve the Owner of any liability which may arise.
ARTICLE 25: SUB-CONTRACTORS
No contractual relationship between any Sub-contractor and the Owner shall be
established by anything in the Contract Documents, 15 days or more before the deadline for
bids. To clarify the aspects of the job for which the subcontractor's competency will be
assessed, the contractor must consult with the architect. The Contractor agrees that he is fully
responsible for the acts and omissions of his Sub-contractors.
ARTICLE 26: CONTRACTOR – SUB-CONTRACTORS RELATIONS
The Contractor agrees to be bound to the Sub-contractor by all obligations. He shall
pay the Sub-contractor upon payment of certificates, on-demand for his work or materials as
far as executed as provided by the contract documents, and just share of any fire insurance
money received by the Contractor. The Contractor shall not demand de liquidated damages to
the Sub-contractor and give him an opportunity to be present and to submit evidence in any
arbitration involving his rights.
On the other hand, the Sub-contractor agrees to be bound to the Contractor by the Terms
of Agreement, General Conditions of the Contract, the Drawings and Specification. Also, he
has the duty to submit to the Contractor applications for such payment and make all claims for
extras, extensions of time and for damages, and delays.
The Contractor and Sub-contractor agree that their rights and obligations and all
procedure shall be analogous to those in the contract.
12
United Architects of the Philippines General Conditions October 4, 2022
SECTION VIII
SUSPENSION OF WORK AND TERMINATION OF CONTRACT
13
United Architects of the Philippines General Conditions October 4, 2022
SECTION IX
RESPONSIBILITIES AND LIABILITIES OF CONTRACTOR AND OF OWNER
14
United Architects of the Philippines General Conditions October 4, 2022
SECTION X
AUTHORITY OF ARCHITECT, ENGINEERS, AND PROJECT
REPRESENTATIVES
but failing to do so does not relieve the Contractor from the responsibility of following the
Contract Documents. The Architect shall decide all questions which may arise as to the quality
and acceptability of materials furnished and work performed. In judging the work performance,
he shall side neither with the Owner nor the Contractor. In the event of termination of the
employment of the Architect, the Owner shall appoint a capable and reputable Architect against
whom the Contractor make reasonable objection and any dispute in connection there shall be
subject to arbitration.
ARTICLE 35: AUTHORITY AND RESPONSIBILITIES OF THE ENGINEERS
The Engineers are solely responsible for their respective designs, computations, and
other professional services they rendered. They shall assist the Architect in the general
supervision and direction where their professional services are concerned subject to the terms
and conditions. Engineers shall inspect the work for conformance with the approved Drawings
and Specification.
ARTICLE 36: AUTHORITY AND DUTIES OF THE PROJECT
REPRESENTATIVES, RESIDENT
Project Representatives, Resident Architects, Resident Engineers, or Construction
Inspectors selected by the Architect and employed by the Owner can be stationed on the project
to help the Architect and Engineers. They have the duties that are stipulated in the Special
Provisions of the Contract. In case of any dispute arising, they shall have the authority to reject
materials or suspend the work until it is decided by the Architect. Nothing in the provisions of
this article will relieve the Contractor from the responsibility of performing the work per the
Drawings, Specification, and other Contract Documents.
SECTION XI
SCHEDULE OF TIME LIMITS
16
United Architects of the Philippines General Conditions October 4, 2022
2. Contract Sum
15 days from the receipt of Notice to
2.1 Contract Sum Breakdown 22.01
Proceed
Within 15 days after receipt of instruction
2.2 Claim for Extra Cost involving extra cost or after recognition of 20.08
delay due to Owner’s the fault
3. Progress Payment
3.1 Architect’s Action on
15 days after receiving request for payment. 22.04
Payment Request
3.2 Owner’s Action on
15 days from date of Architect’s approval 22.07
Payment Request
3.3 Release of Retention 3 months after the date of final payment 22.14
4. Correction of Work
The Contractor must pay expenses within
4.1 Correction Before Final 10 days from removal by the Owner, the
22.13
Payment Owner may sell the materials after 10 days,
from written notice of intent to sell.
For a period of one year from the date of
4.2 Correction After Final acceptance of work by Owner, repairs and
31.05
Payment corrective work shall be done 5 days after
written notice by Owner
5. Sub-contractor’s Claim
making claims for the extra cost is one week 26.02
for Extra Cost
Upon 15 days written notice to Owner and
Architect for the following reasons:
1. public authority orders to stop or
suspend the work for 90 days through
no fault of the Contractor;
2. Architect does not act upon requests
6. Contractor’s Right to
for payment within 15 days after
Suspend or Terminate 17
presentation;
Contract
3. Owner does not act upon request for
payment within 15 days after
certification; and/or
4. Owner does not pay Contractor the
agreed sum within 30 days after
arbitration
7. Owner’s Right to
after giving 15 days written notice 28
Terminate Contract
8. Disputes If Architect does not decide within 15 days 33.04
9. Bonds and Insurances
Shall not be cancelled by insurance
9.1 Contractor’s Liability
company without 10 days’ written notice to 31.01
Insurance
Owner
9.2 Contractor’s Performance remain in effect until replaced by
31.03
and Payment Bond the Contractor’s Guarantee Bond.
9.3 Contractor’s Guarantee effective for a period of one year
31.04
Bond commencing from the date of acceptance
17