Date :16-08-2018
Rev 00
METHOD STATEMENT
INSTALLATION OF TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02
QA/QC Engineer
Job Title
QGG.
Signature
Date
Page 1
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
CONTENTS
1. INTRODUCTION: ........................................................................................................................ 3
2. SCOPE OF WORK ........................................................................................................................ 3
2.1. GENERAL DESCRIPTION ................................................................................................... 3
2.2. MATERIAL, PLANT AND EQUIPMENT. ........................................................................... 3
2.2.1. MATERIALS ................................................................................................................. 3
2.2.2. PLANT AND EQUIPMENT. ......................................................................................... 4
2.3. RESPONSIBILITY: .............................................................................................................. 5
2.4. CONSTRUCTION SEQUENCE & METHODOLOGY:.......................................................... 5
2.5. PNEMATIC TESTING OF LPG PIPING AND TANK.......................................................... 9
3. EMERGENCY PROCEDURES .................................................................................................... 10
4. ENVIRONMENT......................................................................................................................... 10
5. COMMUNICATION AND TRAINING ....................................................................................... 10
6. HSE INDUCTION ....................................................................................................................... 10
7. HSE TOOLBOX TALKS ............................................................................................................. 11
8. METHOD STATEMENT BRIEFINGS ....................................................................................... 11
9. JOB WRAP-UP ........................................................................................................................... 11
10. ORGANIZATION, RESPONSIBILITY, SUPERVISION & WORKFORCE ........................... 12
11. APPENDIX’S .......................................................................................................................... 13
Appendix 1 - Risk Assessment. ..................................................................................................... 14
Appendix 2 – Workforce Organizational Chart ........................................................................... 20
Appendix 3 – Test Manifold. ......................................................................................................... 22
Appendix 4- WPS, Welder certificate. .......................................................................................... 24
Appendix 5- Checklist and Pressure Test Report. ...................................................................... 39
Appendix 6- Welding machine calibration certificate. ............................................................... 50
Appendix 7- Nitrogen Cylinder and regulator certificate........................................................... 52
Appendix 8- First Aider Certificate. ............................................................................................. 60
Page 2
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
1. INTRODUCTION:
The purpose of this Method Statement is to describe the methods and procedures for the
installation of TEMPORARY GAS SYSTEM AT FOX HILLS-RES-A02 in Lusail area.
2. SCOPE OF WORK
2.1. GENERAL DESCRIPTION
This method statement covers the procedure for Installation, Pneumatic Testing &
commissioning of LPG Temporary gas system
2.2. MATERIAL, PLANT AND EQUIPMENT.
2.2.1. MATERIALS
Page 3
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 4
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
2.3.4. Supervisor
2.3.4.1. Control the skilled / unskilled workforce on site to achieve the required progress.
2.3.4.2. Prepare the daily report & inform the site engineer.
2.3.4.3. Supervisor needs to conduct pre-start talk meeting.
2.4.1.1. Ensure that the all materials received are inspected; found acceptable as per material submittal and
are available to carry out the work.
2.4.1.2. Ensure that proper materials are selected and used in accordance with detailed drawings.
2.4.1.3. Materials enough for a day's work will only be stored at installation site. Rest of the materials will be
stored in lay down area or store.
2.4.1.4. Prior to Commencement of work, inspect areas and access to confirm that the site is ready to
commence the work.
Page 5
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
2.4.1.5. Ensure that only latest detailed drawing is available at site. Any revision which supersede shall be
properly endorsed by the Engineering Department to Construction Department and QA/QC
Department for proper execution of site work.
2.4.1.6. All relevant documentation (drawings) and materials applicable to particular section of works will
be checked by Site Engineer prior to commencement of work. Ensure welding related documents are
approved and available at site
2.4.1.7. The Site Engineer/ Site Supervisor will give necessary instructions to tradesmen and provide
necessary "Approved for Construction" detailed drawings of latest revision.
