Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Int J Adv Manuf Technol (2016) 85:547–555

DOI 10.1007/s00170-015-7972-7

ORIGINAL ARTICLE

Value stream mapping and lean simulation: a case study


in automotive company
P. F. Andrade 1 & V. G. Pereira 1 & E. G. Del Conte 1

Received: 11 July 2015 / Accepted: 12 October 2015 / Published online: 19 October 2015
# Springer-Verlag London 2015

Abstract This work aims at applying the concepts of value time. To this end, managers’ concerns in reducing waste are
stream mapping (VSM) in an auto-parts company in the ABC growing.
region of Sao Paulo. By mapping the current state of art, it was One way to achieve reduction of waste is by using the value
possible to identify the waste present in an assembly line of stream mapping (VSM) tool, which is defined by Liker [1] as
clutch discs. The future state was suggested with improve- a map that captures the material and information flow, which
ments for elimination of waste and reduction of lead time, helps identify losses in the system.
which went from 60.5 to 4.14 days. Simulations were made As per Rother and Shook [2], VSM is an easy understand-
using current and future states to support the suggested im- ing tool which allows simultaneous representation of the in-
provements, and reduction of 7 % in total production time was formation and material flow. VSM seeks to identify and elim-
verified, as well as 10 % increase in the use of work positions. inate waste in a factory or production line in order to serve
The results showed that VSM combined with simulation is a customers with higher quality and promptness.
good alternative in the decision-making for change in produc- So, the main purpose of this tool is to reduce time between
tion process. placement of order by customer and the time of delivery of the
product [3].
To achieve this goal, VSM analyzes factors such as infor-
Keywords Value stream mapping . Lean production . Waste . mation flow, delivery time, personnel, inventory, and material
Simulation flow, as these impact each other during the production pro-
cess. The impact that these factors generate is difficult to de-
fine without analysis throughout the value stream.
The construction of VSM consists of drawing the current
1 Introduction
state value stream mapping (VSM). This is the state that re-
flects the reality of the process under review. Based on the
Due to economic, political, and social changes over the years
current state VSM, the future VSM is designed, which intro-
in the global economic market, organizations are forced to
duces the new production flow reducing waste through the
become more competitive due to the increased level of cus-
application of lean tools [4].
tomers’ demand. Within such scenario, companies experience
For the analysis of a VSM, it is necessary to think statically
the need for improvement in its production processes, in order
in terms of time, which is a limitation of the VSM since it is a
to provide high-quality products at affordable prices and on
static image of value stream, and just the most obvious chang-
es are suggested. An alternative that may assist in the analysis
of a VSM is the simulation of the resources actually used in
* E. G. Del Conte the process [5].
erik.conte@ufabc.edu.br For Anand and Kodali [6], simulate is to perform experi-
ments with models of a real system. Simulation is performed
1
Centro de Engenharia, Modelagem e Ciências Sociais Aplicadas by entering the information obtained in VSM in simulation
(CECS), Universidade Federal do ABC, Santo André, Brazil software. The integration of VSM with the simulation is
548 Int J Adv Manuf Technol (2016) 85:547–555

