Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 118

PAINTING WORKS

1.5 1.928571 2.142857 0.214286 0.428571 0.642857


3.5 4.5 5 0.5 1 1.5
3.808 4.896 5.44 0.544 1.088 1.632

cpf 82.56 2 165.1152 25 6.604608 18

doors
2.1
0.9
1.89 2 2 2 15.12 25 0.6048 1.25
facia

5.54
5.54
4.996
4.996
8.4
8.4

37.872 0.25 2 18.936 25 0.75744


199.1712 1.36224 2
199.1712
ROOFING WORKS

1.5 1.928571 2.142857 0.214286 2.357143 0.6428571429


3.5 4.5 5 0.5 5.5 1.5
3.808 4.896 5.44 0.544 5.984 1.632

Length width # sets AREA


5.440 0.70 1.00
0.10 3.00
0.70

5.540 4.40 1.00 24.38

4.896 0.70 1.00


0.10 3.00 #DIV/0!
0.70

4.996 4.40 1.00 21.98

46.36
CARPENTRY WORKS

1.5 1.928571 2.142857 0.214286 0.428571 0.6428571429


3.5 4.5 5 0.5 1 1.5
3.808 4.896 5.44 0.544 1.088 1.632

Length width # sets area


5.385 0.70 1.00
- 3.00
0.70

5.385 4.40 1.00 23.69

4.837 0.70 1.00


- 3.00
0.70

4.837 4.40 1.00 21.28

44.98
PLYWOOD 16.00 pcs
CEILING JOIST 225.00 bd.ft
CEMENT PLASTER FINISH

MAIN WALL
Length height #sets # faces AREA
7.00 2.60 1.00 1.00
7.00
9.00
3.00

26.00 2.60 1.00 1.00 67.60


9.00 2.80 1.00 1.00 25.20
APEX
Length height #sets # faces
7.00 1.50 1.00 1.00 10.50

GROUND
Length height #sets # faces
- 0.20 1.00 1.00
-
-
3.00
-
2.00

5.00 0.20 1.00 1.00

LESS WINDOWS
Length height #sets # faces
0.70 1.177 4.00 (2.00) (6.59)
0.70 1.177 8.00 (1.00) (6.59)
LESS DOORS
Length height #sets # faces
0.90 2.10 2.00 (2.00) (7.56)

82.56
MASONRY WORKS

MAIN WALL
length height # sets AREA
5.00 0.40 1.00
5.00 0.20
3.00 2.60
3.00 (0.25)

16.00 2.95 1.00 47.20

APEX
length height # sets
3.00 1.20 1.00 3.60

ALLEY
length height # sets
3.00 0.20 1.00
1.20 0.20
1.20

5.40 0.40 -

RAMP
length height # sets
2.00 0.20 0.50
2.00
-

4.00 0.20 -

SEPTIC VAULT
length height # sets
1.00 1.50 1.00
1.00
2.40
2.40

6.80 1.50 1.00

LESS WINDOWS #
length height # sets
1.80 1.200 (2.00) (4.32)
1.20 1.200 (2.00) (2.88)
LESS DOORS #
length height # sets 0.4 28 11.2
0.90 2.10 (1.00) (1.89)

41.71
STRUCTURAL CONCRETE

FOOTING
width length depth # sets
0.80 0.80 0.25 4.00 0.64

COLUMN
width length depth # sets
0.15 0.40 1.10 4.00
(0.25)
0.20
2.60
(0.25)

0.15 0.40 3.40 4.00 0.82

COLUMN APEX
width length depth # sets
0.15 0.40 1.50 -

BEAM
width length depth # sets
0.15 5.00 0.25 1.00
5.00
3.00
3.00

0.15 16.00 0.25 1.00 0.60

SLOPING BEAM
width length depth # sets
0.10 2.77 0.20 4.00 0.22

FLOORING SLAB
width length depth # sets
5.00 3.00 0.075 1.00 1.13
1.20 3.00 0.075 -

WALL FOOTING
width length depth # sets
0.30 5.00 0.15 1.00
5.00
3.00
3.00

0.30 16.00 0.15 1.00 0.72

0.30 1.20 0.10


1.20
3.00
0.30 5.40 0.10 -

RAMP
width length depth # sets
1.20 2.00 0.075 -

SEPTIC VAULT
width length depth # sets
1.00 2.40 0.10 1.00
1.00 2.40 0.08 1.00
4.12
REINFORCING STEEL BARS
1.100917 1.090909 1.071429
FOOTING 16mm 12mm 10mm TIE WIRE
Length #pcs # sets kg/m
F-1 0.90 10.00 4.00 0.888 31.97 5.60

COLUMN
Length #pcs # sets kg/m
C-1 0.20
1.10 1.6
0.20 6 6
2.60 8 4.4
0.05
4.15 76.8 1.6
4.15 6.00 4.00 0.888 88.44 237.60 121.1904 1.578 0

TIES 1.1
Length #pcs # sets kg/m 6 #VALUE!
0.80 15.00 4.00 1 1.1
0.30 18.00 20

1.10 33.00 4.00 0.616 89.44 89.4432 0.616 55.09701 22

TIES AT APEX 0.616 40


1.10 10.00 0.616 - 55.0970112 100 0 880

LINTEL BEAM
Length #pcs # sets kg/m
5.40 4.00 1.00
5.40
3.40
3.40

17.60 5.10 1.00 0.888 79.71 177.48 1.578 1.578 0 2.1


#VALUE!
STIRRUPS 0.25
Length #pcs # sets kg/m 4.5 3.5 #VALUE!
0.50 34.00 1.00 0.2 0.2
0.30 34.00 22.5 17.5
0.10 24.00
24.00
#VALUE!
0.90 116.00 1.00 0.616 64.31 0.616 0.616 39.61521
SLOPING BEAM
Length #pcs # sets kg/m
2.77 2.00 4.00

2.77 2.00 4.00 0.616 13.65 50.40


3.93
STIRRUPS 0.2
Length #pcs # sets kg/m
0.20 21.00 4.00 12
0.10 31.65

0.30 21.00 4.00 0.616 15.52

SEPTIC VAULT

1.20 25.00 30.00 31-Dec


2.60 6.00 15.60
-
1.20 8.00 9.60
1.90 4.00 7.60
62.80 0.616

WALL FOOTING
Length #pcs # sets kg/m
5.00 2.00 1.00
5.00
3.00
3.00

16.00 2.00 1.00 0.616 19.71 28.80 19.712 0.616 12.14259

TIES
0.30 16.00
(1.60)

0.30 14.40 0.30 0.616 8.87 5.464166


48.00 17.60676

DOWELS
Perimeter Spacing # pcs Length kg/m
VERTICALS 5.00 0.60 8.00 0.20
5.00 0.60 8.00 0.40
3.00 0.60 4.00 0.20
3.00 0.60 4.00 2.60

24.00 3.40 0.616 50.27 28.80 50.2656 0.616 30.96361

DOWELS
Perimeter Spacing # pcs Length kg/m
HORIZONTALS 0.40 0.60 5.00
0.20 5.00
2.60 3.00
(0.25) 3.00

2.95 0.60 4.00 16.00 0.616 39.42 39.424 0.616 24.28518


528.68
- 200.12 301.20 48.18

1.100000 1.100000 1.100000 10.97


- 220.13 331.32 551.45
10 mm 6 0.4 5.6 1.02 1.092857 1.092857
12 mm 6 0.45 5.55 1.02 1.102703 1.102703
16 mm 6 0.55 5.45 1.02 1.122936 1.122936

#VALUE!
6.666667
6.666667

6.666667
BACKFILL

area main
inside
Length Width Depth # Sets Volume
5.00 3.00 0.125 1.00 1.88
5.00 1.20 0.125 1.00 -
cr
2.00 1.80 0.10 2.00 -

1.88
ramp

1.8 0.5
1.8
1.5
5.1 0.5 2.55
gross 2.55

window #
wid hgt
0.7 1.177 10 8.239

doors
2.1 0.9 2 3.78
2.1 0.6 1 1.26
13.279

net -10.729

septic

wid hght
1 1.5
1
2.4
2.4
6.8
6.8 1.5 10.2
-0.529
Excav

Footing
width length depth # Volume
0.80 0.80 1.10 4.00 2.82

Wall footing
width length depth
0.30 5.00 0.60
5.00
3.00
3.00
(3.20)

0.30 12.80 0.60 2.30

0.30 1.20 0.30


1.20
5.00

0.30 7.40 0.30

septc tnk
width depth height
1.00 2.40 1.40
5.12
BACK-UP COMPUTATION
Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
0.80 0.80 1.10 4.00 2.82
WALL FOOTING
13.00 0.30 0.60 1.00 2.34
7.50 0.30 0.30 1.00 0.68

TOTAL 5.83 CU.M

ITEM 104 STRUCTURE BACKFILL

LENGTH WIDTH DEPTH # SETS QUANTITY


MAIN FLOORING
5.00 3.00 0.125 1.00 1.88
CORRIDOR
5.00 1.20 0.125 1.00 0.75

TOTAL 2.63 CU.M

ITEM 404 REINFORCING STEEL BARS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


FOOTING
0.90 10.00 4.00 0.888 1.10 35.16
COLUMN
4.15 6.00 4.00 0.888 1.10 97.29
LATERAL TIES
1.10 33.00 4.00 0.616 1.10 98.39
BEAM
17.60 5.10 1.00 0.888 1.10 87.68
STIRRUPS
0.90 120.00 1.00 0.616 1.10 73.18
SLOPING BEAM
2.77 2.00 4.00 0.616 1.10 15.02
STIRRUPS
0.30 21.00 4.00 0.616 1.10 17.08
WALL FOOTING
16.00 2.00 1.00 0.616 1.10 21.68
STIRRUPS
0.30 50.00 1.00 0.616 1.10 10.16
VERTICAL DOWELS
3.50 24.00 1.00 0.616 1.10 56.92
HORIZONTAL DOWELS
16.00 4.00 1.00 0.616 1.10 43.37

TOTAL 555.92 Kgs.


ITEM 405 STRUCTURAL CONCRETE

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
0.80 0.80 0.25 4.00 0.64
COLUMN
3.40 0.15 0.40 4.00 0.82
BEAM
16.00 0.15 0.25 1.00 0.60
SLOPING BEAM
2.80 0.10 0.20 4.00 0.22
SLAB
3.00 5.00 0.075 1.00 1.13
3.00 1.20 0.075 1.00 0.27
WALL FOOTING
16.00 0.30 0.15 1.00 0.72

TOTAL 4.40 CU.M

ITEM 409 STRUCTURAL STEEL

Q = ALL Q = ALL

ITEM 704 MASONRY WORKS

LENGTH HEIGHT # SETS QUANTITY


MAIN WALL
16.00 3.00 1.00 48.00
APEX
5.40 0.90 1.00 4.86
LESS WINDOWS
1.80 1.20 (2.00) -4.32
1.20 1.20 (2.00) -2.88
LESS DOORS
0.90 2.10 (1.00) -1.89

TOTAL 43.77 SQ.M


ITEM 1013 ROOFING WORKS

LENGTH WIDTH # SETS QUANTITY


MAIN ROOFING
3.00 6.40 1.00 19.20
3.25 6.40 1.00 20.80

TOTAL 40.00 SQ.M

ITEM SPL.1 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL

PREPARED BY:

628 CONSTRUCTION ENTERPRISES


CONTRACTOR
NAME OF PROJECT : Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
LOCATION: Malasiqui, Pangasinan
CALENDAR DAYS: 75 CD
405
34 CD
MOVE OUT
MOVE IN 803 404 SPL 1 SPL 4 SPL 4
15 CD 1 7CD 1 CD
1 CD 10 CD 21 CD 14 CD
SPL 2
20CD
SPL 5
75 CD

PERT / CPM

BAR CHART/ S- CURVE


CALENDAR DAYS
ITEM No DESCRIPTION QTY UNIT TOTAL ITEM COST % WT
25 50 75
100
#REF!
804 (a) Backfilling of excavated materials 12.10 cu.m. 549.39 #REF!

#REF!
#REF! #REF! #REF! #REF! #REF! #REF!

#REF!
404 (a.1) Reinforcing Steel for Column Footing & WF 2,103.41 kgs 119,547.94 #REF!

#REF! #REF! 75
1010 Door 426.72 sq.m 20,475.28 #REF!

#REF!
SPL1 Personal Protective Equipments (PPE) 480.00 Mandays/proj. - #REF!

#REF!
Spl. 1 Railings #REF! SQ.M. - #REF!

#REF! #REF! 50
#REF! #REF! #REF! #REF! #REF! #REF!

#REF!
#REF! #REF! #REF! #REF! #REF! #REF!

#REF!
#REF! #REF! #REF! #REF! #REF! #REF! 25

#REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF!


