General Tenant Construction Guidelines
General Tenant Construction Guidelines
This chapter guides the merchant in going through the three phases of his leased space construction: Pre-
Construction, Actual Construction, and Post-Construction phases.
1. PRE-CONSTRUCTION PHASE
1.1 Award letter
This is the formal communication from the owner, Century City Development Corp. (CCDC) officially
informing a prospective merchant of the acceptance of his application and indicating basic information, terms
and conditions. A copy of the Award Letter with the merchant's conforme must be returned to CCDC. This
letter is necessary for securing municipal permits.
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
1.4.1 Schedule of receiving plans
TIME DAY PLACE
9:30 a.m. – 3:00 p.m. Mon. - Fri. Admin Office
1.4.2. CCDC shall notify the merchant when the plans are ready for pick-up.
1.4.3 Processing and evaluation period shall be Ten (10) working days from the receipt of the plans.
1.4.4 Plans received after 3:00PM shall be considered submitted the following day.
1.4.5 Incomplete plans shall not be received. It is the merchant’s responsibility to comply all
requirements to prevent any delay in the process.
All sheets of drawings submitted must properly indicate the Store Name/Office
Name, Shop Number/Office Number, Nature of Occupancy/Operation (e.g. Boutique, Men's
Shoe Store, Restaurant, etc.), specific floor, via a key plan.
For example: Store XYZ, Novelty Store, Shop # L100, Ground floor, Century City
Mall
All working drawings submitted for review must be properly collated, arranged
and stapled on the upper, middle and lower left side of each set of drawings. This is to enable
CCDC/CPMI to immediately: 1) establish the number of sets of drawings, 2) determine how
many sheets per set have been submitted and, 3) ensure that no sheets are detached from the
set so as to avoid misplaced drawings/sheets.
Construction Plans – Complete 11 sets
Plans submitted must contain the following:
o Architectural Plans (duly signed by registered and licensed Architect
or Interior Designer only)
Colored perspective
- Submit a separated print in 1/8 size illustration board
A plan showing the location of the Merchant store
Floor Plan
Longitudinal and Cross Sections
Elevations
Reflected Ceiling Plan
Furniture layout
Sign Details
Board-Up Details (if applicable)
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
Structural details of Mezzanine Floors (if applicable, and if approved
by consultant and allowed by Owner)
o Electrical Plans
Riser Diagram
Load Schedule (Normal Power)
Power Layout
Lighting Layout/illumination Proposals
Specifications
Legend
Details of any Electrical Equipment (if applicable)
o Other Plans
Details of Security / Burglar Alarm Systems
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
1.5.2 Electrical Permit
1.5.3 Structural, Mechanical, Sanitary Permits (when applicable)
The merchant shall properly display/post all necessary municipal permits on exterior of
barricade/board up at all times. Copies of these permits must be submitted to the Property Management
Office (CPMI) thru CCDC.
The merchant must provide ID cards for the proper identification of his construction workers/personnel
to be given access to the premises during the construction phase. The ID's must be properly filled out and sealed
to avoid tampering. These should be worn at all times within the construction site.
2 CONSTRUCTION PHASE
2.1 Board Up (if applicable)
2.1.1 Before any construction is allowed, leased premises must be properly boarded up.
2.1.2 Board up shall be constructed of plywood, painted white (unless there is specific design for the
building) with a provision for an access door for CCDC/CPMI inspection purposes. This door shall swing
towards the merchant space so as not to obstruct mall traffic. It shall remain closed at all times during
construction and shall be properly padlocked during non-construction hours.
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
- Spray Painting
- Welding
- Electrical Testing
- Sanding
- All other works which disturb operations of adjacent spaces and which endanger the safety of the
building and its occupants.
2.3.1 All tenants, their workers, supervisors and other parties involved in the construction of the space
must log in with the building security guard upon entry into the building. The Property Management Office
(CPMI) shall announce the location of designated entry/exit points.
2.3.2 Identification cards must be worn at all times while inside the building premises. Those without
ID's shall not be allowed to enter.
2.3.3 All construction workers must be in Shirts bearing the tenant’s / contractor's logo, long pants and
shoes. Workers must wear hard hats at all times. Sandos, short pants, sandals or slippers and the like are
prohibited. Those not properly attired shall not be allowed to enter the premises.