2.4.1.8. The Site Supervisor will also check that proper tools and equipment are available to carry out the
work and are in compliance with contract specification.
2.4.1.9. The Site Supervisor / Safety Officer will explain to the tradesmen regarding safety precautions to be
observed.
2.4.2.1. When received at site, all materials for LPG Temporary gas system shall be checked for data, Model
Nos., physical damages and accessories etc. as per materials submittal and notify supplier of any
discrepancies for suitable rectification or replacement.
2.4.2.2. All the LPG System components shall be checked to make sure that the items are as per manufacturer
country of origin and are from selected models etc.
2.4.2.3. Check that the material is delivered in standard packing for applicable material only.
2.4.2.4. Accessories will be segregated as per models and stored.
2.4.2.5. Any items found damaged or not found suitable as per the project requirements shall be remove from
site. Non-complaint material shall be removed from site.
2.4.2.6. After checking and confirming the materials as per the material submittals. Approved material submittals
2.4.2.7. Manufacturer’s instructions shall be strictly followed as applicable.
2.4.2.8. Storekeeper will be responsible for proper storage and maintenance of records, as required.
a. Pipe hanger and support shall be install which are pre-fabricated and galvanised by manufacturer.
b. Ensure area where supports are installed to be safely barricaded, proper signage to be display.
c. Mark the location of anchor bolt prior drill and make sure the location is correct and as per the drawings.
d. Install support at site based on detailed drawings. Make sure the distance between the supports is two
meters or less or as per the approved drawing.
e. Use proper tools for drilling, cutting of threaded rod and tighten the nut bolt of the supports.
a. Ensure that the pipes and fittings at joining area are free from water, oil, dirt and dust.
Page 6
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
b. Cut pipe ends and bevelled edge as per the detailed drawing.
c. Ream ends of pipes and remove all burrs from the inside and outside edges of the pipe with a deburring
tool. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before welding.
d. Centre both pipes together and ensures alignment of piping and gap of piping are within the WPS’s
tolerance. Secure both pipes with clamps once the alignment and gapping is within tolerance.
e. Start the Welding of seamless carbon steel pipe, Gas tungsten arc welding (GTAW), also known as
tungsten inert gas (TIG) welding process shall be used.
f. Remove scale, slag, and weld spatter after completion of welds.
g. All the completed joints shall be visually inspected by the site engineer.
Inspection with X-ray to be included. Only certified welder to perform welding works
2.4.3.4. INSTALLATION PROCEDURE OF ABOVEGROUND PIPE.
1. Support horizontal piping and fittings at required intervals to maintain alignment and prevent sagging
or grade reversal. The distance between the supports shall be reflected in approved drawings or
otherwise distance between supports should not more than 2 meters of interval.
2. Drill size and depth of hole on concrete ceiling / slab as recommended in the manufacturer
specification for specific drop-in anchors and the threaded rod.
3. Attach the prefabricated hanger support onto the anchor plugs and tightened the bolts on the anchor
plugs.
4. Install pipe shoe on the hanger support. Determine whether the shoe is sliding type or fixed type.
5. Provide large enough pipe sleeves through walls or floor slab to allow for anticipated differential
movement of pipes.
6. Vertical components shall be secured at each stack base and at sufficiently close interval to keep the
system in alignment and to adequately support the weight of the pipe and its contents.
7. Install pipe shoe and one section of the clamp onto the wall bracket.
8. Install piping on the clamp of the pipe shoe. Then use the other half on the clamp to secure the piping.
Bolt down the clamps with proper size and length of bolts and nuts.
1. As per the project requirement and approved drawing pipe are running underground at pavement
area.
2. Civil work like excavation sand bedding, backfilling etc shall be done by other. our scope of work
installation of pipe, sleeved, denso tape, warning tape as per the approved drawing.
3. Excavation, sand bedding shall be done as per the approved drawing by other.
4. Install the pipe with pipe sleeves, wrapping with anti-corrosion denso tape, warning tape as per the
approved drawing and section details for underground pipe.