#REF! #REF! #REF! #REF! #REF! #REF!
0
TOTAL #REF! #REF! #REF! #REF! #REF!
###
CASH FLOW
ACCOMPLISHMENT 25 50 75
PERIODIC P #REF! #REF! #REF!
AMOUNT A
CUMMULATIVE P #REF! #REF! #REF!
A
PERIODIC P #REF! #REF! #REF!
PERCENTAGE A
CUMMULATIVE P #REF! #REF! #REF!
A
SLIPPAGE

Prepared by: Submitted By: Recommending Approval: APPROVED:

ELDRED M. MISLANG BLESILDA P. ESTRADA AQUILINO M. NICER MARIETA B. MENDOZA


Acting Chief, Planning & Design Section OIC-chief, Planning & bDesign Section OIC-Asst. District Engineer OIC-District Engineer
APPROVED BUDGET FOR THE CONTRACT

PROJECT TITLE: Construction of Technical and Vocational-Livelihood Laboratory Building at Speaker Eugenio Perez National Agricultural School
San Carlos City, Pangasinan
Contract Duration 90 C.D.
Princeton Integrated School: An Innovative Green Engineer Design
ITEM TOTAL INDIRECT
DESCRIPTION QUANTITY UNIT MARK-UP IN % TOTAL MARK-UP
NO. TOTAL DIRECT COST VAT COST TOTAL COST (pesos) UNIT COST (pesos)
OCM CP TOTAL (%) VALUE (pesos)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 ) ( 11 ) ( 12 ) ( 13 )
803(a) Structure Excavation (common earth) 26.15 cu.m. 7,686.63 12% 10% 22% 1,691.06 468.88 2,159.94 9,846.57 376.57
804 (a) Backfilling of excavated materials 12.10 cu.m. 428.87 12% 10% 22% 94.35 26.16 120.51 549.39 45.42
804 (b) Embankment (Backfilling & Tampering) 59.02 cu.m. 21,563.65 12% 10% 22% 4,744.00 1,315.38 6,059.39 27,623.04 468.03
1000 (a) Soil Poisoning 191.25 SQ.M 10,906.01 12% 10% 22% 2,399.32 665.27 3,064.59 13,970.59 73.05
404 (a.1) Reinforcing Steel for Column Footing & WF 2,103.41 kgs 93,323.92 12% 10% 22% 20,531.26 5,692.76 26,224.02 119,547.94 56.84
900 (a.1) Reinforce Concrete Column Footing & FTB 15.85 cu.m. 48,111.92 12% 10% 22% 10,584.62 2,934.83 13,519.45 61,631.37 3,887.45
404 (a.2) Reinforcing Steel for Column 1,829.42 kgs 81,438.88 12% 10% 22% 17,916.55 4,967.77 22,884.32 104,323.20 57.03
900 (a.2) Reinforce Concrete for Column 6.98 cu.m. 57,113.49 12% 10% 22% 12,564.97 3,483.92 16,048.89 73,162.38 10,477.96
404 (a.3) Reinforcing Steel for Beam 1,894.92 kgs 84,355.04 12% 10% 22% 18,558.11 5,145.66 23,703.77 108,058.80 57.03
900 (a.3) Reinforce Concrete for Beam 6.79 cu.m. 52,048.72 12% 10% 22% 11,450.72 3,174.97 14,625.69 66,674.41 9,821.31
404 (a.4) Reinforcing Steel for Slab on fill 2,644.35 klgs. 115,906.76 12% 10% 22% 25,499.49 7,070.31 32,569.80 148,476.57 56.15
900e Reinforce Concrete Slab on Fill 803.65 cu.m. 2,399,157.18 12% 10% 22% 527,814.58 146,348.59 674,163.17 3,073,320.34 3,824.20
506(1) Masonry Works (CHB) 7,418.65 sq.m 3,858,089.85 12% 10% 22% 848,779.77 235,343.48 1,084,123.25 4,942,213.09 666.19
1010 Door 426.72 sq.m 15,983.83 12% 10% 22% 3,516.44 975.01 4,491.46 20,475.28 47.98
1018 Ceramic Tiles 15.80 sq.m 17,049.64 12% 10% 22% 3,750.92 1,040.03 4,790.95 21,840.58 1,382.32
1002 Plumbing Works All L.S. 890,335.80 12% 10% 22% 195,873.88 54,310.48 250,184.36 1,140,520.16 979,369.38
1006 Steel Window 816.48 SQ.M 119,097.60 12% 10% 22% 26,201.47 7,264.95 33,466.43 152,564.03 186.86
1010 (a) Door Frames & Accessories 214.00 SETS 10,568.62 12% 10% 22% 2,325.10 644.69 2,969.78 13,538.40 63.26
1027 Cement Plaster Finish 14,957.06 sq.m 2,438,800.59 12% 10% 22% 536,536.13 148,766.84 685,302.96 3,124,103.55 208.87
403 (a) Steel Trusses #REF! kgs #REF! 12% 10% 22% #REF! #REF! #REF! #REF! #REF!
1003 Carpentry & Joinery Works 226.65 SQ.M. 102,467.39 12% 10% 22% 22,542.83 6,250.51 28,793.34 131,260.73 579.13
1013 Roofing Works 240.36 sq.m 168,133.30 12% 10% 22% 36,989.32 10,256.13 47,245.46 215,378.75 896.06
1032a-2 Wooden Painting 476.78 SQ.M 39,568.67 12% 10% 22% 8,705.11 2,413.69 11,118.80 50,687.47 106.31
1032a-1 Masonry Painting 59,828.24 SQ.M 2,516,808.39 12% 10% 22% 553,697.85 153,525.31 707,223.16 3,224,031.55 53.76
1100 Conduit Boxes & Fittings 144.00 L.M. 12,403.78 12% 10% 22% 2,728.83 756.63 3,485.46 15,889.25 110.34
1101 Wires & Wiring Devices 640.00 L.M. 57,240.75 12% 10% 22% 12,592.96 3,491.69 16,084.65 73,325.40 114.57
1102a Lighting Fixtures 21.00 SETS 40,750.02 12% 10% 22% 8,965.00 2,485.75 11,450.76 52,200.78 2,485.75
1102 Panel Boards & Cabinets 1.00 set 11,595.24 12% 10% 22% 2,550.95 707.31 3,258.26 14,853.50 14,853.50
Spl. 1 Railings #REF! SQ.M. #REF! 12% 10% 22% #REF! #REF! #REF! #REF! #REF!
Spl.2 Occupational Safety & Health All LS #REF! 0% 10% 10% #REF! #REF! #REF! #REF! #REF!
Spl 3 Project Billboard 1.00 each 7,796.31 0% 10% 10% 779.63 428.80 1,208.43 9,004.74 9,004.74
TWO MILLION FIVE HUNDRED EIGHTY SEVEN THOUSAND PESOS ONLY #REF! #REF! TOTAL: #REF!

PREPARED/SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED

ALEX S. MAIQUEZ EDITA L. MANUEL MARIETA B. MENDOZA


Chief, Planning & Design Section Assistant District Engineer Distric Engineer
BACK-UP COMPUTATION
Princeton Integrated School: An Innovative Green Engineer Design

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
F1 1.20 1.20 1.10 12.00 19.01
SEPTIC VAULT S.V. 3.40 1.00 2.10 1.00 7.14
TOTAL 26.15 CU.M

ITEM 804 BACKFILLING OF EXCAVATED MATERIALS


(a.)
LENGTH WIDTH DEPTH # SETS QUANTITY
FOOTING
F1 1.20 1.20 0.70 12.00 12.10
TOTAL 12.10 CU.M

ITEM 804b EMBANKMENT (BACKFILLING & TAMPERING)


(a.) STRUCTURE BACKFILL (river mix)
LENGTH WIDTH DEPTH # SETS QUANTITY
MAIN FLOORING
22.50 7.00 0.325 1.00 51.19
CORRIDOR
22.50 1.50 0.20 1.00 6.75
Sub-Total 57.94 CU.M

(b.) GRAVEL BEDDING


LENGTH WIDTH DEPTH # SETS QUANTITY
FOOTING
F1 1.20 1.20 0.05 12.00 0.86
RAMP 21.79 0.20 0.05 1.00 0.22
0.00
Sub-Total 1.08 CU.M
TOTAL 59.02 CU.M
ITEM 1000 (a) TERMITE CONTROL WORKS
LENGTH WIDTH
MAIN FLOORING
22.50 7.00 157.50
CORRIDOR
22.50 1.50 33.75
191.25 SQ.M

ITEM 900 R.C. COLUMN FOOTING/FTB/WALL FOOTING


(a.)
LENGTH WIDTH DEPTH # SETS QUANTITY
FOOTING
F1 1.20 1.20 0.25 12.00 4.32
FTB 1 4.20 0.25 0.40 10.00 4.20
FTB 2 6.65 0.25 0.40 6.00 3.99
TOILET WF 5.20 0.20 0.60 1.00 0.62
RAMP 21.79 0.15 0.10 1.00 0.33
CORRIDOR 25.50 0.30 0.10 1.00 0.77
stair front 27.54 0.15 0.10 1.00 0.41
SEPTIC VAULT 10.80 0.45 0.25 1.00 1.22
TOTAL 15.85 CU.M
ITEM 404 REINFORCING STEEL BARS FOR COL.FOOTING/FTB/WF
(a.)
LENGTH # PCS # SETS kg/m F.S. QUANTITY
FOOTING
F1 1.30 14.00 12.00 1.579 1.10 379.34
FTB 1 4.50 6.00 10.00 1.579 1.10 468.96
Stirrups 1.40 24.00 10.00 0.616 1.10 227.67
FTB-2 7.00 10.00 6.00 1.579 1.10 729.50
Stirrups 1.40 22.00 6.00 0.616 1.10 125.22
TOILET ( C.R.) 5.20 3.00 1.00 0.616 1.10 10.57
0.30 19.00 1.00 0.616 1.10 3.86
CORRIDOR W.F. 25.50 3.00 1.00 0.616 1.10 51.84
0.30 85.00 1.00 0.616 1.10 17.28
STAIR W.F. 27.54 2.00 1.00 0.616 1.10 37.32
0.15 92.00 1.00 0.616 1.10 9.35
SEPTIC VAULT 10.80 3.00 1.00 0.888 1.10 31.65
0.30 37.00 1.00 0.888 1.10 10.84
TOTAL 2,103.41 KLGS.

ITEM 900 R.C. COLUMN


(c.)
LENGTH WIDTH DEPTH # SETS QUANTITY
COLUMN
C1 4.40 0.35 0.35 12.00 6.47
Stiffener 2.80 0.15 0.30 2.00 0.25
PC 1.75 0.25 0.30 2.00 0.26
TOTAL 6.98 CU.M

ITEM 404 REINFORCING STEEL FOR COLUMN


(c.)
LENGTH # PCS # SETS kg/m F.S. QUANTITY

C1 4.40 8.00 12.00 2.467 1.10 1,146.27


Stiffener 3.40 4.00 2.00 0.888 1.10 26.57
PC 1.75 4.00 2.00 0.888 1.10 13.68
LATERAL TIES -
C1 1.50 49.00 12.00 0.616 1.10 597.64
Stiffener 1.00 19.00 2.00 0.616 1.10 25.75
PC 1.20 12.00 2.00 0.616 1.10 19.51
TOTAL 1,829.42 CU.M

ITEM 900 R.C. CONC. BEAM


(d.)
LENGTH WIDTH DEPTH # SETS QUANTITY
BEAM
RB-1 front 22.50 0.25 0.30 2.00 3.38
RB-2 rear 7.00 0.25 0.20 6.00 2.10
LRB-1,SLOPING BEAM front 5.51 0.25 0.25 2.00 0.69
LRB-1,SLOPING BEAM rear 5.00 0.25 0.25 2.00 0.63
TOTAL 6.79 CU.M
ITEM 404 REINFORCING STEEL FOR BEAMS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


BEAMS
RB-1 22.50 4.00 2.00 1.579 1.10 312.64
STIRRUPS 1.20 39.00 10.00 0.616 1.10 317.12
RB-2 7.00 9.00 6.00 1.579 1.10 656.55
STIRRUPS 1.40 28.00 10.00 0.616 1.10 265.62
LRB-1 SLOPING BEAM

FRONT 5.60 4.00 2.00 1.579 1.10 77.81


STIRRUPS
1.10 39.00 2.00 0.616 1.10 58.14
LRB-1 SLOPING BEAM
REAR 5.00 4.00 2.00 1.579 1.10 69.48
STIRRUPS
1.10 36.00 2.00 1.579 1.10 137.56
0.00
TOTAL 1894.92 KLGS.
ITEM 900 R.C. CONC. SLAB
(e.)
LENGTH WIDTH DEPTH # SETS QUANTITY
SLAB 85.00 17.00 0.10 5.00 722.50
Less elevator 3.00 3.00 0.10 4.00 -3.60
3.00 3.00 0.10 5.00 -4.50
Canopy front 85.00 1.50 0.10 5.00 63.75
Canopy rear 85.00 0.60 0.10 5.00 25.50
TOTAL 803.65 CU.M
ITEM 404 REINFORCING STEEL FOR SLAB
(a)
LENGTH # PCS # SETS kg/m F.S. QUANTITY

SLAB(classrm.) 85.00 25.00 1.00 0.616 1.10 1439.90


7.00 76.00 1.00 0.616 1.10 360.48
CORRIDOR
1.50 75.00 1.00 0.616 1.10 76.23
85.00 6.00 1.00 0.616 1.10 345.58
RAMP/LANDING 13.39 17.00 1.00 0.616 1.10 154.24
4.80 34.00 1.00 0.616 1.10 110.58
CONC. SINK 2.80 4.00 1.00 0.616 1.10 7.59
0.65 15.00 1.00 0.616 1.10 6.61
CONC. PATHWAYS 20.00 5.00 1.00 0.616 1.10 67.76
1.00 68.00 1.00 0.616 1.10 46.08
S.V. SLAB 3.40 5.00 1.00 0.888 1.10 16.61
1.00 13.00 1.00 0.888 1.10 12.70
2,644.35 klgs.