2.3.4 Workers and their supervisors are not allowed to loiter within the building premises.
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
2.7 Fire Safety
2.7.1 One (1) unit- 20lb. ABC type fire extinguisher must be provided for every 11.40 radius. An
extinguisher must be provided and a fire watch assigned where welding and/or gas cutting operations is
performed.
2.7.2 Smoking is strictly prohibited within the construction site.
2.7.3 Cooking is strictly prohibited within the construction site.
2.7.4 Water supply and distribution facilities for firefighting purposes shall be provided and
maintained in the construction site in accordance with the Local Fire Code.
2.8 Others
2.8.1 Tapping of Utilities - Tapping of electrical, mechanical, fire protection, and plumbing utilities
must be done in coordination with the Property Management Office (CPMI).
2.8.2 Security - Security within the space is the sole responsibility of the merchant.
2.8.3 Sanitation - The leased space as well as the common areas must be kept clean and free from foul
odor. Garbage/Construction debris must not remain lying outside the merchant space. This must be hauled out
of the building every day.
2.8.4 Portable Toilets - Portable toilets shall be available for the use of all workers. These shall be
placed in an area accessible to all.
2.8.5 Medical Facilities - First Aid Kits must be provided by each merchant at the construction site for
the use in case of emergency.
2.8.6 Protective Apparel - Personal protective devices (hard hats, gloves, boots, etc.) shall be
furnished by the contractor as needed.
2.8.7 Safety Materials/Equipment - The contractor shall provide safety measures such as
construction nets, sheeting, shoring etc. whenever necessary.
2.8.8 Obstruction - Work will not be permitted outside the merchant's leased space. Construction
materials will neither be allowed to lie outside the merchant space nor in any other common area of the
building.
2.8.9 Damages - The merchant/contractor shall be responsible for any damages incurred resulting from
the construction of the space. Likewise, death and/or injuries within the premises shall be the merchant's sole
responsibility.
2.8.10 Behavior of Workers - The merchant is responsible for controlling the conduct of their
contractors and workers. CPGI/CPMI has the right to remove a worker for any misdemeanor.
2.8.11 Routine inspections – CCDC/CPMI and their assigned representatives shall make their routine
inspections of all construction sites as often as necessary. All observations and instructions given by the
inspectors (indicated on merchant construction checklists - See "Annex C") must be taken note of and
strictly followed. CCDC/CPMI reserves the right to issue construction changes on approved plans when
deemed necessary.
2.8.12 Pre-Final Inspection - Merchant shall request CPMI thru CCDC (in written form) at least three
(3) days in advance, to conduct a pre-final inspection prior to the following critical construction activities:
Permanent closure of ceiling.
Pouring of concrete.
2.8.13 Testing and Commissioning - The Merchant shall inform CPMI thru CCDC (through a written
request) at least three (3) days in advance, to witness the following:
Hydrotest - fire protection
Flow test - plumbing and sanitary
Smoke alarm test - fire protection
Insulation test – electrical
Flood test - plumbing and sanitary (if applicable)
Load test – electrical
Leak test - mechanical (LPG and exhaust system )
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
2.8.14 Supervisors - Merchant shall assign key personnel (Project Manager, Supervisor or Foreman)
to be present at all times at the construction site for coordination purposes. All communications related to
Merchant construction will be directed to designate key personnel.
2.8.15 Compliance - Violations and/or non-compliance with any or all of the above guidelines and
requirements and deviations from approved plans shall constitute grounds for the stoppage of construction
especially when previous notices remain uncorrected or unresolved. A written Work Stoppage shall be issued
for this purpose. The merchant shall be responsible for the communication and implementation of all
Construction Guidelines to his assigned contractor.
2.8.16 Monetary Penalties - Monetary penalties shall be imposed upon the merchant for any and all
violations and/or non- compliance with the above Construction Guidelines and deviation from approved plans:
Gross violations even on the first offense shall be automatically penalized with a Work
Stoppage Order and a fine of P3,000.00.
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
Main office address and telephone number (Only the signatures of the owner (s) and their
authorized representatives.
Store telephone number representatives shall be honored for permit purposes.)
Emergency telephone number(s) (This shall be used in case of any emergency during non-
operating hours.)
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200
ANNEX "A"
STANDARD GUIDELINES FOR CONDUCTING LEASE RE-MEASUREMENTS (LR) IN CENTURY CITY
MALL
________________________________________________________________________________________________________
Managed by Century Properties Management, Inc
Century City Mall, Kalayaan corner Salamanca Avenue, City of Makati
Telephone Numbers 635-705-6200