5. Welding of carbon steel pipe shall be done specified in the above clause 2.4.33.
.Sealing of the sleeve ends shall be done to prevent sand and debris enter the sleeve
2.4.3.6. INSTALLATION OF LPG TANK, VALVE AND ACCESSORIES IN THE TANK AREA.
.Provide details of floor preparation prior to installation of concrete pad for LPG tank
1. At LPG Tank protection cage area mark the location of the LPG tank, piping, gas detectors as per the
approved drawings.
2. Make the tank area clean and level.
3. Fix the precast concrete pad/slab for the tank placement as per the approved drawing.
4. Put the LPG tank on the precast concrete pad/slab.
5. Drill size and depth of hole on concrete slab and fixed the LPG tank with concrete slab by using studs
and bolt.
Page 7
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
6. Install the ball valve, pressure regulator, pressure gauge, solenoid valve, inside LPG tank area as shown
in approved drawings.
7. Install the Protection Tank enclosure with lockable door as per the approved drawing.
8. Install the Safety Signage, steel step Ladder and Fire Extinguisher as per the approved drawing and
authority requirement.
9. Final connection to the PRMS (cylinder provision valve) shall be followed by completion of installation
and pneumatic test of piping works.
1. With reference to the detailed drawings, determine the location of explosion proof gas detector.
2. Check to verify the location of required conduits and fittings for the wiring of explosion proof
detection.
3. Install the conduits for wiring as per the detailed drawing.
4. Use junction box for easy wire pulling.
5. Size of cable will be indicated in the detailed drawings or use FP200 fire proof cable 2 core 1.5mm²
and 3 core1.5mm². for solenoid valve and emergency push button use 2 core 1.5mm² cable and 3 core
1.5mm² cable for gas detector connection
6. Interface the explosion proof gas detector with existing gas control panel as shown in approved
drawing.
Page 8
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
9. Check that coming power supply is same as the requirement. If the same switch on the control panel
successfully pass, proceed with simulation of detection system.
10. All electrical connection must be done by qualified electrician.
B. STORAGE
Pressure gauge and testing pipe spools shall be handled and stored in a proper manner that will prevent
damages of these pressure monitoring devices.
C. ROUGH-IN-WORKS
1. All joints including welds and threaded joint shall be expose for examination during test.
2. Test manifold preparation refers to the attachment No 2. For manifold diagram.
D. EXECUTION
1. Pneumatic testing involves additional hazard due to the possibility of release the stored energy from
compressed gas in the event of failure.
2. Vent/ purging system shall be installed at the test manifold
3. Confirm the pressure gauges are calibrated and in workable condition.
4. Confirm the integrity of the nitrogen cylinder including air hose accessories.
E. PROCEDURE
1. From a test manifold connect Nitrogen supply in the test plug at the point of connection (P.O.C) of testing
sources medium to be tested, so that Nitrogen supply maybe shut off, pressure observed on the pressure
gauge while Nitrogen filling and pressure release through the vent when necessary or after the duration
of test.
2. As per the woqod requirement pressure test shall be done at 6 bar for piping and tank pressure test shall
be 9 bar.
3. The test pressure of the pipes shall be 6 bar as per M/S Woqod requirements and the pressure
test of the tank and the pipes will be inspected by Woqod as well not witnessed by Marafeq
only.
4. After the test has been accepted the piping system shall be de-pressurized as soon as practical. Then
Nitrogen will be vented to atmosphere.
5. In the event of a leak during testing, the pipe shall be overhauled for subsequent repair until satisfactory
testing is obtained.
. Provide details if the tank and pipe work will be tested separately and the method of isolation between the tank and pipe work
.Test duration is not mentioned along with apparatus used for recording pressure readings
Page 9
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
F. COMPLETION OF TESTING
Pneumatic testing shall be considered completed when:
1. All defective weld, defective materials, valves, or other such defects have been corrected and accepted
by the operation manager.
