Professional Documents
Culture Documents
7.2 Benefit Cost of A Single Project
7.2 Benefit Cost of A Single Project
2 BENEFIT/COST ANALYSIS OF A
SINGLE PROJECT
The benefit/cost ratio, a basic analysis tool for public-sector
initiatives, was created to provide objectivity to the field of public-
sector economics. It was created in response to the United States. The
1936 Flood Control Act was enacted. The B/C ratio comes in a variety of
forms, but the essential concept remains the same. At the discount
rate, all cost and benefit estimations must be converted to a common
equivalent monetary unit (PW, AW, or FW) (interest rate). The B/C ratio
is then calculated using one of these relations:
PW = PRESENT WORK
AW = ANNUAL WORK
FW = FUTURE WORK
The B/C value would change considerably were disbenefits
added to costs. For example, if the numbers 10, 8, and 5 are used to
represent the PW of benefits, dis- benefits, and costs, respectively,
Equation [7.2] results in B/C (10 - 8)/5 = 0.40. The incorrect placement
of disbenefits in the denominator results in B/C 10/ (8 + 5) = 0.77,
which is approximately twice the correct B/C value.
CORRECT INCORRECT
B 10−8 B 10
= =0.40 = =0.77
C 5 C (8+5)
SOLUTION
Benefit = $1,500,000 per year
Disbenefit = $200,000 per year
Cost = $15,000,000 (A/P,6%,10) = $2,038,019 per year
M and Q cost = $500,000 per year
B 1,500,000−200,000 1,300,000
= = =0.51
C 2,038,019+500,000 2,538,019
B 1,500,000−200,000−500,000
= =0.39
C 2,038,01 9
EXAMPLE 2
SOLUTION:
BENEFIT = $175,000
DISBENEFIT = $25,000
COST = $1,400,000 (A/P,6%,10) = $190,215
M and Q cost = $40,000
B 175,000−25,000 150,000
= = =0.65
C 190,215+ 40,000 230,215