Professional Documents
Culture Documents
QAQC Monthly Maintenance Report (Form)
QAQC Monthly Maintenance Report (Form)
Machine
Sr. Machine Name No. Problem Action Taken Action By Action Date Confirmation
1 A-Air Conditioning System 1 -
13 SANDING MACHINE 6
15 BORING MACHINE 10
Machine
Sr. Machine Name No. Problem Action Taken Action By Action Date Confirmation
21 BAND SAW MACHINE 29
31 CNC ROUTER 18
35 AIR COMPRESSOR 5 2
37 PAINTING BOOTH 1 1
38 PAINTING BOOTH 2 2
39 PAINTING BOOTH 3 3
40 PAINTING BOOTH 4 4
QA/QC Monthly Maintenance Report
Machine
Sr. Machine Name No. Problem Action Taken Action By Action Date Confirmation
41 PAINTING BOOTH 5 5
44 Dust Collector 1 1
45 Dust Collector 2 2
46 Dust Collector 3 3
47 Electrical System -
48 Camera (CCTV) -
49 Elevator 1 -
50 Cargo Lift -
51 Skylight -
52 Roof -
53 Water Tank -
54 Drainage -
55 Wash Room -
56 Septic Tank -