2. All documentation and “test section” information is complete and accepted by operation manager.
3. EMERGENCY PROCEDURES
4. ENVIRONMENT
A. ENVIRONMENT REQUIREMENTS
1. Rubbish and waste materials must be collected and placed in specified area, bin or skip.
2. Fire hazards are to be eliminated by prompt removal of accumulated trade waste, rubbish, etc.
3. Lighting of fires at the workplace is prohibited
B. ENVIRONMENT PROCEDURES
1. All safety precautions are to be observed.
2. Before using or storing any hazardous substances, a copy of the respective MSDS is to be given to the site
supervisor
3. Electrical equipment including all power tools are to be inspected and tagged with colour codes at regular
intervals (monthly) and maintained in locations where they are not likely to be damaged.
4. Use the toilets and facilities provided, and keep them clean.
6. HSE INDUCTION
The HSE shall provide health and safety orientation for all its employees and
Subcontractors. This Induction is a prerequisite to entering the site to work, except to those persons entering
the site as a visitor (Visitors must be accompanied by a designated, orientation project person, and will abide
by the project safety regulation).
Workers who have attended the AHEW site safety Induction session shall be given a hard hat decal (or
identification card) which will be retained by the employee and shall be produced on demand while on the
work site. The safety Induction will include a review of the following:
1. Health and safety relationship of AHEW, Contractors and the Client. Site Access and Safe work procedure.
2. Proper use of personal protective clothing and other safety equipment.
Page 10
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
3. Emergency response plan, including evacuation points, location for emergency use.
4. General site lay out including location of sanitary facilities and first aid equipment. Vehicle / equipment
operation and safety.
5. All permit-required for the work.
6. Other site rules and regulations.
7. The safety Induction will be conducted in the morning, and the workers will be allowed to proceed to their
workplace afterwards. In no event shall any worker commence work prior to having undergone orientation.
All workers who attend the orientation session will be sign in the attendance sheet.
1. Mainly, the working plan and procedures for the day or the week shall be explained and confirmed, including
the following:
2. Detailed work procedures.
3. Potential hazards anticipated and involved.
4. Safety instructions for equipment and tools to be used.
5. Use of proper Personal Protective Equipment.
6. Other instructions by the safety department etc.
9. JOB WRAP-UP
1. Adjusting and Cleaning
a. Store all tools and equipment after use.
b. Collect and dispose of all scrap material and chemical according Material Safety Data Sheet (MSDS).
2. Documentation
As built drawings shall be updated as and where appropriate with the installed LPG piping, Gas tank and
all the equipment related to LPG temporary gas system location.
Page 11
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 12
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
11. APPENDIX’S
All equipment and instrument used shall be duly approved and claibrated and contractor
shall provide valid calibration certificates during its usage
Page 13
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 14
DATE:
DOC. NO: REV: 00
16 / 08 / 2018
Risk Assessment
RISK ASSESSMENT (S=Severity , L=Likelihood , R=Risk )
Activity Group affected Initial Risk Proposed Control Measures Resultant Risk
Hazard/Risk Rating Rating
S L R S L R
17 | P a g e
Page 14
15
DATE:
DOC. NO: REV: 00
16/ 08 / 2018
Page 16
15
DATE:
DOC. NO: REV: 00
16 / 08 / 2018
Page 17
16
DATE:
DOC. NO: REV: 00
16 / 08 / 2018
Use of Power Tools Using faulty / Workers Carry out inspection before use, label all
damaged equipment Others working in adjacent areas. damaged equipment Colour coding to be
Personal injury applied.
Electrocution Flying 4 3 12 Follow manufacturer’s instruction 3 2 6
objects Flying sparks before using the power tools Only
qualified electricians shall repair
defective power tools All power tools
must comply with the electrical
regulations applicable to the project
Tool has proper guarding.