advantageous because it adds time dynamics to VSM and 1. Many steps certainly add value.
assists in making decisions regarding changes in a production 2. Many other steps do not add value but are inevitable.
process. 3. Many additional steps do not create value and should be
The objectives of this paper are to apply concepts of VSM promptly avoided.
to an auto-parts company and simulate the current and future
state of a clutch disc assembly cell. Figure 1 illustrates these activities, proportionately show-
For this, there was an initial review of literature regarding ing where each activity fits in. For example, unnecessary ac-
lean manufacturing and waste concepts, in addition to the tivities represent approximately one fourth of the activities
types of losses that occur in a production process. Concepts involved in the production process and are seen as a loss,
about the value chain and steps for conducting a VSM were while works that really add value represent a small portion
also raised. of the whole. Some of these activities cannot be completely
Later, a case study was performed in an assembly line of a eliminated but can be improved, thus lowering the percentage
multinational company in the auto-parts sector. That case loss.
study sought to identify and examine production flows Such addition of value or not is defined by means of activ-
existing in the assembly line and apply tools and techniques ities that effectively transform or not the product in a way that
of lean production in order to reduce waste. the customer is willing to pay. VSM, by encompassing the
To identify sources of waste, the current state of the assem- entire value chain, helps identify and understand the flow of
bly line value stream was mapped and analyzed. From such material and information to the extent that the product follows
analysis, improvements using lean manufacturing tools have its flow [2].
been suggested and used for mapping the future value stream
state.
2.2 Value stream mapping
Seeking to prove and quantify the benefits gained from
such improvements, a simulation model for each VSM state
For Belokar et al. [9], VSM is used for analyzing and mapping
was suggested and their results were compared.
processes to reduce waste, allowing better flow of production.
The next section comprises a literature review, which de-
The purposes of VSM are to highlight the sources of waste
fines concepts and tools used. The development and presen-
and eliminate them through the implementation of future state
tation of the case study are described in the third section,
mapping. The goal is building a production chain in which
followed by the analysis of results. Finally, the last section
individual processes are connected to their customers, by ei-
provides conclusions regarding this work.
ther continuous or pulled streaming, and each process pro-
duces only what customers need and when they need.
To determine the percentage of added value, it is necessary
2 Literature review to calculate the processing time, which is the sum of the cycle
times of all operations in a production process, and these are
According to Womack and Jones [7], waste is any human the operations that really add value to the product. After de-
activity which absorbs resources without creating value. For termining it, just divide it by the lead time to find the percent-
organizations to aim at preventing and eliminating waste in age of added value.
the production process, it is necessary for them to identify the Lead time, according to the VSM theory, is determined by
value chain of their products. the sum of processing time with the sum of the times that
intermediate stocks are standing still in the production line.
These times are calculated by multiplying the takt time of
2.1 Value chain
process by the number of items in the intermediate stock [4].
Figure 2 shows an example for calculating the percentage
The definition of Shank and Govindarajan [8] says that
considering a takt time of 50 s per piece.
the value chain for any company, in any business, is the
By applying lean tools, it is possible to eliminate waste of
interconnected set of all activities that create value,
the current state and draw a future state with lean processes.
from a basic source of raw materials, through compo-
Percentage of added value is the indicator used to compare the
nent suppliers, until handing over the final product to
current and future states.
consumers.
The identification of this chain for each family of products
is one of the main steps of lean production as it greatly con- 2.3 Simulation
tributes to expose large and amazing amounts of waste. The
analysis of the value chain often shows that there are three Simulation is a resource that is widely used in various seg-
types of action along its length [7]: ments, and particularly engineering, the application of this
Int J Adv Manuf Technol (2016) 85:547–555 549

Fig. 1 Understanding the Completely unnecessary for


manufacturing function [18] accomplishment of works
Net Examples:
work - Handling time
Loss - Unnecessary transport
- Storage of in-process materials
- Change of material or tools from one
hand to the other
- Transportation of materials to places
No added value, but it other than final destination
must be done because
Work with no Movement of workers
of the current work
added value Works with added value
conditions.

Examples:
- Walk from one place to another in order to get material
- Removal of purchased parts from packages
- Removal of a small amount of parts from a large box
- Equipment activation