ITEM 506 (1) MASONRY WORKS (CHB)

LENGTH HEIGHT # SETS QUANTITY


MAIN WALL
200.00 3.20 5.00 3200.00
PARTITION 1428.00 3.20 1.00 4569.60
C.R. 57.00 3.20 5.00 912.00
S.V.WALL 10.80 0.00
PLANT BOX 4.60 0.00
LESS WINDOWS
W1 1.80 2.10 88.00 -332.64
W2 1.80 1.20 224.00 -483.84
W3 0.50 0.50 79.00 -19.75
LESS DOORS
D1 1.00 2.10 178.00 -373.80
D2 0.70 2.10 36.00 -52.92
TOTAL 7418.65 SQ.M

ITEM 1010 DOOR


(b.)
LENGTH HEIGHT # SETS QUANTITY
MAIN DOOR
D1 1.00 2.10 178.00 373.80
D2 0.70 2.10 36.00 52.92
426.72 SQ.M

ITEM 1018 CERAMIC TILE WORKS

LENGTH WIDTH # SETS QUANTITY


UNGLAZED
C.R.
FLR TILES 1.80 1.70 1.00 3.06
CLASS RM. 22.50 7.00 1.00
SUB TOTAL 3.06
GLAZED
WALL TILES 7.00 1.40 1.00 9.80
CONC.SINK 2.80 0.65 1.00 1.82
CONC.SINK WALL 2.80 0.40 1.00 1.12

SUB TOTAL 12.74


GRAND TOTAL 15.80

ITEM 1002 PLUMBING WORKS

Q = ALL Q = ALL

ITEM 1009 STEEL CASEMENT WINDOW


(1)
LENGTH HEIGHT # SETS QUANTITY

w1 1.80 2.10 88.00 332.64


w2 1.80 1.20 224.00 483.84
w3 0.50 0.50 79.00 19.75
TOTAL 816.48 SQ.M

ITEM 1010 DOOR FRAMES & ACCESSORIES


(b.) # SETS QUANTITY
214.00 214.00 SETS
ITEM 1027 CEMENT PLASTER FINISH

LENGTH HEIGHT # SETS # FACES QUANTITY


MAIN WALL
Front 85.00 3.20 5.00 2.00 2,720.00
Rear 81.00 3.20 5.00 2.00 2,592.00
2 Endwall 17.00 3.20 10.00 2.00 1,088.00
Partion 1,428.00 3.20 1.00 2.00 9,139.20
C.R 57.00 3.20 5.00 2.00 1,824.00
STAIR 3.00 3.00 5.00 1.00 45.00
LESS WINDOWS
W1 1.80 2.10 88.00 2.00 (665.28)
W2 1.80 1.20 224.00 2.00 (967.68)
W3 0.50 0.50 79.00 2.00 (39.50)

LESS DOORS
D1 0.90 2.10 178.00 2.00 (672.84)
D2 0.70 2.10 36.00 2.00 (105.84)
TOTAL 14,957.06 SQ.M

ITEM 1013 ROOFING WORKS

LENGTH WIDTH # SETS QUANTITY


MAIN ROOFING
5.316 23.30 1.00 123.86
5.000 23.30 1.00 116.50
TOTAL 240.36 SQ.M

ITEM 1003 CARPENTRY & JOINERY

LENGTH WIDTH SET QUANTITY


Ceiling inside 22.50 7.00 1.00 157.50
Ceilingoutside 5.50 0.40 2.00 4.40
5.00 0.40 2.00 4.00
22.50 1.50 1.00 33.75
22.50 1.20 1.00 27.00
TOTAL 226.65 SQ.M.

ITEM 1032 WOODEN PAINTING


(a-2)
LENGTH HEIGHT # SETS # FACES # COATS QUANTITY
DOORS 0.90 2.10 3.00 2.00 2.00 22.68
CEILING INSIDE 22.50 7.00 1.00 1.00 2.00 315.00
CEILING OUTSIDE 6.00 0.40 2.00 1.00 2.00 9.60
5.00 0.40 2.00 1.00 2.00 8.00
22.50 1.50 1.00 1.00 2.00 67.50
22.50 1.20 1.00 1.00 2.00 54.00
0.00
TOTAL 476.78 SQ.M

ITEM 1032 MASONRY PAINTING


(a-1)
LENGTH HEIGHT # SETS # FACES # COATS QUANTITY
MAIN WALL (PLASTERED AREA) Painting inside & outside wall
14957.06 SQ.M 2.00 2.00 59828.24
TOTAL 59,828.24 SQ.M

ITEM 1100 CONDUIT, BOXES AND FITTINGS

LENGTH WIDTH QUANTITY QUANTITY


PVC & RCS PIPE
3.00 1.00 46.00 138.00
3.00 1.00 2.00 6.00
TOTAL 144.00 L.M.

ITEM 1101 WIRES AND WIRING DEVICES


LENGTH WIDTH QUANTITY QUANTITY
WIRE 3.5MM2 600 600
WIRE 8.0MM2 40 40.00
TOTAL 640.00 L.M.

ITEM 1102 LIGHTING FIXTURES


(a.)
QUANTITY QUANTITY
21 21
TOTAL 21.00 SETS
ITEM 1102 PANEL BOARDS AND CABINETS

QUANTITY QUANTITY
1 1
TOTAL 1.00 SETS
SPL-1 Railings
LENGTH WIDTH QUANTITY QUANTITY
38mm dia. G.I. Pipe 9.00 22.00 198.00 L.M.
Accordion Dr. #REF! 2.90 #REF! SQ.M.
TOTAL #REF! SQ.M.

ITEM SPL.2 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL

ITEM SPL.3 PROJECT BILLBOARD

Q = 1 EACH Q = 1 EACH
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Pangasinan IV District Engineering Office
OFFICE OF THE DISTRICT ENGINEER
Area Equipment Compound
Sta. Barbara, Pangasinan
16-Feb-16
INDIVIDUAL PROGRAM OF WORK
Name of Project : Construction of Technical and Vocational-
Livelihood Laboratory Building at Speaker
Eugenio Perez National Agricultural School
Location : San Carlos City, Pangasinan Issued Obligated Authority :
Project Category : School Building Calendar Days to Complete : 90 CD
Appropriation : P2,600,000.00 Desirable Starting Date : Upon Approval
Source of Fund : Net Length :
% OF
DESCRIPTION OF WORK TO BE DONE EQUIPMENT/Nos.
TOTAL

One (1) Plate Compactor


Scope of Work: One (1) Bar Cutter (Manually Operated)
Construction of 1-Unit, Standard Technical and Vocational Building One (1) Concrete Mixer
( 22.50 x 7.00m.) Elevation 0.325 mtrs. One (1) Concrete Vibrator
Two (2) Welding Machine
1. Complete concrete works includes corridor, stair & ramp. Two (2) Electric Drill
2. Complete masonry works includes corridor, stair & ramp. Two (2) Riveter
3. Complete ceiling works, Iinside & outside.
TECHNICAL PERSONNEL REQUIRED
4.Plastering works complete includes corridor stair & ramp.
5. Roofing system complete w/ long span corr. Pre-painted roofing sheet w/ gutter. One (1) Const'n.Foreman
6. Complete masonry & wooden painting, includes window & door jamb & panel door. Two (2) Welder
7. Complete electrical works lighting & power & panel board. Two (2) Tinsmithman
8. With Blackboard & chalkdust bob. Two (2) Mason
9. With 4- wall fan. Two (2) Carpenter
10.With Comfort Room and concrete sink One (1) Steelman
11.With floor tiles at C.R. & conc.sink. Three (3) Laborer
12. Complete painting works ceiling & masonry wall. One (1) Electrician

ESTIMATED COST OF PROPOSED WORK


ADJUSTED COST
ITEM NO. DESCRIPTION UNIT QUANTITY
UNIT COST % TOTAL AMOUNT
803(a) Structure Excavation (common earth) cu.m. 26.15 376.57 #REF! 9,846.57
804 (a) Backfilling of excavated materials cu.m. 12.10 45.42 #REF! 549.39
804 (b) Embankment (Backfilling & Tampering) cu.m. 59.02 468.03 #REF! 27,623.04
1000 (a) Soil Poisoning SQ.M 191.25 73.05 #REF! 13,970.59
404 (a.1) Reinforcing Steel for Column Footing & WF kgs 2,103.41 56.84 #REF! 119,547.94
900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. 15.85 3,887.45 #REF! 61,631.37
404 (a.2) Reinforcing Steel for Column kgs 1,829.42 57.03 #REF! 104,323.20
900 (a.2) Reinforce Concrete for Column cu.m. 6.98 10,477.96 #REF! 73,162.38
404 (a.3) Reinforcing Steel for Beam kgs 1,894.92 57.03 #REF! 108,058.80
900 (a.3) Reinforce Concrete for Beam cu.m. 6.79 9,821.31 #REF! 66,674.41
404 (a.4) Reinforcing Steel for Slab on fill klgs. 2,644.35 56.15 #REF! 148,476.57
900e Reinforce Concrete Slab on Fill cu.m. 803.65 3,824.20 #REF! 3,073,320.34
506(1) Masonry Works (CHB) sq.m 7,418.65 666.19 #REF! 4,942,213.09
1010 Door sq.m 426.72 47.98 #REF! 20,475.28
1018 Ceramic Tiles sq.m 15.80 1,382.32 #REF! 21,840.58
1002 Plumbing Works L.S. All 979,369.38 #REF! 979,369.38
1006 Steel Window SQ.M 816.48 186.86 #REF! 152,564.03
1010 (a) Door Frames & Accessories SETS 214.00 63.26 #REF! 13,538.40
1027 Cement Plaster Finish sq.m 14,957.06 208.87 #REF! 3,124,103.55
403 (a) Steel Trusses kgs #REF! #REF! #REF! #REF!
1003 Carpentry & Joinery Works SQ.M. 226.65 579.13 #REF! 131,260.73
1013.00 Roofing Works sq.m 240.36 896.06 #REF! 215,378.75
1032a-2 Wooden Painting SQ.M 476.78 106.31 #REF! 50,687.47
1032a-1 Masonry Painting SQ.M 59,828.24 53.76 #REF! 3,224,031.55
1100 Conduit Boxes & Fittings L.M. 144.00 110.34 #REF! 15,889.25
1101 Wires & Wiring Devices L.M. 640.00 114.57 #REF! 73,325.40
1102a Lighting Fixtures SETS 21.00 2,485.75 #REF! 52,200.78
1102 Panel Boards & Cabinets set 1.00 14,853.50 #REF! 14,853.50
Spl. 1 Railings SQ.M. #REF! #REF! #REF! #REF!
Spl.2 Occupational Safety & Health LS All #REF! #REF! #REF!
Spl 3 Project Billboard each 1.00 9,004.74 #REF! 9,004.74
A. Civil Works #REF! #REF!
B. Construction Engineeringn .50% 0.50% P13,000.00
C. Project Cost
D. Acquisition of RROW
E. Cost of Completed Structure
F. Project Contingencies
G. Total Estimated Cost
0.50% say #REF!
Prepared By: Checked By:

ISADORA D. PORTUGUEZ ELDRED M. MISLANG


Architect II Asst. Chief Planning & Design Section

Submitted By: Recommending Approval:

ALEX S. MAIQUEZ EDITA L. MANUEL


Chief Planning & Design Section Assistant District Engineer

APPROVED:

MARIETA B. MENDOZA
Distric Engineer

CONCURRED:

DR. LORNA G. BUGAYONG, CESO VI


San Carlos City, Division Superintendent
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Pangasinan Sub-District Engineering Office
OFFICE OF THE DISTRICT ENGINEER
Area Equipment Compound
Sta. Barbara, Pangasinan

INDIVIDUAL PROGRAM OF WORK


4-Dec-12
NAME/ LOCATION OF PROJECT APPROPRIATION Php 627,000.00
Construction of 1-Storey, 1 CL.Rm. School SOURCE OF FUND
Building at Coliling NHS,Coliling,San Carlos ISSUED OBLIGATED AUTHORITY
City, Pangasinan RELEASED
CALENDAR DAYS TO COMPLETE 30 C.D
PROJECT CATEGORY DESIRABLE STARTING DATE ASAP
Multi-Purpose Building
PROJECT DESCRIPTION
WORK INCLUDES:
Demolition & Removal of obstruction.
Construction of kitchen with comport room (extension) with roofing, ceiling eaves, doors and windows.
Complete painting works: ceiling, ceiling eaves, wall and partition. (including existing walls and ceiling).
Installation of gutter.
Construction of septic vault with plumbing and fixtures.