Page 18
17
DATE:
DOC. NO: REV: 00
15/ 08 / 2018
Likelihood
Risk Rating Table
1 2 3 4 5
1 1 2 3 4 5
2 2 4 6 8 10
Severity of Hazard
3 3 6 9 12 15
4 4 8 12 16 20
5 5 10 15 20 25
1 -4 Low Attention
Page 18
19
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 20
WORK FORCE ORGANISATION
CHARTS-QATAR GAS GROUP
W.L.L
Page 20
21
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 22
TEST MANIFOLD ASSEMBLIES.
Page 23
22
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 24
Page 24
25
Page 25
26
Page 26
27
Page 27
28
Page 28
29
Welder certifications to be revalidated . Provide updated
certificates
Page 30
29
Page 30
31
Page 31
32
Page 32
33
Page 33
34
Page 34
35
Page 35
36
Page 36
37
Page 37
38
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Appendix 5- Bulk LPG Final Inspection Checklist and Pressure Test Report.
Page 39
Bulk LPG Final Inspection Checklist
Project Name
Tank Size
No. of Tanks
Site Location
Inspection I √ II III
Site Inspected By
Designation: Designation:
Page 40
A – Site Distance Requirements
Item
Description NA Yes No Comments
No.
Important building
Property line
2 Adjacent fuel storage tanks
Adjacent LPG tanks
Overhead electrical lines (over 600 volts)
Vaporizer
Pumps
Are clearance distances maintained from the following source of
ignition?
3 Air conditioner
Ventilator Fan
Flue
4 Are Fire Extinguishers well maintained and Hydro Static Test labeled?
Are adequate Hazard Warning Signs placed in prominent position
5
around the tank installation?
6 Is gas tank enclosure / fencing as per approved submittal plans?
7 Is gas tank enclosure / fencing in good condition?
8 Are storage tanks of correct capacity as per approved submittal plans?
Designation: Designation:
Page 41
B - Site Condition and Safety Precaution
Item
Description NA Yes No Comments
No.
Are the tanks secured at both ends against flotation and against
9
movement at the end to which the connection are made?
C - Tank Fittings
Item
Description NA Yes No Comments
No.
1 Is Gas Tank data plate available?
2 Is safety relief valve in good condition and have rain cap?
Are liquid level gauges approved for the services involved and in good
3
condition?
4 Are all tank fittings approved for the services involved and leak free?
Designation: Designation:
Page 42
C - Tank Fittings
Are all tanks openings equipped with proper fixed restriction back
5
check valve?
Are all tanks openings equipped with proper fixed restriction internal
6
valve and shutoff valve?
Are Emergency Shutoff Valve in good working condition and leak
7
free?
8 Is the pneumatic control system in good working condition?
D - Liquid Filling ( ACME Connection )
Item
Description NA Yes No Comments
No.
1 Is filling point is secured inside the ventilated locked box?
Is filling point is easily accessible and not visually obstructed by
2
landscaping or architectural elements?
Is pressure relief valve incorporated with Carbon Steel Seamless Pipe
3
(Sch. 80) in good working condition?
4 Is earthing in good condition?
Designation: Designation:
Page 43
F - Pump and Compressor
Item
Description NA Yes No Comments
No.
1 Are pumps and compressor in good working condition?
2 Is drive motor in good working condition?
3 Are pumps/compressor securely mounted on proper foundation?
Page 44
H - Pressure Reducing Station ( PRS )
Item
Description NA Yes No Comments
No.
1 Is PRS enclosure place and fitted as per approved submittal plan?
2 Is PRS enclosure fitted properly and in good condition?
Are solenoid valve, shut off valve, pressure gauges in good working
3
condition?
4 Are all test point openings plugged (capped)?
I – Piping
Item
Description NA Yes No Comments
No.
Are pipe works and pipe route installed in accordance with the
1
approved submittal plan?
Are pipe works passing through walls or floor slabs properly wrapped
2
and enclosed in metal sleeves and without joints?
Is a minimum clearance of 150mm maintained between LPG pipes and
3
electric conduits and cables?
