WORK BREAKDOWN STRUCTURE

RE-PWHT ETHANOL PIPING PROJECT

No Description Duration Percentage Day(s) Remarks


(days) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Documenting 4 20% 1 1 1 1
1.1 Procedure 3 15% 1 1 1

1.1.1 PWHT 3 3.8% 1 1 1


1.1.2 NDE 3 3.8% 1 1 1
1.1.3 Hydrotstatic Test 3 3.8% 1 1 1
1.1.4 Painting 3 3.8% 1 1 1

1.2 Project ITP 3 2.5% 1 1 1


1.3 Submit Document to Shell Malaysia 2 2.5% 1 1

2 Process 11 55% 1 1 1 1 1 1 1 1 1 1 1
2.1 Demobilization 2 10% 1 1
2.2 Re-PWHT Process 6 30% 1 1 1 1 1 1
2.3 NDE 1 5% 1

2.3.1 RT (10%) 1 2.5% 1


2.3.2 PT (100%) 1 2.5% 1

2.4 Hydrostatic Test 2 3.3% 1 1


2.5 Re-Painting 2 3.3% 1 1
2.6 Mobilization to Site 2 3.3% 1 1

3 Installation 5 25% 1 1 1 1 1
3.1 Installation to existing facility 5 25% 1 1 1 1 1
TOTAL 20 100%