Revised Civil Quantities

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

PERCENTAGE OF BUILDING TO TOTALCivil

COST OF BUILDING
Quantities

Serial Activity Percentage


No. (%)

1 Excavation & Concreting Foundation 3

2 Brickwork Up To Plinth 5

3 Superstructure (Brickwork / Blockwork) 25

4 Roofing 20

5 Flooring 6

6 Woodwork (Door & Windows) 15

7 Internal Finishes (Plastering, Screeding, etc 6

8 External Finishes 3

9 Water Supply 4

10 Sanitation 8

11 Electrification 5

Total 100

Note : In arriving at the labour costs the above breakdown can be applied.

Estimate Sheet Page 1 JN/CB.


A. STEEL WORK Civil Quantities

1.0 Labour for cutting and bending steel bars

- 6 mm dia. to 100 mm dia. = 720 kg / day / man


- 12 mm DIA = 150 kg / day / man
- 16 mm DIA. and above = 220 kg / day / man

NB : Density of mild steel = 1,833 Kg / m3

B. PAINTING

1.0 White washing per 100 sq.mtr

- 1st coat = 12 kg lime


- 2nd coat = 22 kg lime
- 3rd coat = 32 kg lime

NB : Applicable for new surface

2.0 Vanishing per 100 sq.mtr

- 1st coat = 8 litres


- 2nd & subsequent coats = 6.5 litres

3.0 Painting using PVA and / or gloss paint per 35 sq.mtr

- 1st coat = 5 litres


- 2nd & subsequent coats = 5 litres

NB : Applicable for new surface

4.0 Painting using PVA and / or gloss paint per 40 sq.mtr

- 1st coat = 5 litres


- 2nd & subsequent coats = 5 litres

NB : Applicable for repainting surface

5.0 Painting plastered surfaces per sq.mtr

Paint = 0.11 litres / m2


Painter = 0.25 hours / m2

Estimate Sheet Page 2 JN/CB.


C. CONCRETING Civil Quantities

1.0 1 : 2 : 4 mix per cubic metre of concrete

Cement 4.35 pkts


River sand 0.35 cub.mtr
20 mm stones 0.70 cub.mtr

2 Bricklayers = 0.68 hrs


4 Helpers = 0.68 hrs
Mixer = 0.68 hrs
Vibrator = 0.68 hrs

7th day strength = 14N/mm2


28th day strength = 21N/mm2

2.0 1 : 2 : 3 mix per cubic metre of concrete

Cement = 7.1 pkts


River sand = 0.48 cub.mtr
20 mm stones = 0.72 cub.mtr

2 Bricklayers = 0.68 hrs


4 Helpers = 0.68 hrs
Mixer = 0.68 hrs
Vibrator = 0.68 hrs

7th day strength = 17 N/mm2


28th day strength = 25.5 N/mm2

3.0 1 : 1 : 2 mix per cubic metre of concrete

Cement = 9.38 pkts


River sand = 0.48 cub.mtr
20 mm stones = 0.72 cub.mtr

2 Bricklayers = 0.68 hrs


4 Helpers = 0.68 hrs
Mixer = 0.68 hrs
Vibrator = 0.68 hrs

7th day strength = 20N/mm2


28th day strength = 30 N/mm2

Estimate Sheet Page 3 JN/CB.


4.0 1 : 3 : 6 mix per cubic metre of concrete
Civil Quantities

Cement 3 pkts
River sand 0.3 cub.mtr
20 mm stones 0.6 cub.mtr

2 Bricklayers = 0.68 hrs


4 Helpers = 0.68 hrs
Mixer = 0.68 hrs
Vibrator = 0.68 hrs

7th day strength = 8 N/mm2


28th day strength = 13N/mm2

5.0 1 : 12 mix 50 mm thick cement blinding per sq. mtr

Cement 0.12 pkts


River sand = 0.06 cub.mtr

Bricklayer = 0.16 hrs


Helper = 0.16 hrs
Mixer = 0.02 hrs

6.0 15 mm thick cement screeding per sq. mtr

Cement = 0.32 pkts


River sand = 0.022 cub.mtr

Bricklayer = 0.37 hrs


Helper = 0.37 hrs
Labourer = 0.2 hrs

7.0 50 mm thick concrete blinding (1 : 3 : 6) per sq. mtr

Cement = 0.19 pkts


River sand = 0.018 cub.mtr
20 mm stones = 0.038 cub.mtr

Bricklayer = 0.37 hrs


Helper = 0.37 hrs
2 x Labourer = 0.4 hrs

Estimate Sheet Page 4 JN/CB.