MINIMUM EQUIPMENT REQUIREMENTS TECHNICAL PERSONNEL REQUIRED


Description No Description No
Plate Compactor 1 Const'n. Foreman 1
Bar Cutter (manually operated) 1 Welder 2
Concrete Mixer (1-Bagger) 1 Tinsmithman 1
Concrete Vibrator 1 Mason 2
Water truck (1000 gal) 1 Carpenter 1
Welding machine 1 Steelman 2
Electric Drill 1 Laborer 6
Riveter 1 Electrician 1
ESTIMATED COST OF PROPOSED WORK

TOTAL ITEM
ITEM NO. DESCRIPTION %TOTAL UNIT QUANTITY UNIT COST TOTAL UNIT COST
COST

Structure Excavation (common


803(a) earth) #REF! cu.m. 26.15 9,846.57 293.97 376.57
804 (a) Backfilling of excavated materials #REF! cu.m. 12.10 549.39 - 45.42
804 (b) Embankment (Backfilling & Tamperin #REF! SQ.M 59.02 27,623.04 #REF! #REF!
Reinforcing Steel for Column
404 (a.1) Footing & WF #REF! kgs 2,103.41 119,547.94 - 56.84
Reinforce Concrete Column
900 (a.1) Footing & FTB #REF! cu.m. 15.85 61,631.37
404 (a.2) Reinforcing Steel for Column #REF! kgs 1,829.42 104,323.20
900 (a.2) Reinforce Concrete for Column #REF! cu.m. 6.98 73,162.38
404 (a.3) Reinforcing Steel for Beam #REF! kgs 1,894.92 108,058.80
900 (a.3) Reinforce Concrete for Beam #REF! cu.m. 6.79 66,674.41
506(1) Masonry Works (CHB) #REF! sq.m 7,418.65 4,942,213.09
1010 Door #REF! sq.m 426.72 20,475.28 - 47.98
1010 (a) Door Frames & Accessories #REF! SETS 214.00 13,538.40
1027 Cement Plaster Finish #REF! sq.m 14,957.06 3,124,103.55
1003 Carpentry & Joinery Works #REF! sq.m 63.00 -
403 (a) Steel Trusses #REF! kgs #REF! #REF!
1013 Roofing Works #REF! sq.m 240.36 215,378.75
1100 Conduit Boxes & Fittings #REF! L.M. 144.00 15,889.25
1101 Wires & Wiring Devices #REF! L.M. 640.00 73,325.40
1102a Lighting Fixtures #REF! SETS 21.00 52,200.78
1102 Panel Boards & Cabinets #REF! set 1.00 14,853.50 - 8.94
SPL1 Personal Protective Equipments (PP #REF! Mandays/proj. 480.00 - 14,853.50 -
SPL2 Safety Health Officer #REF! hrs./proj. #REF! #REF! #REF! #REF!
Spl. 1 Railings #REF! SQ.M. #REF! - - #REF!
#REF! P #REF!

file:///conversion/tmp/activity_task_scratch/621623912.xls
BREAKDOWN OF ESTIMATE EXPENDITURE TOTAL AMOUNT
(%) (PESOS)
ESTIMATE COST:

a) DIRECT COST -

1. Mobilization / Demobilization
2. Materials #REF! -
2.1 Supply/ Delivery
2.2 Testing of Materials
3. Labor ( Including fringe benefit) #REF! -
4. Equipment Expenses #REF! -
5. Well Development

b) INDIRECT COST #REF!

1. Overhead Contingency, Miscellaneous #REF! 55,952.55


7% to 12% of A1 to A4
2. Profit 5% to 10% of A1 to A4 #REF! 46,627.12
3. Comprehensive All Risk Insurance 1.5% to A1 to A4
4. VAT 10% of A3 to A4 #REF! #REF!
5. Preparation of Plans and Detailed Estimates
6. Local Tax
7. Budgetary Reserve
8. Preliminary Engineering
SUB- TOTAL CONTRACT COST #REF! #REF!

ESTIMATED GOVERNMENT EXPENDITURES


1. Engineering and Administrative Overhead 3% of A1 to A4 #REF! -
2. ROW/ Site Acquisition
3. Soil Eploration
4. Parcellary Survey
5. Project Supervision
6. Regional/ Central Office Retension

CONTINGENCIES/ RESERVES

1. Physical up to 5% of the estimate Contract Cost


2. Price Escalation up to 12% of the Estimate Contract Cost

#REF! #REF!

Prepared by: Submitted by:

ELDRED M. MISLANG BLESILDA P. ESTRADA


OIC-Asst Chief, Planning & Design Section OIC-Chief, Planning & Design Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


Assistant District Engineer OIC-District Engineer
CERTIFICATION

This is to certify that the Preliminary Engineering has been conducted for the
Construction of 1-Storey 2CL.RM. School Building at Olea NHS , located at Olea,
Malasiqui, Pangasinan.

This certification was initiated to conform with the implementing rules and
regulations of R.A. 9184.

Conducted by: Checked By:

GILBERT G. PAGLINGAYEN BLESILDA P. ESTRADA


Special Investigator I OIC-Chief, Planning & Design Section

Noted:

MARIETA B. MENDOZA
OIC- District Engineer
UNIT PRICED ANALYSIS
Item No. 803(a)
Structure Excavation (common earth) QUANTITY 26.15 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0.7500 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 6.00 34.860 36.75 7,686.63


6.00 4.36 26.15

Sub- Total 7,686.63


unit cost 293.97
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 293.97
PREPARED BY: 12% of total DC OCM 35.28
10% of total DC CP 29.40
5% of (total DC+OCM+CP) VAT 17.93
Total Direct & Indirect Unit Cost 376.57
Total Direct & Indirect Cost 9,846.57
DETAILED ESTIMATES
Item No. 803(b)
Structure Excavation (sand) QUANTITY 100.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.2926 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 2.00 77.36 36.75 5,685.96


2.00 #REF! #REF!

Sub- Total 5,685.96


unit cost 56.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
DETAILED ESTIMATES
Item No. 803(c)
Structure Excavation (clay) QUANTITY 100.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 2.5940 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 5.00 38.55 36.75 7,083.56


5.00 #REF! #REF!

Sub- Total 7,083.56


unit cost 70.84
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
DETAILED ESTIMATES
Item No. 803(d)
Structure Excavation (rock) QUANTITY 1.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0.3225 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 1.00 3.10 36.75 113.93


1.00 #REF! #REF!

Sub- Total 113.93


unit cost 113.93
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
UNIT PRICED ANALYSIS
Item No. 804 (a)
Backfilling of excavated materials QUANTITY 12.10 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 3.1125 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 3.00 3.89 36.75 428.87


3.00 0.49 1.46

Sub- Total 428.87


unit cost 35.46
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 35.46
PREPARED BY: 12% of total DC OCM 4.25
10% of total DC CP 3.55
5% of (total DC+OCM+CP) VAT 2.16
Total Direct & Indirect Unit Cost 45.42
Total Direct & Indirect Cost 549.39
UNIT PRICED ANALYSIS
Item No. 804 (b)
Embankment (Backfilling & Tampering) QUANTITY 59.02 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 5.3289 cu.m / hour

River mix (plus 10% loose volume) 65.00 cu.m 300.00 19,500.00
MATERIAL COST

Sub- Total 19,500.00


unit cost 330.40
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 3.00 11.08 36.75 1,221.57


3.00 1.39 4.16

Sub- Total 1,221.57


unit cost 20.70
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Plate compactor 1.00 11.08 76.00 842.08

Sub- Total 842.08


unit cost 14.27
Direct Unit Cost 365.37
PREPARED BY: 12% of total DC OCM 43.84
10% of total DC CP 36.54
5% of (total DC+OCM+CP) VAT 22.29
Total Direct & Indirect Unit Cost 468.03
Total Direct & Indirect Cost 27,623.04
DETAILED ESTIMATES
Item No. 804 (d-1)
Gravel Fill (hand placed) QUANTITY 100.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.0200 cu.m / hour

Gravel Fill 100.00 cu.m 300.00 30,000.00


MATERIAL COST

Sub- Total 30,000.00


unit cost 300.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 6.00 98.04 36.75 21,617.82


6.00 #REF! #REF!

Sub- Total 21,617.82


unit cost 216.18
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Plate compactor 1.00 24.51 76.00 1,862.76

Sub- Total 1,862.76


unit cost 18.63
Direct Unit Cost 534.81
PREPARED BY: 12% of total DC OCM 64.18
10% of total DC CP 53.48
12% of (total DC+OCM+CP) VAT 78.30
Total Direct & Indirect Unit Cost 730.76
Total Direct & Indirect Cost 73,075.86
UNIT PRICED ANALYSIS
Item No. 1000 (a)
Soil Poisoning QUANTITY 191.25 SQ.M
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 2.7000 sq.m. / hour

Termite x 6.00 liters 950.00 5,700.00


MATERIAL COST

Sub- Total 5,700.00


unit cost 29.80
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 2.00 70.830 36.75 5,206.01


2.00 8.85 17.71

Sub- Total 5,206.01


unit cost 27.22
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 57.02
PREPARED BY: 12% of total DC OCM 6.84
10% of total DC CP 5.70
5% of (total DC+OCM+CP) VAT 3.48
Total Direct & Indirect Unit Cost 73.05
Total Direct & Indirect Cost 13,970.59
UNIT PRICED ANALYSIS
Item No. 404 (a.1)
Reinforcing Steel for Column Footing & WF QUANTITY 2,103.41 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 25.5000 kgs / hour
placing = 35.9025 kgs / hour
MATERIAL COST

Assorted RSB 2,103.41 kgs 35.00 73,619.21


#16 Tie Wire 31.60 kgs 57.00 1,801.20

Sub- Total 75,420.41


unit cost 35.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 3.00 100.06 47.62 14,294.57


2.00 12.51 25.02

Sub- Total 14,294.57


unit cost 6.80
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 82.49 43.75 3,608.94

Sub- Total 3,608.94


unit cost 1.72
Direct Unit Cost 44.37
PREPARED BY: 12% of total DC OCM 5.32
10% of total DC CP 4.44
5% of (total DC+OCM+CP) VAT 2.71
Total Direct & Indirect Unit Cost 56.84
Total Direct & Indirect Cost 119,547.94
UNIT PRICED ANALYSIS
Item No. 900 (a.1)
Reinforce Concrete Column Footing & FTB QUANTITY 15.85 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 2.8578 cu.m / hour
placing = 2.0750 cu.m / hour

Portland cement 142.70 bags 225.00 32,107.50


MATERIAL COST

Washed sand 8.00 cu.m 500.00 4,000.00


Crushed gravel 15.90 cu.m 600.00 9,540.00

Sub- Total 45,647.50


unit cost 2,879.25
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 5.55 65.55 363.80


LABOR COST

Skilled Laborer 2.00 5.55 47.62 528.58


Unskilled Laborer 3.00 5.55 36.75 611.89
6.00 0.69 4.16

Sub- Total 1,504.27


unit cost 94.88
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 5.55 173.00 960.15

Sub- Total 960.15


unit cost 60.56
Direct Unit Cost 3,034.70
PREPARED BY: 12% of total DC OCM 364.16
10% of total DC CP 303.47
5% of (total DC+OCM+CP) VAT 185.12
Total Direct & Indirect Unit Cost 3,887.45
Total Direct & Indirect Cost 61,631.37
UNIT PRICED ANALYSIS
Item No. 404 (a.2)
Reinforcing Steel for Column QUANTITY 1,829.42 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 25.5000 kgs / hour
placing = 31.8750 kgs / hour
MATERIAL COST

Assorted RSB 1,829.42 kgs 35.00 64,029.63


#16 Tie Wire 27.40 kgs 57.00 1,561.80

Sub- Total 65,591.43


unit cost 35.85
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 3.00 88.96 47.62 12,708.83


2.00 11.12 22.24

Sub- Total 12,708.83


unit cost 6.95
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 71.74 43.75 3,138.63

