Professional Documents
Culture Documents
CONS 1011 - Conditions of Contract
CONS 1011 - Conditions of Contract
CONTRACT
INTRODUCTION
1. GENERAL PROVISION
2. THE EMPLOYER
3. THE ENGINEER
4. THE CONTRACTOR
5. NOMINATED SUBCONTRACTOR
6. STAFF AND LABOUR
7. PLANT, MATERIALS AND WORKMANSHIP
8. COMMENCEMENT, DELAYS AND SUSPENSION
9. TESTS ON COMPLETION
10. EMPLOYERS TAKING OVER
11.
DEFECTS LIABILITY
12.
MEASUREMENTS AND EVALUATION
13.
VARIATION AND ADJUSTMENTS
14.
CONTRACT PRICE AND PAYMENT
15.
TERMINATION BY EMPLOYER
16.
SUSPENSION AND TERMINATION BY CONTRACTOR
17.
RISK AND RESPONSIBILITY
18.
INSURANCE
19.
FORCE MAJEURE
20 . CLAIMS, DISPUTES & ARBITRATION
APPENDIX-General Conditions of Dispute Adjudication
Board
ANNEX-Procedural rules
INDEX of Sub-Clauses
GUIDANCE of the Preparation of Particular Conditions
FORMS of Letter of Tender
Appendix to Tender
Contract Agreement
Dispute Adjudication Agreement
APPENDIX
METHOD OF PAYMENT
TERMINATION
AVAILABILITY
INTRODUCTION
RISK ALLOCATION
GENERALLY THE CONTRACTOR ACCEPTS ALL RISKS THAT ARE NOT SPECIFICALLY
ALLOCATED TO THE EMPLOYER.
THE CONTRACTOR
SUB-CLAUSE 8.1 – “THE CONTRACTOR SHALL . . . PROCEED WITH THE WORKS WITH DUE EXPEDITION AND
WITHOUT DELAY”
CAN EMPLOY SUB-CONTRACTOR BUT RETAINS HIS OBLIGATION UNDER THE CONTRACT TO THE EMPLOYER.
HAS CONTROL OF THE SITE, THEREFORE RESPONSIBLE FOR THE CARE OF THE WORKS, FOR SECURITY,
SAFETY AND OTHER GENERAL DUTIES.
THE ENGINEER
CONTRACT AGREEMENT
EMPLOYER’S DETAILS
CONTRACTOR’S DETAILS (COMPLETED AFTER CONTRACT AWARD)
ENGINEER’S DETAIL
TIME FOR COMPLETION OF THE WORKS
DEFECTS NOTIFICATION PERIOD
ELECTRONIC TRANSMISSION SYSTEMS
GOVERNING LAW
RULING LANGUAGE
LANGUAGE FOR COMMUNICATIONS
TIME FOR ACCESS TO THE SITE
NORMAL WORKING HOURS
PERIODS FOR SUBMISSION OF INSURANCES
DATE BY WHICH DAB SHALL BE APPOINTED
SECTION COMPLETIONS (OPTIONAL)
APPENDIX TO TENDER