"Points to note" Civil Quantities
One packet cement = 50 kg
= 0.035m3 or one batch box

1m3 river sand = 1.8 Tons


1m3 building sand = 1.8 Tons
1m3 20 mm stones = 2.5 Tons

One batch box = one load of standard construction wheelbarrow

When finding quantities using the ratio, always add 25% shrinkage ratio :
E.g. mix 1 : 2 : 4 (quantities per one cub.mtr concrete)
Cement = (1/7)+0.25
= (1.25/7) x 1
= 0.18 m3

Cement bags= 0.18 m3 @ 0.035 m3 / bag


= 5.14 bags

Sand = (1.25/7) x 2
= 0.36 m3

Stones = (1.25/7) x 4
= 0.71 m3

D. BLOCKWORK & BRICKWORK

1.0 100 mm thick blockwall per sq.mtr in 1 : 3 cement mortar

Block size = 350 x 150 x 100

Concrete blocks = 19 no.


Building sand = 0.012m3
Cement = 0.12 pkts

Bricklayer = 0.6 hrs


Helper = 0.6 hrs
Mixer = 0.6 hrs
4 x Labourer = 0.6 hrs

Estimate Sheet Page 5 JN/CB.


2.0 150 mm thick blockwall per sq.mtrCivil
in 1Quantities
: 4 cement mortar

Block size = 400 x 200 x 150

Concrete blocks = 13 no.


Building sand = 0.02m3
Cement = 0.12 pkts

Bricklayer = 1.33 hrs


Labourer = 1.33 hrs

3.0 200 mm thick blockwall per sq.mtr in 1 : 4 cement mortar

Block size = 450 x 230 x 200

Concrete blocks = 10 no.


Building sand = 0.02m3
Cement = 0.12 pkts

Bricklayer = 1.33 hrs


Labourer = 1.33 hrs

4.0 200 mm thick decorated concrete brickwork / brise soleil per sq.mtr
in 1 : 4 cement mortar
Block size = 300 x 300 x 100

Concrete blocks = 20 no.


Building sand = 0.02m3
Cement = 0.12 pkts

Bricklayer = 1.33 hrs


Labourer = 1.33 hrs

5.0 100 mm thick brickwork per sq.mtr in 1 : 4 cement mortar

Brick size = 190 x 90 x 90

Burnt bricks = 50 no.


Cement = 0.15 pkts
Building sand = 0.023m3
Brickforce = 0.33m2 every 3rd course

2 x Lab (mixing) = 0.17 hrs For brickforce :


Bricklayer = 0.76 hrs Bricklayer = 0.40 hrs
Helper = 0.76 hrs Labourer = 0.40 hrs

Estimate Sheet Page 6 JN/CB.


6.0 200 mm thick brickwork per sq.mtr in 1Quantities
Civil : 4 cement mortar

Brick size = 190 x 90 x 90

Burnt bricks = 100 no.


Cement = 0.32 pkts
Building sand = 0.059m3
Brickforce = 0.66m2 every 3rd course

2 x Lab (mixing) = 0.47 hrs


Bricklayer = 1.06 hrs
Helper = 1.06 hrs

For brickforce :
Bricklayer = 0.50 hrs
Labourer = 0.50 hrs

7.0 200 mm thick waste rock wall per sq.mtr

Rock size = 200 mm on average

Cement = 0.12 pkts


Building sand = 0.02m3

Bricklayer = 1.33 hrs


Labourer = 1.33 hrs

8.0 19 mm thick plaster per sq.mtr in 1 : 3 mix

Cement = 0.16 pkts


Building sand = 0.02m3

2 x Lab (mixing) = 0.25 hrs


Bricklayer = 0.42 hrs
Helper = 0.42 hrs

9.0 13 mm thick plaster per sq.mtr in 1 : 4 mix

Cement = 0.09 pkts


Building sand = 0.015m3

2 x Lab (mixing) = 0.2 hrs


Bricklayer = 0.3 hrs
Helper = 0.3 hrs

Estimate Sheet Page 7 JN/CB.