resource has been growing in recent years. Generically, this inventory levels through the production process, which is not
can be defined as a model that mimics real activity [10, 11]. possible with just a map of the future state, because a static
In the opinion of Freitas Filho [12], simulation helps test model does not allow assessing how stock levels will be af-
hypotheses by evaluating the various possible scenarios with- fected to various production scenarios with different parame-
out modifications in the real system. This becomes advanta- ters [11, 14].
geous since changes may involve costs and time. By using simulation, it is possible to measure improve-
Decision to use the simulation on certain projects is justi- ments in performance, which may be anticipated from the
fied based on the following factors [12]: application of principles of streaming lean manufacturing, set-
up reduction, total preventive maintenance, just-in-time in-
& Gains in productivity from development of projects by ventory, and leveled production scheduling [15].
means of simulation. Some authors like Rajentirakumar et al. [16] and
& Amount of information enough to make it possible to per- Donatelli and Harris [13] use VSM and simulation as
form a simulation analysis of various scenarios. mutual complement. Lian and Landeghem [17] suggest a
& Possibility of using animations during the simulation pro- method for deploying extended VSM by means of simu-
cess, in order to facilitate visualization of what is being lation, where the simulated model is fed with information
modeled. on the current and future states of VSM, initially to val-
& Simulated model behaves similarly to the real system. idate modeling in relation to the current state and then to
analyze the impact of improvements suggested before the
Thus, simulation can help an organization to consider tech- implementation of future state.
niques of lean production, acting as a complementary tool for
VSM and thus being able to quantify gains during the initial
planning and evaluation stages, also being able to identify 3 VSM development
needs for resources and generate performance statistics, while
remaining flexible to the organization’s details [13]. The case study was conducted in a branch of a multinational in
In some cases, the future state map can be assessed in a the auto-parts industry located in the ABC region of Sao Paulo
relative ease way, but in others, there may be some difficulty. and aimed at applying VSM to review its mounting process of
In such cases, you can use simulation to further analyze data. clutch discs, so as to identify waste and have a better control of
An example where this may be observed is the prediction of productivity.
In the assembly line of clutch discs, about 20,000 discs are
Process 1 Process 2
assembled, on a monthly basis. It counts on approximately
8640 Items x 50 864 Items x 50 3456 Items x 50 150 products, and such products bear from 30 to 40 compo-
5 days 2 days
Standstill time: 7.5 days
No value added 12 h

Value added 20 s 20 s Processing time: 65 s


nents each in its assembly. This shows that the line used in the
case study requires high flexibility and minimum waste to
Percentage of added value
Processing time 65 s
0.0001%
meet demand, which justifies the application of VSM.
Lead-time 7.5 days + 65 s The family of products used in the study was family 13
Fig. 2 Example for calculating the percentage of added value that, despite showing only 3.8 % of the monthly demand,
550 Int J Adv Manuf Technol (2016) 85:547–555

was chosen because it has a complex flow of production, with Spring Washer, with 5313 items of that component in the line
a lot of processes accomplished and a large number of com- and only 427 being necessary to carry out the production. This
ponents used for assembly. scenario shows that there is no effective control on the supply
Within family 13, clutch disc alfa was the model cho- of components and that demand would not be met since it was
sen for data collection on the shop floor. This choice is not possible to produce a single disc alfa.
due to the fact that this model is one of the major de- In the current state information flow, multiplier is the one
mands of remanufactured discs. which informs what will be produced to employees after re-
The production flow for manufacturing disc alfa was col- ceiving the daily production control and planning (PCP); i.e.,
lected, as well as cycle times of each operation, the number of it says what will be produced and the amounts to be produced.
employees in each position, and inventories of components From data collected, takt time and takt time of process were
required to assemble the model. Thus, generating the VSM calculated, resulting in 61 and 44 s per piece, respectively. The
of current state is shown in Fig. 3. cycle time of each operation is shown in Table 2, with takt
The first point of improvement observed was the num- time and takt time of process. From this table, it was possible
ber of components required for mounting disc alfa. To to draw the chart in Fig. 4, in which we are able to observe that
assemble 427 discs of the monthly demand for model alfa, operations regarding manual positioning of rivets (operation
components presented in Table 1 are required. It shows A) and final assembly and pressing (operation E) are above
the amount of each component to mount a single disc the takt time of process and may be considered as processes to
and to meet demand, in addition to quantities available be improved in the line.
in stock for each component. In operation trim + reinforcement disc, a manual riveter is
It was observed that there were no amounts enough of used. Below the current state mapping is the time line, which
components such as the Trim Spring, Tubular Rivet, Torsion bears the processing time of each operation and the number of
Disc, Solid Rivet, Hub Flange, Friction Ring, and Hub to meet days for each intermediate stock. Total processing time is
the demand of 427 discs model alfa. Other components were 308 s, and lead time of 60.5 days, so the percentage of added
in amounts much higher than those required, for example, value of the assembly line in current state is 0.006 %.