Sub- Total 3,138.63


unit cost 1.72
Direct Unit Cost 44.52
PREPARED BY: 12% of total DC OCM 5.34
10% of total DC CP 4.45
5% of (total DC+OCM+CP) VAT 2.72
Total Direct & Indirect Unit Cost 57.03
Total Direct & Indirect Cost 104,323.20
UNIT PRICED ANALYSIS
Item No. 900 (a.2)
Reinforce Concrete for Column QUANTITY 6.98 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 2.3815 cu.m / hour
placing = 0.8925 cu.m / hour
Area = 126.5200 sq.m
formwork installation = 2.8600 sq.m / hour
stripping = 7.9600 sq.m / hour
MATERIAL COST

Portland cement 62.80 bags 225.00 14,130.00


Washed sand 3.50 cu.m 500.00 1,750.00
Crushed gravel 7.00 cu.m 600.00 4,200.00
Coco lumber 523.70 bd.ft 20.00 10,474.00
Assosted CWN 10.50 kgs 70.00 735.00
Plywood 4' x 8' x 1/4" 23.30 pcs 315.00 7,339.50

Sub- Total 38,628.50


unit cost 5,532.19
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 52.18 65.55 3,420.40


LABOR COST

Skilled Laborer 2.00 52.18 47.62 4,969.62


Unskilled Laborer 5.00 52.18 36.75 9,588.08
8.00 6.52 52.18

Sub- Total 17,978.10


unit cost 2,574.74
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 2.93 173.00 506.89

Sub- Total 506.89


unit cost 72.59
Direct Unit Cost 8,179.52
PREPARED BY: 12% of total DC OCM 981.54
10% of total DC CP 817.95
5% of (total DC+OCM+CP) VAT 498.95
Total Direct & Indirect Unit Cost 10,477.96
Total Direct & Indirect Cost 73,162.38
UNIT PRICED ANALYSIS
Item No. 404 (a.3)
Reinforcing Steel for Beam QUANTITY 1,894.92 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 25.5000 kgs / hour
placing = 31.8750 kgs / hour
MATERIAL COST

Assorted RSB 1,894.92 kgs 35.00 66,322.06


#16 Tie Wire 28.40 kgs 57.00 1,618.80

Sub- Total 67,940.86


unit cost 35.85
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 3.00 92.14 47.62 13,163.12


2.00 11.52 23.04

Sub- Total 13,163.12


unit cost 6.95
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 74.31 43.75 3,251.06

Sub- Total 3,251.06


unit cost 1.72
Direct Unit Cost 44.52
PREPARED BY: 12% of total DC OCM 5.34
10% of total DC CP 4.45
5% of (total DC+OCM+CP) VAT 2.72
Total Direct & Indirect Unit Cost 57.03
Total Direct & Indirect Cost 108,058.80
UNIT PRICED ANALYSIS
Item No. 900 (a.3)
Reinforce Concrete for Beam QUANTITY 6.79 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 2.8578 cu.m / hour
placing = 1.0200 cu.m / hour
Area = 77.8000 sq.m
formwork installation = 2.4525 sq.m / hour
stripping = 7.4250 sq.m / hour
MATERIAL COST

Portland cement 61.10 bags 225.00 13,747.50


Washed sand 3.40 cu.m 500.00 1,700.00
Crushed gravel 6.80 cu.m 600.00 4,080.00
Coco lumber 509.20 bd.ft 20.00 10,184.00
Assosted CWN 10.20 kgs 70.00 714.00
Plywood 4' x 8' x 1/4" 22.60 pcs 315.00 7,119.00

Sub- Total 37,544.50


unit cost 5,530.40
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Leadman 1.00 36.96 65.55 2,422.73


LABOR COST

Skilled Laborer 2.00 36.96 47.62 3,520.07


Unskilled Laborer 6.00 36.96 36.75 8,149.68
9.00 4.62 41.58

Sub- Total 14,092.48


unit cost 2,075.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 2.38 173.00 411.74

Sub- Total 411.74


unit cost 60.65
Direct Unit Cost 7,666.91
PREPARED BY: 12% of total DC OCM 920.03
10% of total DC CP 766.69
5% of (total DC+OCM+CP) VAT 467.68
Total Direct & Indirect Unit Cost 9,821.31
Total Direct & Indirect Cost 66,674.41
UNIT PRICED ANALYSIS
Item No. 404 (a.4)
Reinforcing Steel for Slab on fill QUANTITY 2,644.35 klgs.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 42.5000 kgs / hour
placing = 53.1250 kgs / hour
MATERIAL COST

Assorted RSB 2,644.35 kgs 35.00 92,552.32


#16 Tie Wire 39.70 kgs 57.00 2,262.90

Sub- Total 94,815.22


unit cost 35.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 5.00 77.15 47.62 18,369.42


2.00 9.64 19.29

Sub- Total 18,369.42


unit cost 6.95
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 62.22 43.75 2,722.13

Sub- Total 2,722.13


unit cost 1.03
Direct Unit Cost 43.83
PREPARED BY: 12% of total DC OCM 5.26
10% of total DC CP 4.38
5% of (total DC+OCM+CP) VAT 2.67
Total Direct & Indirect Unit Cost 56.15
Total Direct & Indirect Cost 148,476.57
UNIT PRICED ANALYSIS
Item No. 900 (a.4)
Reinforce Concrete for Suspended Slab QUANTITY 2.60 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 0.9526 cu.m / hour
placing = 0.5100 cu.m / hour
Area = 29.8000 sq.m
formwork installation = 1.3625 sq.m / hour
stripping = 4.1250 sq.m / hour
Area = - sq.m
formwork installation = - sq.m / hour
MATERIAL COST

stripping = - sq.m / hour

Portland cement 24.70 bags 225.00 5,557.50


Washed sand 1.30 cu.m 500.00 650.00
Crushed gravel 2.60 cu.m 600.00 1,560.00
Coco lumber 195.00 bd.ft 28.00 5,460.00
Assosted CWN 3.90 kgs 70.00 273.00
Plywood 4' x 8' x 1/4" 8.70 pcs 315.00 2,740.50

Sub- Total 16,241.00


unit cost 6,246.54
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 25.48 65.55 1,670.21


LABOR COST

Skilled Laborer 2.00 25.48 47.62 2,426.72


Unskilled Laborer 2.00 25.48 36.75 1,872.78
5.00 76.44 382.20

Sub- Total 1,872.78


unit cost 720.30
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 2.73 173.00 472.29

Sub- Total 472.29


unit cost 181.65
Direct Unit Cost 7,148.49
PREPARED BY: 12% of total DC OCM 857.82
10% of total DC CP 714.85
12% of (total DC+OCM+CP) VAT 1,046.54
Total Direct & Indirect Unit Cost 9,767.69
Total Direct & Indirect Cost 25,396.01
UNIT PRICED ANALYSIS
Item No. 900e
Reinforce Concrete Slab on Fill QUANTITY 803.65 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 3.3341 cu.m / hour
placing = 1.1475 cu.m / hour
Area = ### sq.m
formwork installation = 2.7250 sq.m / hour
stripping = 8.2500 sq.m / hour
Area = - sq.m
formwork installation = sq.m / hour
MATERIAL COST

stripping = sq.m / hour

Portland cement 125.00 bags 225.00 28,125.00


Washed sand 401.80 cu.m 500.00 200,900.00
Crushed gravel 803.70 cu.m 600.00 482,220.00
-
-
-

Sub- Total 711,245.00


unit cost 885.02
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Leadman 1.00 3937.93 65.55 258,131.31


Mason 2.00 3937.93 47.62 375,048.45
Laborer 7.00 3937.93 36.75 1,013,032.49
10.00 492.24 4,922.41

Sub- Total 1,646,212.26


unit cost 2,048.42
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 241.04 173.00 41,699.92

Sub- Total 41,699.92


unit cost 51.89
Direct Unit Cost 2,985.33
PREPARED BY: 12% of total DC OCM 358.24
10% of total DC CP 298.53
5% of (total DC+OCM+CP) VAT 182.10
Total Direct & Indirect Unit Cost 3,824.20
Total Direct & Indirect Cost 3,073,320.34
UNIT PRICED ANALYSIS
Item No. 404e
Reinforcing Steel for Slab on Fill QUANTITY 528.16 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 25.5000 kgs / hour
placing = 31.8750 kgs / hour
MATERIAL COST

Assorted RSB 555.00 kgs 55.00 30,525.00


#16 Tie Wire 7.90 kgs 57.00 450.30

Sub- Total 30,975.30


unit cost 58.65
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 3.00 25.68 47.62 3,668.64


2.00 25.68 51.36

Sub- Total 3,668.64


unit cost 6.95
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 20.71 43.75 906.06

Sub- Total 906.06


unit cost 1.72
Direct Unit Cost
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
UNIT PRICED ANALYSIS
Item No. 506(1)
Masonry Works (CHB) QUANTITY 7,418.65 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: CHB Laying = 1.5939 sq.m / hour
MATERIAL COST

CHB 6" x 8" x 16" 93,104.06 pcs 12.00 1,117,248.69


Portland Cement 7,552.00 bags 225.00 1,699,200.00
Washed Sand 626.10 cu.m 500.00 313,050.00
RSB 10mm dia. 19,950.30 kgs 35.00 698,260.50
#16 G.I. Tie Wire 299.30 kgs 57.00 17,060.10
-
-

Sub- Total 3,844,819.29


unit cost 518.26
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (mason) 3.00 52.43 47.62 7,490.15


LABOR COST

Unskilled Laborer 3.00 52.43 36.75 5,780.41


2.00 6.55 13.11

Sub- Total 13,270.56


unit cost 1.79
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 520.05
PREPARED BY: 12% of total DC OCM 62.41
10% of total DC CP 52.01
5% of (total DC+OCM+CP) VAT 31.72
Total Direct & Indirect Unit Cost 666.19
Total Direct & Indirect Cost 4,942,213.09
UNIT PRICED ANALYSIS
Item No. 1010
Door QUANTITY 426.72 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0.4652 sq.m / hour

(D-1) Tanguile Panel Door on wood.Jamb 2.00 sets 5,000.00 10,000.00


(0 .90 x 2.10m.)
MATERIAL COST

(D-2) Flush Hollow Core Door (Lever Type


Dr. Knob)(0.90 x 2.10m.)on wood jamb 1.00 sets 4,000.00 4,000.00

1/4" thk.Clear Glass Transom 2.00 sets 550.00 1,100.00

Sub- Total 15,100.00


unit cost 35.39
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer 2.00 9.28 47.62 883.83


2.00 1.16 2.32

Sub- Total 883.83


unit cost 2.07
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 37.46
PREPARED BY: 12% of total DC OCM 4.49
10% of total DC CP 3.75
5% of (total DC+OCM+CP) VAT 2.28
Total Direct & Indirect Unit Cost 47.98
Total Direct & Indirect Cost 20,475.28
DETAILED UNIT PRICE ANALYSIS
Item No. 1018
Ceramic Tiles QUANTITY 15.80 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Laying glazed tiles = 1.1200 sq.m / hour
Laying unglazed tiles = 0.7800 sq.m / hour
MATERIAL COST

Ceramic Glazed Tiles 12.74 sq.m 550.00 7,007.00


Ceramic Unglazed Tiles 3.06 sq.m 850.00 2,601.00
Portland Cement 2.00 bag 225.00 450.00
Tile adhesive 2.00 bag 250.00 500.00

Sub- Total 10,558.00


unit cost 668.23
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
Output rate:
Construction foreman 1.00 15.30 65.55 1,002.92
Skilled Laborer (mason) 4.00 15.30 47.62 2,914.34
LABOR COST

Unskilled Laborer 4.00 15.30 36.75 2,249.10


8.00 1.91 15.30

Sub- Total 6,166.36


unit cost 390.28
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Tile Cutter 2.00 15.30 10.63 325.28

Sub- Total 325.28


unit cost 20.59
Direct Unit Cost 1,079.09
PREPARED BY: 12% of total DC OCM 129.49
10% of total DC CP 107.91
5% of (total DC+OCM+CP) VAT 65.82
Total Direct & Indirect Unit Cost 1,382.32
Total Direct & Indirect Cost 21,840.58
DETAILED UNIT PRICE ANALYSIS
Item No. 1002
Plumbing Works QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: installation = 12.5250 L.M / hour