10.0 12 mm thick plaster per 100 sq.mtr
Civil Quantities

Mix Cement (kg) Sand (m3)


1:2 979 1.371
1:3 734 1.541
1:4 547 1.532
1:5 446 1.516
1:6 360 1.512

11.0 15 mm thick plaster per 100 sq.mtr

Mix Cement (kg) Sand (m3)


1:2 1170 1.638
1:3 877 1.842
1:4 654 1.831
1:5 533 1.812
1:6 430 1.806

12.0 20 mm thick plaster per 100 sq.mtr

Mix Cement (kg) Sand (m3)


1:2 1523 2.43
1:3 1142 2.39
1:4 851 2.38
1:5 694 2.36
1:6 560 2.35

13.0 Mortar

Mix Cement / m3 Sand / m3


1:2 680 0.95
1:3 510 1.05
1:4 380 1.05
1:5 310 1.05
1:6 250 1.05

12.0 Rough cast

(a) 1 : 2 mix
Cement = 1 pkt
River sand = 0.070 cub.mtr (c) 1 : 4 mix
(b) 1 : 3 mix (most common) Cement = 1 pkt
Cement = 1 pkt River sand = 0.140 cub.mtr
River sand = 0.105 cub.mtr

Estimate Sheet Page 8 JN/CB.


13.0 Blockmaking using 3 men per dayCivil Quantities

- Hollow blocks = 120 no.


- Roof tiles = 100 no.
- Paving Flags = 25 no.

Honey comb bricks will require one tenth mortar (material for blockmaking)
and half labour of blocks

14.0 Cement pointing to brickwork

(a) Cement = 0.023 bags / m2


(mortar 0.0018 m3)
Building sand = 0.0016 m3
2 x lab (mixing) = 0.015 hrs
Bricklayer = 0.83 hrs
Helper = 0.83 hrs

(b) Cement pointing per 100 sq.mtr in 1 : 3 cement mortar

Cement = 155 kg
Building sand = 0.32 m3
Labour = 12 hrs

15.0 Face bricks per sq.mtr

Face bricks = 65 no.


Cement = 0.15 pkts
Building sand = 0.023m3
Bricklayer = 0.059 hrs
Helper = 0.095 hrs

E. OTHERS

1.0 Road works

1. Grader = 83.6 sq.mtr / 0.5 hrs 4. F.E.L. = 76 cub.mtr / 2 hrs

2. Roller = 83.6 sq.mtr / 0.4 hrs 5. Truck (6 m3) = 76 cub.mtr / 15.6 hrs

3. Bowser = 83.6 sq.mtr / 0.2 hrs

Estimate Sheet Page 9 JN/CB.


2.0 Asphalting floor Civil Quantities

Primer = 2 litres / sq.mtr


Stellalite 5.70 = 18 kg / sq.mtr

3.0 Excavations

(a) One Labourer = 2.67 hours / m3


Loading = 4 labourers @ 0.33 hours / m3
Tipper = 0.67 hours / 5.5m3 average distance of 3 km

(b) Waste rock / hard-core / m3

Collect, spread and compact :


- F.E.L. = 0.17 hours / m3
- Loading = 4 labourers @ 0.33 hours / m3
- Tipper = 0.67 hours / 5.5m3 average distance of 3 km
- Spread and compact :
1 x labourer = 4 hrs / m3

(c) Laterite / m3

Collect, spread and compact :


- F.E.L. = 0.17 hours / m3
- Loading = 4 labourers @ 0.33 hours / m3
- Tipper = 0.67 hours / 5.5m3 average distance of 3 km
- Spread and compact :
1 x labourer = 3.5 hrs / m3

(d) - In manholes or trenches 1.5 metres deep :


Labourer = 2.5 m3 / shift (8 hrs)
- Surface excavation not exceeding 150 mm :
Labourer = 15 m2 / shift (8 hrs)
- Returning filling in including compaction :
Labourer = 6.5 m3 / shift (8 hrs)
- Forming embankments including compaction :
Labourer = 4.0 m3 / shift (8 hrs)
- Remove earth in barrows (distance 30m to 50m) :
Labourer = 2.5 m3 / shift (8 hrs)

4.0 Floor tiling

Floor tiles = 6.75m2 / box @ (300 x 300 x 75 no.)


Adhesive = 16m2 / 5 litres

Estimate Sheet Page 10 JN/CB.