Current State of Stream 13

External Supplier Sales – Monthly


(Buy) Auto-parts and
Planning
Automobile Manufacturer
Markets
Internal Supplier
(Do) PCP
Daily Planning

Multiplier

Stock
Shipment

pieces
Manual positioning Trim + Trim Join 2 parts and Final Assembly Riveting Buckling and
Packing
of Rivets spring clinch and Pressing Axial Runout
457 pieces
pieces pieces pieces pieces pieces pieces

F 7514 pieces

G 332 pieces

B 79920 pieces
pieces pieces
pieces pieces
pieces

Trim + pieces
Reinforcement pieces
pieces disc
pieces
pieces
pieces

D 1473 pieces

pieces
pieces

Production Lead
days days day days days days days days Time = 60.5 days

seconds seconds seconds seconds seconds seconds seconds

Fig. 3 Current status of stream 13


Int J Adv Manuf Technol (2016) 85:547–555 551

Table 1 List of components


required Component Amount per unit Amount for demand Available

A Trim 2 854 914


B Trim rivet 72 30,744 79,920
C Trim spring 9 3843 999
D Reinforcement disc 1 427 1473
E Tubular rivet 18 7686 1998
F Torsion spring 8 3415 7514
G Torsion disc 2 854 332
H Solid rivet 8 3416 888
I Locking ring 2 854 4125
J Hub flange 1 427 0
K Spring washer 1 427 5313
L Snap ring 1 427 3396
M Friction collar 2 854 147
N Hub 1 427 0
O Spacer 4 1708 4379
P Washer 1 427 845
Q Smaller spring washer 1 427 5509

To improve percentage of added value in production line, a In the future state (see Fig. 5), it is also possible to observe
future state has been suggested (see Fig. 5), where we may that information flow has also changed because there is the
find some improvements made to the assembly line. availability of Heijunka board in the line, so as to take the
To remove the manual riveter from assembly line, it has multiplier responsibility to inform which item and which
been suggested that the press used for trim + trim spring op- amounts must be produced. So, operators are independent to
eration must also perform the trim + reinforcement disc oper- begin production of the planned item.
ation in future state. As both operations supply the operation Supermarkets are also present in future state, one for inter-
for joining two parts and clinching, it is necessary to create nal and external suppliers of the line and another at the end of
two buffers, one for each operation, in order to provide enough the line, so that shipment pulls the discs being required. With
pieces to the joining operation. By means of testing performed kanbans, it is possible to inform the previous process that the
in line, it is possible to define that buffers would have a max- customer has pulled an item.
imum of six components and a minimum of three, in addition With the supermarket in suppliers, it is ensured that
to compliance with first-in, first-out (FIFO). the line will only have the necessary components and
As per Fig. 4, the cycle times of operations A and E are quantities required for production, as can be seen in fu-
above the takt time of process. Operation E has two operators ture state.
to offset its high cycle time. Thus, to reduce operation A cycle To work with supermarket at the end of the line, the pro-
time, it has been suggested that, in future state, the operator duction lot for disc alfa has been set at 60 parts. With this
that used manual riveter in the trim + reinforcement disc op- amount, the line is going to carry out seven times the produc-
eration would also carry out operation A, which would also tion of that batch during the month. In the supermarket, two
count with two operators. batches of 60 pieces will be available to be used for shipment.