PVC pipe 3" dia. 120.00 pcs. 434.00 52,080.00


PVC pipe 3" dia. Elbow 1/4bend 70.00 pcs. 38.00 2,660.00
Water Closet 1.6 gpf with accessories 71.00 pcs. 5,500.00 390,500.00
Lavatory w/ accessories 35.00 pcs. 2,500.00 87,500.00
Urinal 48.00 pc. 2,500.00 120,000.00
MATERIAL COST

faucet 1/2" dia. 126.00 pcs. 136.00 17,136.00


PVC pipe 4" dia. 100.00 pc. 560.00 56,000.00
PVC Pipe 4 x 3 wye 45.00 pc. 95.00 4,275.00
PVC Pipe 4 x 4 wye 45.00 pc. 113.00 5,085.00
PVC Pipe 4 x 4 tee 80.00 pc. 200.00 16,000.00
PVC pipe 4" dia. Elbow 1/4" bend 125.00 pcs. 71.00 8,875.00
Solvent 25.00 can 150.00 3,750.00
Floor drain 4" x 4" H.D. 78.00 pc. 98.00 7,644.00
G I pipe 1/2" dia 100.00 pcs. 365.00 36,500.00
G I coupling 1/2" dia. 126.00 pcs. 8.00 1,008.00
G I elbow 1/2" dia. 126.00 pcs. 10.00 1,260.00
G I tee 1/2" dia 120.00 pcs. 15.00 1,800.00
G I adapter 1/2" dia 50.00 pcs. 15.00 750.00
Sub- Total 812,823.00
unit cost 812,823.00
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
Assumed Output/day installation = 12.53
LABOR COST

Skilled Laborer (Plumber) 2.00 320.00 47.62 30,479.20


Unskilled Laborer 4.00 320.00 36.75 47,033.60
6.00 40.00

Sub- Total 77,512.80


unit cost 77,512.80
DESCRIPTION NO DAYS RATE(Pesos)TOTAL(Pesos)
Assumed Output/day installation = 12.53
EQUIPMENT COST

Sub- Total -
unit cost -
Direct Unit Cost 890,335.80
10% of total DC CP 89,033.58
Total Direct & Indirect Unit Cost 979,369.38
Total Direct & Indirect Cost 979,369.38
UNIT PRICED ANALYSIS
Item No. 1006
Steel Window QUANTITY 816.48 SQ.M
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.0125 sq.m. / hour

(W1).Awning type Steel Casement Window 7.68 sq.m. 1,850.00 14,208.00


w/ glass
Area=(2.40 x 1.60)2 = 7.68 sq.m.
(W2).Awning type Steel Casement Window 5.76 sq.m. 1,850.00 10,656.00
w/ glass
MATERIAL COST

Area=(2.40 x 1.20)2 = 5.76 sq.m.


(W3).Awning type Steel Casement Window 1.92 sq.m. 1,850.00 3,552.00
w/ glass
Area=(1.20 x 0.80)2 = 0.96 sq.m.
(W4).Awning type Steel Casement Window 0.72 sq.m. 1,850.00 1,332.00
w/ glass
Area=(1.80 x 0.40)1 = 0.72 sq.m.
(W5).Awning type Steel Casement Window 0.24 sq.m. 1,850.00 444.00
w/ glass
Area=(0.60 x 0.40)1 = 0.24 sq.m. -

Sub- Total 30,192.00


unit cost 36.98
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 3.00 806.40 36.75 88,905.60


3.00 100.80 302.40

Sub- Total 88,905.60


unit cost 108.89
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
EQUIPMENT COST

Sub- Total -
unit cost -
Direct Unit Cost 145.87
PREPARED BY: 12% of total DC OCM 17.50
10% of total DC CP 14.59
5% of (total DC+OCM+CP) VAT 8.90
Total Direct & Indirect Unit Cost 186.86
Total Direct & Indirect Cost 152,564.03
UNIT PRICED ANALYSIS
Item No. 1010 (a)
Door Frames & Accessories QUANTITY 214.00 SETS
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 6.6682 set / hour

2" X 6" Door Jamb (Tanguile)Fabricated D1


= 2 set 2.00 set 1,300.00 2,600.00
2" X 6" Door Jamb (Tanguile)Fabricated D2
MATERIAL COST

= 1 set 1.00 set 1,300.00 1,300.00


Locksets (Lever arm type) 3.00 set 450.00 1,350.00
3 1/2" x 3 1/2" Hinges 12.00 pcs. 30.00 360.00
2" x 6" Transom (Tanguile) Fabricated 2.00 set 1,300.00 2,600.00
-

Sub- Total 8,210.00


unit cost 38.36
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Carpenter 2.00 32.09 36.75 2,358.62


2.00 4.01 8.02

Sub- Total 2,358.62


unit cost 11.02
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None

Sub- Total -
unit cost -
Direct Unit Cost 49.39
PREPARED BY: 12% of total DC OCM 5.93
10% of total DC CP 4.94
5% of (total DC+OCM+CP) VAT 3.01
Total Direct & Indirect Unit Cost 63.26
Total Direct & Indirect Cost 13,538.40
UNIT PRICED ANALYSIS
Item No. 1027
Cement Plaster Finish QUANTITY 14,957.06 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: CHB Plastering= 2.3750 sq.m / hour
MATERIAL COST

Portland Cement 5,385.00 bags 225.00 1,211,625.00


Washed Sand 329.00 cu.m 500.00 164,500.00
Decorative Mouldings (0.45m. X1.83m.) 13.18 sq.m. 400.00

Sub- Total 1,376,125.00


unit cost 92.01
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (mason) 2.00 6297.71 47.62 599,793.90


LABOR COST

Unskilled Laborer 2.00 6297.71 36.75 462,881.69


4.00 787.21 3,148.86

Sub- Total 1,062,675.59


unit cost 71.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 163.05
PREPARED BY: 12% of total DC OCM 19.57
10% of total DC CP 16.31
5% of (total DC+OCM+CP) VAT 9.95
Total Direct & Indirect Unit Cost 208.87
Total Direct & Indirect Cost 3,124,103.55
UNIT PRICED ANALYSIS
Item No. 1003
Carpentry & Joinery Works QUANTITY 63.00 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Frame Works = 2.5500 sq.m / hour
Plywood Installation = 3.4000 sq.m / hour
MATERIAL COST

1/4" X 4"X 8",Ordinary Plywood 23.00 pcs 315.00 7,245.00


Ceiling Joists, Hangers & Nailers 315.00 bd.ft 75.00 23,625.00
Insect Screen 5.00 sq.m. 150.00 750.00
Assorted CWN 6.60 kgs 70.00 462.00

Sub- Total
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)

Output rate:
Skilled Laborer (carpenter) 4.00 30.26 47.62 5,763.92
LABOR COST

Unkilled Laborer 2.00 30.26 36.75 2,224.11


2.00 30.26 60.52

Sub- Total
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost -
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
UNIT PRICED ANALYSIS
Item No. 403 (a)
Steel Trusses QUANTITY #REF! kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 85.0000 kgs / hour
erection/Installation = 0.2000 kgs / hour
painting = 12.7500 L.M/ hour

95 LC 150 x 65 x 20 x 2.0mm x 6.00m Purlins 2,713.20 kgs 52.00 141,086.40


16 65 x 65 x 6mm x 6.00m. Top chord AB 556.80 kgs 52.00 28,953.60
12 65 x 65 x 6mm x 6.00m. Bott.Chord AB 417.60 kgs 52.00 21,715.20
32 50 x 50 x 6mm x 6.00m. Web Members AB 864.00 kgs 52.00 44,928.00
9 75 x 75 x 6.0mm x 130mm Long Clip AB 367.20 kgs 52.00 19,094.40
12 100 x 100 x 6.0mm x 6.00m. Angular Base Plate 662.40 kgs 52.00 34,444.80
12 255 x 90 x 25 x 3mm LC Channel (Steel Fascia) 708.48 kgs 52.00 36,840.96
MATERIAL COST

4 1 1/2" x 1 1/2" x 3/16" Angle Bar 57.60 kgs. 52.00 2,995.20


Base plates 250mm x 300mm x 12.00mm 13.00 pcs. 300.00 3,900.00
12mm dia x 0.85m sagrod w/ nuts & washers 250.00 pcs 80.00 20,000.00
12mm dia x 150mm anchor bolts 48.00 pcs 30.00 1,440.00
16mm dia x 300mm long bent anchor bolts 36.00 pcs 120.00 4,320.00
Std. Turn Buckel 16mm dia. 20.00 pcs 185.00 3,700.00
6mm dia machine bolts 48.00 pcs 10.00 480.00
Welding rod 20.00 kgs. 120.00 2,400.00
Oxygen (content only) 3.00 kgs 45.00 135.00
Acetylene (content only) 3.00 kgs 65.00 195.00
Red lead primer 3.00 gal 430.00 1,290.00
Paint thinner 2.00 gal 200.00 400.00
Paint brush 2.00 pcs 80.00 160.00
Misc. plate connector , Angular seat .6mm & 10mm
Gusset plate etc.. All L.S. 4,000.00 4,000.00
-

Sub- Total 372,478.56


unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (welder) 2.00 105.00 47.62 10,000.20


LABOR COST

Unskilled Laborer 3.00 105.00 36.75 11,576.25


5.00 13.13 65.63

Sub- Total 21,576.45


unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Welding machine 2.00 105.00 62.50 13,125.00


Scaffolding All L.S. 6,000.00 6,000.00

Sub- Total 19,125.00


unit cost #REF!
Direct Unit Cost #REF!
PREPARED BY: 12% of total DC OCM #REF!
10% of total DC CP #REF!
5% of (total DC+OCM+CP) VAT #REF!
Total Direct & Indirect Unit Cost #REF!
Total Direct & Indirect Cost #REF!
UNIT PRICED ANALYSIS
Item No. 1003
Carpentry & Joinery Works QUANTITY 226.65 SQ.M.
DESCRIPTION QUANTITY UNIT U- PRICE(P)TOTAL(Pesos)
Output rate: Frame Works = 3.1875 sq.m / hour
Plywood Installation = 4.2500 sq.m / hour

3/16" X 4"X 8",Fiber Cement Plywood 82.60 pcs 315.00 26,019.00


1/4" X 4"X 8",Marine Plywood for blackboard 2.00 pcs. 380.00 760.00
2" x 2" Nailers,painting,conc.nail, etc. for
blackboard 150.00 bd.ft 75.00 11,250.00
Double Furring (19x50x.40mmx 5.0m.) 105.00 pcs. 102.00 10,710.00
Wall Angle (25x25x0.40mm x 2.44m.) 75.00 pcs. 42.00 3,150.00
MATERIAL COST

Carrying Channel (12x38x0.80mmx5.0m.) 55.00 pcs. 115.00 6,325.00


W-Clip 362.64 pcs. 4.00 1,450.56
Blind Rivets (1/8x3/8) 761.54 pcs. 1.00 761.54
Insect Screen 10.00 sq.m. 150.00 1,500.00
Assorted CWN 30.00 kgs 70.00 2,100.00
Fab.Louver Vent(0.27x1.15m) 6.00 pcs. 800.00 4,800.00
120 x 150 x 70mm Chalkdust Bob 1 pc. 300.00 300.00
Misc. 50mm x 6mm thk.plywood, hanger rod
etc. All L.S. 3,000.00 3,000.00

Sub- Total 72,126.10


unit cost 318.23
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)

Output rate:
Skilled Laborer (carpenter) 5.00 87.10 47.62 20,738.51
LABOR COST

Unskilled Laborer 3.00 87.10 36.75 9,602.78


8.00 10.89 87.10

Sub- Total 30,341.29


unit cost 133.87
DESCRIPTION NO HOURS RATE(Pesos)TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 452.10
PREPARED BY: 12% of total DC OCM 54.25
10% of total DC CP 45.21
5% of (total DC+OCM+CP) VAT 27.58
Total Direct & Indirect Unit Cost 579.13
Total Direct & Indirect Cost 131,260.73
UNIT PRICED ANALYSIS
Item No. 1013
Roofing Works QUANTITY 240.36 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 34.0000 sq.m. / hour
erection/Installation = 0.2000 kgs / hour

Pre-painted Corr.G.I. Long Span (0.40mm) 240.36 sq.m. 350.00 84,126.98


Pre-painted ready made ridge roll (0.40mm) 24.20 l.m. 220.00 5,324.00
Pre-painted ready made Flashing (0.40mm) 22.00 l.m. 220.00 4,840.00
Pre-painted ready made gutter(0.40mm) 48.40 l.m. 220.00 10,648.00
MATERIAL COST

Rivets 200.00 box 2.00 400.00


J-Shape Bolt w Neoprene Gasket (Fabricated) 2,000.00 pcs. 20.00 40,000.00
Misc. sealant, etc. All L.S. 2,000.00 2,000.00
-
-
-
-
-
-
-
-

Sub- Total 147,338.98


unit cost 612.99
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (Tinsmithman) 2.00 32.48 47.62 3,093.40


LABOR COST

Unskilled Laborer 3.00 32.48 36.75 3,580.92


5.00 4.06 20.30

Sub- Total 6,674.32


unit cost 27.77
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Electric Drill 2.00 32.48 62.50 4,060.00


