ID Task Name Duration Start Finish July August September

Sun 27 Sun 4 Sun 11 Sun 18 Sun 25 Sun 1 Sun 8 Sun 15 Sun 22 Sun 29 Sun 5
1 Precomm Pipa Segmen 10A & 12A 68 days 7/2/21 9/7/21
2 Milestones 9 days 7/2/21 7/11/21
3 start 0 days 7/2/21 7/2/21 7/2
4 hot bend 24" onsite 0 days 7/5/21 7/5/21 7/5
5 desain civil sbv-1 afc 0 days 7/8/21 7/8/21 7/8
6 desain civil sbv-2 afc 0 days 7/11/21 7/11/21 7/11
7 desain civil loop afc 0 days 7/11/21 7/11/21 7/11
8 cleaning & gauging (downstream 7 days 7/2/21 7/8/21
loop - upstream sbv -1)
13 site preparation civil work 22 days 7/9/21 7/30/21
21 pekerjaan remaining pipeline 11 days 7/25/21 8/4/21
27 Precomm KP-0 +260 - exit HDD kp 39 days 7/31/21 9/7/21
19+500
28 Preparation (install Test Header, 4 days 7/31/21 8/3/21
set up equipment)
29 20" 16 days 8/5/21 8/20/21
30 Waterfilling (bidi pig c/w 8 days 8/5/21 8/12/21
gauging plate)
31 hydrostatic test 2 days 8/13/21 8/14/21
32 dewatering 2 days 8/15/21 8/16/21
33 swabbing 4 days 8/17/21 8/20/21
34 24" 17 days 8/15/21 8/31/21
35 Waterfilling (bidi pig c/w 8 days 8/15/21 8/22/21
gauging plate)
36 hydrostatic test 2 days 8/23/21 8/24/21
37 dewatering 3 days 8/25/21 8/27/21
38 swabbing 4 days 8/28/21 8/31/21
39 Precomm launcher KP-0 +000 - 7 days 9/1/21 9/7/21
0+260 (Expansion Loop)
40 Preparation (install Test Header,1set
dayup equipment)
9/1/21 9/1/21
41 20" 3 days 9/1/21 9/3/21
42 Waterfilling (bidi pig c/w gauging
1 dayplate)9/1/21 9/1/21
43 hydrostatic test 1 day 9/2/21 9/2/21
44 dewatering 1 day 9/2/21 9/2/21
45 swabbing 1 day 9/3/21 9/3/21
46 24" 3 days 9/3/21 9/5/21
47 Waterfilling (bidi pig c/w gauging
1 dayplate)9/3/21 9/3/21
48 hydrostatic test 1 day 9/4/21 9/4/21
49 dewatering 1 day 9/4/21 9/4/21
50 swabbing 1 day 9/5/21 9/5/21
51 Golden joint expansion loop 2 days 9/6/21 9/7/21
52 20" 1 day 9/6/21 9/6/21
53 24" 1 day 9/7/21 9/7/21