Table 2 Cycle times of stream 13 in seconds (s)

Manual positioning Trim + trim Trim + reinforcement Join two Final assembly Riveting Buckling and Packing
of rivets spring disc parts and clinch and pressing axial runout

Stream 13 A B C D E F G H
Total cycle 45.00 42.00 44.00 38.00 57.00 37.00 25.00 20.00
Takt time 61 61 61 61 61 61 61 61
Takt time of 44 44 44 44 44 44 44 44
process
552 Int J Adv Manuf Technol (2016) 85:547–555

Fig. 4 Chart of stream 13 cycle


times

Time (s)
Cycle

Takt Time of Process

Operations

When a batch is removed from the line, the production of a For better analysis of data, only the amounts of raw mate-
new batch may be used for replenishment. rials required for the production of 427 clutch discs were used.
With all the improvements made in future state, the assem- According to the company, the production of 427
bly line of discs will have a processing time of 264 s and lead clutch discs was made in about 5 h and 40 min. And,
time of 4.14 days. Thus, the percentage of added value will according to the obtained data, calculations were made
increase to 0.074 %. using processing times of each position. The bottleneck
Simulation was done in a simplified manner, because of the process, as previously mentioned, is the operations
of the complexity of the production line under study, for manual positioning of rivets (operation A) and final
especially considering processing times at each position. assembly and pressing (operation E), which are above
Thus, the study focused on the decreased time of pro- the takt time of process, but operation E has two perma-
duction, in order to use the available manpower in the nent workers in place, which reduces by half the process-
best possible way. ing time of this position. So, the bottleneck is only in the

Future State of Stream 13


Sales – Monthly
Planning Auto-parts and
Automobile Manufacturer
Markets

External Supplier
(Buy)
PCP
Daily Planning

Shipment

Trim + Trim spring


Internal Supplier Manual positioning Max. Amount Join 2 parts and Final Assembly Buckling and Axial
+ Reinforcement Riveting Packing
(Do) of Rivets clinch (press) and Pressing Runout
disc
A 120 pieces
Min. Amount
Max. Amount

Min. Amount
B 4320pieces pieces pieces
pieces pieces
pieces
pieces
pieces pieces
pieces pieces

42s for trim + trim spring


30s for trim + Reinforcement disc pieces
pieces

pieces
pieces

Production Lead
day day day day days Time = 4.14 days
days
Processing Time =
seconds seconds seconds seconds seconds seconds seconds 264 seconds

Fig. 5 Future state of stream 13


Int J Adv Manuf Technol (2016) 85:547–555 553

Fig. 6 Simulation of current state

first position, with 45 s. From this number, it is possible 4 Results and discussion
to calculate the total production time, as shown in Eq. 1.
Since operation C, junction of trim and reinforcement disc According to statistics generated by the simulation program, it
is independent from operation B, they can be made at the was possible to draw charts for visualization of results about
same time, and only the longest processing time between the current VSM. Figure 7 shows the percentage of use of
two operations should be counted. Thus, calculation is work positions, where one can see that stations A, C, and H
made considering the time of operation A—positioning are never filled, because such stations have infinite capacity,
rivets—to 427 pieces and then adding the processing time being able to store both endless raw materials and products
for the last piece to reach to operation H—packaging: already processed, stations A and C, as they are places where
raw materials come in and station H where products come out.
ð427pieces  45sÞ þ 44s þ 38s þ 57s=2þ The most used position is the final assembly and pressing
ð1Þ
25s þ 20s ¼ 19:370; 5s ¼ 5h and 23min station, with 96.16 % of use because of the largest processing
time among stations.
Figure 8 shows the use of available resources, the eight
Simulation showed production time much closer to workers who work in the line. In the current state, the most
that calculated—5 h and 21 min—and only 5 % lower used worker is worker 1, responsible for manual positioning
than the time communicated by the company for the of rivets, current bottleneck of production, with 9.07 % utili-
production under study, validating the simulation model. zation. Worker 7 responsible for trim and reinforcement disc is
Figure 6 illustrates the simulation environment of cur- the one with the lowest percentage of use.
rent state.

