MEMORANDUM

Ref. No. : EPC-HSE-MEM-012

DATE : April 05, 2021

TO : ALL MCC Project Site

FROM : HSSE DEPARTMENT – HEAD OFFICE

Mandatory Requirements of having Material Recovery


SUBJECT : Facilities with standard segregation to all Project Site

In Line with the Republic Act 9003 also known as Ecological Solid Waste
Management Act, under Section 33, we are mandated that all project must have a
designated area for the generated waste of each project site. Standard category for
proper segregation is align to the construction waste given below:

 Metal Scrap
- Rebars
- Mixed metals (C-purlins, pipes, angle bars, galvanized Iron, Wire
Mesh, Architectural Frames)
- Other if any
 Wooden Scrap
- Phenolic Boards
- Dimensional lumber
- Corrugated cardboards and Papers
- Other if any
 Debris
- Concretes
- Rocks
- Damage Bricks
- Other if any
 Plastic Scrap
- Plastic Bottles
- Other if any
 Hazardous waste
- LED Lights
- Medical waste
- Empty paint gallon/ spray
- Other if any
Sample design are as follows:

Metal Wooden Plastic


Debris
Scrap Scrap Scrap

HAZARDOUS WASTE

Empty Paint
Gallon/Spray
LED light

Actual size and design of the MRF will be depends on the project capacity.
All Site HSSE Team are mandatory required to send their compliance report with
attached photos and visible signages in front of the area.

Thank you very much.

Prepared by:

Katherina Grace B. Malunes


Pollution Control Officer
MCC-Head Office

Noted by:

Joselito Agawin
HSE Manager
MCC-Head Office

Rey Castillo
HSSE Head,EPC

Approved by:

Frederick Tan
Deputy Head Construction, EPC