Riveter 2.00 32.48 62.50 4,060.00
Scaffoldings All L.S. 6,000.00 6,000.00

Sub- Total 14,120.00


unit cost 58.74
Direct Unit Cost 699.50
PREPARED BY: 12% of total DC OCM 83.94
10% of total DC CP 69.95
5% of (total DC+OCM+CP) VAT 42.67
Total Direct & Indirect Unit Cost 896.06
Total Direct & Indirect Cost 215,378.75
UNIT PRICED ANALYSIS
Item No. 1032a-2
Wooden Painting QUANTITY 476.78 SQ.M
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Production Rate 11.5252 sq.m. / hour
placing = sq.m. / hour
MATERIAL COST

Glazing Putty -
Flat Wall Enamel (Primer) 19.87 gals. 480.00 9,535.60
Enamel Quick Dry 19.87 gals. 500.00 9,932.92
Paint Thinner 3.00 gals. 240.00 720.00
Assorted Tintin Color (Enamel) 10.00 ltr. 150.00 1,500.00
Misc. wall putty, punching compound etc. All L.S. 4,000.00 4000.00

Sub- Total 25,688.52


unit cost 53.88
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Painter) 4.00 41.37 47.62 7,880.16


2.00 5.17 10.34

Sub- Total 7,880.16


unit cost 16.53
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Scaffolding All L.S. 6,000.00

Sub- Total 6,000.00


unit cost 12.58
Direct Unit Cost 82.99
PREPARED BY: 12% of total DC OCM 9.96
10% of total DC CP 8.30
5% of (total DC+OCM+CP) VAT 5.06
Total Direct & Indirect Unit Cost 106.31
Total Direct & Indirect Cost 50,687.47
UNIT PRICED ANALYSIS
Item No. 1032a-1
Masonry Painting QUANTITY 59,828.24 SQ.M
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 8.3652 SQ.M. / hour

Flat wall Latex (Boysen) 2,601.23 gals. 480.00 1,248,589.36


Latex Paint Gloss 2,601.23 gals. 480.00 1,248,589.36
MATERIAL COST

Paint Brush 4" 3.00 pcs. 85.00 255.00


Paint roller 12" 3.00 pc. 160.00 480.00
Assorted Acry Color (Latex) 8.00 ltr. 150.00 1,200.00
Calsumine powder 20.00 kg. 15.00 300.00
Concrete Neutralizer 1.00 gals. 220.00 220.00
Patching compound all L.S. 1,500.00 1,500.00
Wall GlazingPutty 1.00 gal. 604.02 604.02

Sub- Total 2,501,737.74


unit cost 41.82
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Painter) 4.00 47.62 47.62 9,070.66


2.00 5.95 11.91

Sub- Total 9,070.66


unit cost 0.15
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Scaffloding All L.S. 6,000.00

Sub- Total 6,000.00


unit cost 0.10
Direct Unit Cost 41.97
PREPARED BY: 12% of total DC OCM 5.04
10% of total DC CP 4.20
5% of (total DC+OCM+CP) VAT 2.56
Total Direct & Indirect Unit Cost 53.76
Total Direct & Indirect Cost 3,224,031.55
UNIT PRICED ANALYSIS
Item No. 1032-3
Roof Painting QUANTITY 528.16 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 25.5000 kgs / hour
placing = 31.8750 kgs / hour
MATERIAL COST

Assorted RSB 555.00 kgs 55.00 30,525.00


#16 Tie Wire 7.90 kgs 57.00 450.30

Sub- Total
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (steelman) 3.00 25.68 47.62 3,668.64


2.00 25.68 51.36

Sub- Total
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 20.71 43.75 906.06

Sub- Total
unit cost -
Direct Unit Cost -
PREPARED BY: 12% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
UNIT PRICED ANALYSIS
Item No. 1100
Conduit Boxes & Fittings QUANTITY 144.00 L.M.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 3.5000 lm./ hour ###

wt pe
PVC Pipe 12.50mm DIA. 3.0 meters 80.00 pcs. 69.00 5,520.00
RSC Pipe 25mm DIA. 3.0 mtrs. 3.00 pcs. 834.00 2,502.00
Locknuts and Bushing 12.50mm DIA. 30.00 pcs. 6.00 180.00
PVC - ELBOW - 12.50mm DIA. 30.00 pcs. 12.00 360.00
MATERIAL COST

Utility Box G.I. Type 30.00 pcs 30.00 900.00


Junction Box G.I. TYPE 25.00 pcs 30.00 750.00
Square Box Deep Type 2.00 pcs 37.00 74.00
Locknut and Bushing 25mm. DIA. 2.00 pcs 18.00 36.00
Service Entrance Cap 25 mm. DIA. 1.00 pcs 191.00 191.00
1 phase Spool Insulator and Secondary Rack w/ Bolt 1.00 pcs 780.00 780.00
Misc. conc. Nail. Clamp etc.. All L.S. 391.25 391.25
-
-
-
-
-

Sub- Total 11,684.25


unit cost 81.14
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Electrician) 1.00 15.11 47.62 719.54


1.89
2.00 15.11 30.22

Sub- Total 719.54


unit cost 5.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None

Sub- Total -
unit cost -
Direct Unit Cost 86.14
PREPARED BY: 12% of total DC OCM 10.34
10% of total DC CP 8.61
5% of (total DC+OCM+CP) VAT 5.25
Total Direct & Indirect Unit Cost 110.34
Total Direct & Indirect Cost 15,889.25
UNIT PRICED ANALYSIS
Item No. 1101
Wires & Wiring Devices QUANTITY 640.00 L.M.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 37.5000 lm. / hour

Electric Wire 3.5mm2 THHN 4.00 roll 3,600.00 14,400.00


Electric Wire 85.5mm2 THHN 2.00 roll 5,200.00 10,400.00
Electric Wire 8.0mm2 THHN 2.00 roll 6,750.00 13,500.00
MATERIAL COST

Duplex Convenience Outlet HEAVY DUTY 8.00 pcs. 500.00 4,000.00


Duplex Convenience Outlet 16.00 pcs. 245.00 3,920.00
(3) Gang Switch 2.00 pcs. 280.00 560.00
(2) Gang Switch 3.00 pcs. 235.00 705.00
(1) Gang Switch 1.00 pcs. 210.00 210.00
Electric Tape 14.00 pc. 30.00 420.00
Mica tube 2.00 roll 2,250.00 4,500.00
Miscellanous etc. 12mm dia.G.I.Pipe hanger All L.S. 3,000.00 3,000.00

Sub- Total 55,615.00


unit cost 86.90
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Electrician) 2.00 17.07 47.62 1,625.75


2.00 2.13 4.27

Sub- Total 1,625.75


unit cost 2.54
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None -

Sub- Total -
unit cost -
Direct Unit Cost 89.44
PREPARED BY: 12% of total DC OCM 10.73
10% of total DC CP 8.94
5% of (total DC+OCM+CP) VAT 5.46
Total Direct & Indirect Unit Cost 114.57
Total Direct & Indirect Cost 73,325.40
UNIT PRICED ANALYSIS
Item No. 1102a
Lighting Fixtures QUANTITY 21.00 SETS
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 1.0000 ckt. / hour

Wall Fan 4.00 sets 2,300.00 9,200.00


FLOURESCENT LIGHTING FIXTURE
(2X40WATTS) ALUMINUM LOUVER
RECESS 15.00 sets 1,450.00 21,750.00
MATERIAL COST

FLOURESCENT LIGHTING FIXTURE


(1X40WATTS) ALUMINUM LOUVER
RECESS 5.00 sets 1,120.00 5,600.00
COMPACT LED LAMP 1.00 sets 350.00 350.00
Equipment for Fire Alarm Bell / with accesso 1.00 sets 2,850.00 2,850.00

Sub- Total 39,750.00


unit cost 1,892.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Electrician) 1.00 21.00 47.62 1,000.02


2.00 2.63 5.25

Sub- Total 1,000.02


unit cost 47.62
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None -

Sub- Total -
unit cost -
Direct Unit Cost 1,940.48
PREPARED BY: 12% of total DC OCM 232.86
10% of total DC CP 194.05
5% of (total DC+OCM+CP) VAT 118.37
Total Direct & Indirect Unit Cost 2,485.75
Total Direct & Indirect Cost 52,200.78
UNIT PRICED ANALYSIS
Item No. 1102
Panel Boards & Cabinets QUANTITY 1.00 set
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 0.5000 set / hour

-
MATERIAL COST

-
Panelboard & Cabinets BOLT ON 15 HOLES
1.00 set 3,500.00 3,500.00
Circuit Breaker Bolt-on type 40 amp. 8.00 set 400.00 3,200.00
Circuit Breaker Bolt-on type 20 amp. 7.00 set 400.00 2,800.00
MAIN Circuit Breaker Plug In type 250 amp. 1.00 set 2,000.00 2,000.00

Sub- Total 11,500.00


unit cost 11,500.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Electrician) 1.00 2.00 47.62 95.24


2.00 0.25 0.50

Sub- Total 95.24


unit cost 95.24
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None

Sub- Total -
unit cost -
Direct Unit Cost 11,595.24
PREPARED BY: 12% of total DC OCM 1,391.43
10% of total DC CP 1,159.52
5% of (total DC+OCM+CP) VAT 707.31
Total Direct & Indirect Unit Cost 14,853.50
Total Direct & Indirect Cost 14,853.50
UNIT PRICED ANALYSIS
Item No. SPL1
Personal Protective Equipments (PPE) QUANTITY 480.00 Mandays/proj.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
MATERIAL COST

Safety Helmet 480.00 Man-Days 0.25 120.00


Safety Gloves 480.00 Man-Days 2.77 1,329.60
Safety Shoes 480.00 Man-Days 7.67 3,681.60

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

None
2.00 - -

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

None

Sub- Total -
unit cost -
Direct Unit Cost -
PREPARED BY: 0% of total DC OCM -
10% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
UNIT PRICED ANALYSIS
Item No. SPL2
Safety Health Officer QUANTITY #REF! hrs./proj.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
None
MATERIAL COST

Sub- Total -
unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
LABOR COST

Safety Hours (Part Time) 1.00 4.00 500.00 2,000.00


2.00 4.00 8.00

Sub- Total
unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

None

Sub- Total -
unit cost #REF!
Direct Unit Cost #REF!
PREPARED BY: 0% of total DC OCM #REF!
10% of total DC CP #REF!
12% of (total DC+OCM+CP) VAT #REF!
Total Direct & Indirect Unit Cost #REF!
Total Direct & Indirect Cost #REF!
DETAILED UNIT PRICE ANALYSIS
Item No. Spl. 1
Railings QUANTITY #REF! SQ.M.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: installation = 0.7500 L.M / hour
MATERIAL COST

Steel railings, 38mmØ GI Pipe 198.00 l.m. 175.00 34,650.00


handrail Dr.
Accordion #REF! sq.m. 3,850.00 #REF!
Misc. materials (welding rod, paint, etc.,) 1,317.62
### #REF!
Sub- Total #REF!
unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (Welder) 1.00 #REF! 47.62 #REF!


LABOR COST

Unkilled Laborer 1.00 #REF! 36.75 #REF!


2.00 #REF! #REF!

Sub- Total #REF!


unit cost #REF!
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Welding machine 1.00 #REF! 62.50 #REF!

Sub- Total #REF!


unit cost #REF!
Direct Unit Cost #REF!
PREPARED BY: 12% of total DC OCM #REF!
10% of total DC CP #REF!
5% of (total DC+OCM+CP) VAT #REF!
Total Direct & Indirect Unit Cost #REF!
Total Direct & Indirect Cost #REF!
DETAILED UNIT PRICE ANALYSIS
Item No. Spl.2
Occupational Safety & Health QUANTITY All LS
DESCRIPTION QUANTITY MAN-DAY U- PRICE(P) TOTAL(Pesos)
Safety Gears
MATERIAL COST

Safety Shoes #REF! Man-Day 2.77 #REF!


Safety Helmet #REF! Man-Day 0.25 #REF!
Safety Gloves #REF! Man-Day 7.67 #REF!

Sub- Total #REF!