% Utilization in the Current State


% Utilization in the Current State

A - Manual positioning of Rivets

B - Trim and Trim spring


D - Join 2 parts and clinch

C - Trim and Reinforcement Disc


E - Final Assembly and Pressing
F - Riveting
Operator 1

Operator 2

Operator 3

Operator 4

Operator 5

Operator 6

Operator 7

Operator 8

G - Buckling and Axial Runout

H - Packing

Fig. 7 Chart depicting utilization of positions in the current state Fig. 8 Chart depicting utilization of resources in the current state
554 Int J Adv Manuf Technol (2016) 85:547–555

Fig. 9 Simulation of future state

With the simulation results, the suggested future state now position—operation B—with 42 s. By calculating just as
has arguments to be applied. The way found to reduce pro- the current state, we have Eq. 2:
duction time would be decreasing processing time of some
45s=2 þ ð427 pieces  42 sÞ þ 38s þ 57s=2 þ 25s þ 20s ¼
operations, using the available resources. Due to the similarity
18:068s ¼ 5h and 2min
of operation B, junction of trim and trim spring with operation
C, and junction of trim with reinforcement disc, the connec- ð2Þ
tion of both operations has been suggested, due to the high
The screen capture of future state is shown in Fig. 9, with
percentage of time with the C position only partially occupied,
its simulated processing time. As in the current VSM, the time
as observed in the simulation. With only one position respon-
given by the software is close to the calculated value, with 4 h
sible for these two operations, the production of these two
and 59 min of production, thereby decreasing the total pro-
products would be switched, and the available capacity of
duction time by approximately 7 %.
such position would be used in a better way.
From the charts generated with the new outputs of
Operator 7, responsible for the extinguished position,
ProModel®, it is possible to see an improvement in the per-
would work to reinforce position A, where there was the big-
centage of utilization of positions. Figure 10 shows the best
gest bottleneck of the process, thus, reducing the processing
use of position B. The new work position now uses approxi-
time of that position and, consequently, reducing the produc-
mately 99 % of its capacity, reducing loss by idleness.
tion time of 427 clutch discs.
In addition, as in current state, a chart to analyze the use of
With the changes, it is possible to estimate the new
resources has been generated (see Fig. 11). As mentioned
production time, which considers half of the operation A
above, operator 7 started working in the first position, now
processing time due to the extra operator in the new sce-
being called operator 1.2, sharing the work with operator 1.1,
nario. Thus, the bottleneck time turns to the second

% Utilization of Resources in the Future State


% Utilization in the Future State

Manual positioning of Rivets

Trim and Trim spring

Join 2 parts and clinch

Final Assembly and Pressing

Riveting

Buckling and Axial Runout


Operator 1

Operator 2

Operator 3

Operator 4

Operator 5

Operator 6

Operator 7

Operator 8

Packing

Fig. 10 Chart depicting utilization of work positions in the future state Fig. 11 Chart depicting utilization of resources in the future state
Int J Adv Manuf Technol (2016) 85:547–555 555