Are all pipe works buried underground adequately treated and
4 protected against corrosion and mechanical damage, especially those
sections at road crossing?
5 Are piping supported and protected properly?
6 Are piping color coded properly?
7 Are piping free of exterior corrosion?
8 Are identification markings (liquid/vapor) available?
9 Are piping tested against leak free?
Are shut off valve provided at every required stage to ensure maximum
10
safety?
11 Are piping route fulfilled acceptable safety separation distance?
12 Are pipes epoxy / polyurethane coated?
Are underground pipes suitably protected against corrosion by suitable
13
external coating and wrapping?
Are underground piping laid under at minimum depth of 600mm
14
within private property?
Are minimum clearance (300mm) well maintained from other known
15
buried utilities (e.g. Electrical cables) to underground pipe?
Page 45
I – Piping
Item
Description NA Yes No Comments
No.
Are signs of ground settlement along the pipe and warning sign
16
provided?
Designation: Designation:
Page 46
L - Gas Meter
Item
Description NA Yes No Comments
No.
1 Is meter in good working condition?
2 Is gas meter seal in place?
Is meter properly calibrated at appropriate time
3
intervals?
Is meter located at visible location and
4
Accessible for maintenance?
5 Is gas meter protected from tampering?
Is meter flexible connection couplings secured and good working
6
condition?
M - Water Sprinkler System
Item
Description NA Yes No Comments
No.
1 Is pressure sufficient to cool gas tank?
2 Are all spray nozzles working properly?
3 Are deluge valve good working condition?
Are sprinkler system inter connected to firefighting system and gas
4
control panel?
N – Electrical ( General )
Item
Description NA Yes No Comments
No.
Are all electrical components and wiring in compliance with electrical
1
area classification?
Are electrical controls for equipment clearly marked or color coded to
2
indicate the on and off (stop) position?
Is electrical wiring, in Division 1 or Division 2 areas, installed in rigid
3
conduit? Class 1, Group D
For electric motors, are flexible connectors Class 1, Group D, Division
4
1 or 2 where applicable?
Page 47
Contractor
Logo
Project Name
Location
Work Permit Ref. No.
A: LPG TANK
- LPG tank(s) with associated fittings (Pneumatic test at 9 bars with Nitrogen / Air*):
Tank Capacity Tank Type
No. of Tank(s) 2
Tanks Serial No(s).
Test Duration hrs Test Pressure
Start Time End Time
Satisfactory Unsatisfactory
Pressure Drop (bars) in
Tanks Serial No(s).
* Note: If air is used as a testing medium, it shall be followed by Nitrogen for Purging purpose.
Air shall be used as a test medium for Tanks of sizes above 4,000 Liters.
Satisfactory Unsatisfactory
Pressure Drop bar
Satisfactory Unsatisfactory
Pressure Drop bar
Satisfactory Unsatisfactory
Submitted By
Name Date
Contractor Signature
WOQOD Remarks:
QA/QC
Office
Name Signature Signature
Date Date
Date :16-08-2018
Rev 00
Contractor to ensure that all equipment and instruments are duly calibrated and valid
certificates are available during the works
Page 50
Page 39
51
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 52
Page 41
53
MS Page.26
Page 42
54
MS Page.27
Page 43
55
MS Page.28
Page 44
56
Page 45
57
Page 46
58
Page 47
59
METHOD STATEMENT FOR INSTALLATION OF
TEMPORARY GAS SYSTEM (TGS) AT FOX HILLS-RES-A02 -
Date :16-08-2018
Rev 00
Page 60
Page 49
61
ffi##"#:#,F*t'"ru H
attiiio='3 (oiffir'*
PROVIDER COURSE
Fedinard Omonzejele
in recognition of their successful completion of the
BLS/AED & First Aid Course
according to standards set by Hamad International Training Center
and European Resuscitation Council guidelines.
= Page 50
62
Ms. Sonia Bunouh Dr. Khalid Abdulnoor
Course Director Director of HITC