and reducing the use of operator 1.1, but decreasing the pro- We suggested the use of pull production with strict control
cessing time of that position. Operator 2 now works harder, over the raw material inventory with kanban; the production
alternating between two operations that are now made at po- would be made in batches of 60 pieces, reducing the inventory
sition B. cost of the final product.
With the suggested changes, there was a 10 % increase in
the use of work positions and reduction of 7 % in total pro-
duction time of 427 clutch discs—from 5 h and 21 min to 4 h Acknowledgments Special thanks are due to Dr. Guilherme Canuto da
and 59 min. Silva and Dr. Leonardo Ribeiro Rodrigues.
For purposes of comparison, we used the same amount of
pieces for production; however, the proposal is to use the pull
demand and produce clutch discs in batches of 60 pieces, in References
order to avoid costs of inventory and costs of idle parts,
waiting for use. 1. Liker JK (2005) O Modelo Toyota: 14 principios de gestão do
maior fabricante do mundo. Bookman, Porto Alegre
2. Rother M, Shook J (2003) Aprendendo a Enxergar: mapeando o
fluxo de valor para agregar valor e eliminar o desperdício. Lean
5 Conclusions Institute Brasil, São Paulo
3. Lustosa L, Mesquita MA, Quelhas O, Oliveira R (2008)
The present study showed the use of VSM in applying con- Planejamento e controle da Produção. Elsevier, Rio de Janeiro
cepts of lean production, combined with simulation as a com- 4. Nash MA, Poling SR (2008) Mapping the total value stream. CRC
plementary tool. Press, New York
Using the simulation, it was possible to predict the produc- 5. Abdulmalek FA, Rajgopal J (2007) Analyzing the benefits of lean
manufacturing and value stream mapping via simulation: a process
tion line under study according to the VSM. From the data sector case study. Int J Prod Econ 107:223–236
generated by the software, the current state of production line 6. Anand G, Kodali R (2009) Simulation model for the design of lean
was analyzed and weaknesses in the production process were manufacturing systems—a case study. Int J Product and Qual
identified. According to that, a plan of action was suggested. Manag 4(5–6):691–714
7. Womack Jp, Jones DT (2003) A Mentalidade Enxuta nas empresas:
The main problems in the production line were exaggerated
elimine o desperdício e crie riqueza 9th ed. Campus, Rio de Janeiro
stocks and the bottleneck in a production process. The com- 8. Shank JK, Govindarajan V (1993) Strategic cost management: the
pany has no effective control over raw materials necessary for new tool for competitive advantage. The Free Press, New York
production, thus maintaining surpluses of some parts and no 9. Belokar Rm, Kumar V; Kharb SS (2012) An application of value
inventory for others, which increases the cost of production, stream mapping in automotive industry: a case study. International
Journal of Innovative Technology and Exploring Engineering
whether due to increased production time or cost of unneces-
(IJITEE) Vol 1 No 2.
sary stocks. 10. Rajakumar S, Arunachalan VP, Selladurai V (2005) Simulation of
As a solution, we suggest joining two work positions workflow balancing in assembly shopfloor operations. J Manuf
that had similar operations, applying the concept of FIFO Technol Manag 16(3):265–281
and a single operator alternating operations, due to the 11. Mönch L (2007) Simulation-based benchmarking of production
control schemes for complex manufacturing systems. Control Eng
maximum production quantities of each intermediate Pract 15(11):1381–1393
product. The operator of the extinguished station turns 12. Freitas Filho PJ (2008) Introdução à modelagem e simulação de
into a reinforcement in the workplace, responsible for sistemas com aplicações em arena 2. Visual Books, Florianópolis
the bottleneck of production, therefore reducing the total 13. Donatelli A, Harris G (2004) Combining value stream mapping and
time of line processing. discrete event simulation, in Proceedings of the Huntsville
Simulation Conference. Society for Modeling and Simulation
Simulation allowed changing the virtual production line in International, San Diego, CA
a simple way, thus making it possible to analyze the impact of 14. McDonald T, VAN Aken EM, Rentes AF (2002) Utilizing simula-
changes before actually implementing them, avoiding unnec- tion to enhance value stream mapping: a manufacturing case appli-
essary costs, and saving time. Thus, the improvements sug- cation. Int J Logist: Res and Appl 5(2):213–232
gested have been simulated, in order to check for feasibility of 15. Mohamed AS, Khaled SE, Aziz EE (2011) Value stream map sim-
ulator using ExtendSim. Proceedings of the World Congress on
such changes. Engineering, London
The future state suggested decreased by 7 % of the 16. Rajenthirakumar D et al. (2012) Lean manufacturing: a study of
total production time of 427 pieces in the simulation, application in a customary atmosphere. International Journal of
only with the relocation of an operator and joint of two Lean Thinking. pp. 20–35.
work positions. 17. Lian YH, Landeghem HV (2002) An application of simulation and
value stream mapping in lean manufacturing. In: Proceedings 14th
The action plan suggested is advantageous according to the European Simulation Symposium, pp 1–8.
application of lean tools, kanban, supermarket and especially 18. Ohno T (1988) Just-in-time for today and tomorrow.
the VSM along with the simulation of the developed model. Productivity Press.
International Journal of Advanced Manufacturing Technology is a copyright of Springer,
2016. All Rights Reserved.

You might also like