DESCRIPTION NO UNIT RATE(Pesos) TOTAL(Pesos)
Part Time Safety Practitioner 10.00 Day 524.36 5,243.60
LABOR COST

Sub- Total 5,243.60


DESCRIPTION NO UNIT RATE TOTAL
EQUIPMENT COST

Warning Signs 1.00 LOT 2,000.00 2,000.00

2,000.00
Total Direct Cost #REF!
PREPARED BY: 0% of total DC OCM #REF!
10% of total DC CP #REF!
5% of (total DC+OCM+CP) VAT #REF!
Total Item Cost #REF!
Adjusted Unit Cost #REF!
DETAILED ESTIMATES
Item No. Spl 3
Project Billboard QUANTITY 1.00 each
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day
DPWH BILLBOARD
Tarpaulin 32.00 sq.m. 30.00 960.00
Ordinary Plywood 1/4 1.00 pcs. 315.00 315.00
Coco Lumber 2 x 3 x 12 12.00 bd.ft. 28.00 336.00
MATERIAL COST

Coco Lumber 2 x 2 x 12 16.00 bd.ft. 28.00 448.00


Assorted CWN 2.00 kgs. 70.00 140.00

COA BILLBOARD
Tarpaulin 64.00 sq.m. 30.00 1,920.00
Ordinary Plywood 1/4 2.00 pcs. 315.00 630.00
Coco Lumber 2 x 3 x 12 24.00 bd.ft. 28.00 672.00
Coco Lumber 2 x 2 x 12 32.00 bd.ft. 28.00 896.00
Assorted CWN 4.00 kgs. 70.00 280.00

Sub- Total 6,597.00


unit cost 6,597.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer 1.00 1.00 380.99 380.99


Unskilled Laborer 1.00 1.00 293.96 293.96
3.00 1.00 3.00

Sub- Total 1,199.31


unit cost 1,199.31
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day
EQUIPMENT COST

Sub- Total
unit cost -
Direct Unit Cost 7,796.31
PREPARED BY: 0% of total DC OCM -
10% of total DC CP 779.63
5% of (total DC+OCM+CP) VAT 428.80
Total Direct & Indirect Unit Cost 9,004.74
Total Direct & Indirect Cost 9,004.74
DETAILED ESTIMATES
Item No. 1100
Electrical Works QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day

Flourescent Lighting Fixtures (40 watts) wi 1.00 pcs. 600.00 600.00


Compact flourescent lamp 1.00 pcs. 130.00 130.00
Porcelain socket # 4"Ø 1.00 pcs. 40.00 40.00
Light Switch 1 way 3 gang pcs. 142.00 -
Light Switch 1 way 2 gang pcs. 142.00 -
Light Switch 1 way 1 gang 2.00 pcs. 142.00 284.00
Utility Box (Deep tape) 18.00 pcs. 30.00 540.00
MATERIAL COST

PVC Coupling PNS 14,1/2" dia. 15.00 pcs. 3.00 45.00


PVC Pipe PNS 14,1/2"dia. 30.00 pcs. 69.00 2,070.00
PVC Pipe PNS 14,1"dia. 1.00 pcs. 120.00 120.00
PVC Adapter PNS 14,1/2"dia. 1.00 pcs. 8.00 8.00
Entrance cap # 1/2"Ø 1.00 pcs, 62.00 62.00
Junction Box (Deep tape w/ Cover) 17.00 pcs. 31.00 527.00
Copper Wire #3.50mm2 TW 350.00 mtrs 24.00 8,400.00
Electrical Tape 3.00 pcs. 40.00 120.00
Utility Box (Deep tape) 20.00 pcs. 25.00 500.00
PVC Pipe Flexible 1/2"dia. 80.00 mtrs 15.00 1,200.00
Ligthing Panel Air circuit breaker 1.00 set 1,350.00 1,350.00
Miscellaneous materials 5,500.00

Sub- Total
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 5.00 524.36 2,621.80


LABOR COST

Skilled Laborer (Electrician) 1.00 5.00 380.99 1,904.95


Unskilled Laborer 1.00 5.00 293.96 1,469.80
3.00 5.00 15.00

Sub- Total
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -
EQUIPMENT COST

Minor tools (10% of Labor) -

Sub- Total -
unit cost -
Direct Unit Cost -
PREPARED BY: 12% of total DC OCM -
12% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
DETAILED ESTIMATES
Item No. Spl.5
Steel Gate & Perimeter Fences QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day

Steel Gate (2sets- 4.00m x 2.45m) 19.60 sq.m 2,500.00 49,000.00


Steel Gate (1set- 2.00m x 2.30m) 4.60 sq.m 2,500.00 11,500.00
MATERIAL COST

Steel junior Gate (1set-1.80m x 2.45m) 4.41 sq.m 2,500.00 11,025.00


Fences (10sets- 3.00m x 1.30m) 39.00 sq.m 2,500.00 97,500.00
Red Lead Primer 20.00 gal 430.00 8,600.00
Paint Thinner 5.00 gal 200.00 1,000.00
Paint Brush 10.00 pcs 80.00 800.00
Rush Converter/Remover 6.00 gal 450.00 2,700.00
Miscellaneous materials (sand paper, steel brush, welding rod,etc.,) 3,000.00

Sub- Total
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 524.36 -


LABOR COST

Skilled Laborer (Welder) 2.00 0.00 380.99 -


Unskilled Laborer 5.00 0.00 293.96 -
8.00 - -

Note:
Labor includes repair & installation of old fences.

Sub- Total -
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Welding machine 1.00 - 500.00 -


EQUIPMENT COST

Grinder (handy) 1.00 - 150.00 -


Electricity,Acetylane,oxygen & etc. All LS 7,193.04 7,193.04
Minor tools (10% of Labor) -

Sub- Total
unit cost -
Direct Unit Cost -
PREPARED BY: 12% of total DC OCM -
12% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0017
Contract Name : Completion of Multi-Purpose Building at Buenlag 1st & Manabong Sur, Bayambang, Pangasinan, Construction of 2-Cl at
Arenas NHS, Ambayat 2nd, Bayambang, Pangasinan, Construction of 1-Cl at Bogaoan E/S, San Carlos City and Completion
of Multi-Purpose Building (Gym) at Brgy. Coliling & Brgy. Quintong, San Carlos City, Pangasinan (CLUSTER I)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


C-Rafter 46mm x 148mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 75mm (1.00mm) ………………………… 460.00 / pcs.
C-Purlins 44mm x 100mm (1.00mm) ………………………… 510.00 / pcs.
C-Purlins 50mm x 150mm (1.40mm) ………………………… 1,075.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x 200mm ………………………… 150.00 / pcs.
Anchor Bolt, 16mmØ x 250mm ………………………… 170.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
20mm dia. X 50 Machine Bolts w/ nuts ………………………… 100.00 / pcs.
20mm dia. X 500 Straight Bolts w/ nuts ………………………… 250.00 / pcs.
16mm dia. X 200 Anchor Bolts w/ nuts ………………………… 120.00 / pcs.
10mm Thk. Steel Plate ………………………… 18,500.00 / pcs.
Gusset Plates 4 x 8 x 4mm ………………………… 12,550.00 / pcs.
Base Plate 150mm x 300mm x 4mm ………………………… 300.00 / pcs.
Base Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 250mm x 200mm x 4mm ………………………… 200.00 / pcs.
71.2 x 71.2 x 5.00mm Angle Bar ………………………… 2,425.00 / pcs.
46.8 x 46.8 x 5.00mm Angle Bar ………………………… 1,400.00 / pcs.
46.8 x 46.8 x 4.25mm Angle Bar ………………………… 980.00 / pcs.
46.8 x 46.8 x 3.50mm Angle Bar ………………………… 800.00 / pcs.
38.0 x 38.0 x 3.50mm Angle Bar ………………………… 685.00 / pcs.
20mm dia. Tension Rod (Strut 1) ………………………… 50.00 / kgs.
Plain 12mm dia w/ nuts & washer at both ends (Sag Rod) ………………………… 80.00 / pcs.
Plain 12mm dia (Cross bracing) ………………………… 50.00 / kgs.
Std. Turn Buckel 12mm dia. ………………………… 200.00 / pcs.
C-Rafter 46mmx150mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 100mm (1.0mm) ………………………… 510.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x .200mm ………………………… 150.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
Base / Sole Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 300mm x 150mm x 4mm ………………………… 300.00 / pcs.
Cleats 48.1 x 48.1 x 3.5mm Angular bar ………………………… 950.00 / pcs.
Sag Rod(10mm ø) Plain bar with Bolts & Washers ………………………… 80.00 / pcs.
Paint brush 4" ………………………… 90.00 / pcs.
Thinner ………………………… 250.00 / gal
Red Lead Primer ………………………… 550.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 65.00 / pcs.
150X150X4mm, Base Plate ………………………… 150.00 / pcs.
10mm dia.Sag rod w/n/b ………………………… 80.00 / pcs.
10mm dia,x0.70m.Dowels ………………………… 25.00 / pcs.
12mm dia. X 150mm long Anchor Bolt ………………………… 80.00 / pcs.

Ceramics Glazed Tiles & Trims ………………………… 750.00 / sq.m.


Ceramics Unglazed Tiles & Trims ………………………… 850.00 / sq.m.
Tile Grout ………………………… 70.00 / kls.

Paint brush 4" ………………………… 90.00 / pcs.


Paint brush 2" ………………………… 45.00 / pcs.
Paint Tinner ………………………… 240.00 / gal
Red Lead Primer ………………………… 580.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 75.00 / pcs.
Portland Cement, 40 kgs ………………………… 220.00 / bags
Washed Sand ………………………… 500.00 / cu. m.
Gravel Fill ………………………… 450.00 / cu. m.
River mix ………………………… 300.00 / cu.m.
Crushed Gravel ………………………… 600.00 / cu. m.
Plywood - 1/2 x 4' x 8' ………………………… 625.00 / pcs.
Plywood - 1/4 x 4' x 8' ………………………… 355.00 / pcs.
Good Lumber ………………………… 75.00 / bd.ft
Coco Lumber ………………………… 28.00 / bd.ft
Air ventillation ………………………… 450.00 / set
Assorted CWN ………………………… 70.00 / kgs
Asstd. RSB ………………………… 52.00 / kgs
Tie wire # 16 GI ………………………… 55.00 / kgs
CHB ( 4" x 8" x 16") ………………………… 10.00 / pcs
Security Steel Grills (10mm) ………………………… 1,200.00 / sq.m.
Sliding Analuk Windows ………………………… 3,000.00 / sq.m.
Jalousie window w/ Aluminum Frame ………………………… 850.00 / sq.m.
Swing type Steel Casement window with glass ………………………… 1,850.00 / sq.m.
Panel type door (2.10m X 0.90m) incl. Door jambs & …………………………
Hinges with screw. 5,000.00 / sets
5/8"Glass Door With Aluminum Frames ………………………… 6,500.00 / sq.m.
Flush hollow core door ………………………… 920.00 / sq.m.
PVC Door (2.10m x 0.80m) incl. Door jambs & Hinges with …………………………
screw. 2,850.00 / units
Improvised Door Lock (Hook-in flat bar 4mm Thk with …………………………
padlock and puller) 380.00 / pcs.
Door lock w/ screw ………………………… 450.00 / pcs.
Hinges ………………………… 35.00 / pcs.
Pre-painted Tri-wave (0.40mm) ………………………… 420.00 / sq.m.
Pre-painted ready made ridge roll (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Flashing S-Type (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made End Flashing (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Gutter (0.40mm) ………………………… 220.00 / L.M.
Tekscrew ………………………… 2.00 / pcs.
Blind rivets ………………………… 250.00 / box
Silicon Sealant ………………………… 180.00 / pcs.
Toilet Bowl ………………………… 1,000.00 / set
Water Closet ………………………… 6,750.00 / set
PVC pipe 4" dia. ………………………… 580.00 / pcs.
PVC pipe 2" dia. ………………………… 290.00 / pc.
PVC pipe 4 x 2 wye ………………………… 95.00 / pc.
PVC pipe 4 x 4 wye ………………………… 125.00 / pc.
PVC pipe 4 x 4 tee ………………………… 125.00 / pc.
PVC pipe 4 x 2 Tee ………………………… 80.00 / pc.
PVC pipe 2" dia. Elbow 1/4 bend ………………………… 25.00 / pc.
PVC pipe 2" dia. Elbow 1/8 bend ………………………… 20.00 / pc.
PVC pipe 4" dia. Elbow 1/4 bend ………………………… 80.00 / pc.
PVC pipe 4" dia. Elbow 1/8 bend ………………………… 55.00 / pc.
PVC pipe 2" dia. P-Trap ………………………… 105.00 / pc.
PVC pipe 4" dia. Cleanout w/ plug ………………………… 60.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. ………………………… 110.00 / pcs.
Solvent ………………………… 185.00 / can
Floor drain 4" x 4" H.D. ………………………… 290.00 / pc.
G I pipe 1/2" dia ………………………… 365.00 / pcs.
G I coupling 1/2" dia. ………………………… 8.00 / pcs.
G I elbow 1/2" dia. ………………………… 10.00 / pcs.
G I tee 1/2" dia ………………………… 22.00 / pcs.
G I adapter 1/2" dia ………………………… 15.00 / pcs.
Faucet 1/2" dia ………………………… 170.00 / pcs.
PVC pipe 3" dia. (downspout) ………………………… 430.00 / pcs.
PVC pipe 3" dia. Elbow 1/4 bend ………………………… 80.00 / pc.

Flourescent Lighting Fixtures (40 watts) with box type housing ………………………… 650.00 / sets
Lighting Fixture (CFL 20 A) 150.00 / sets
Bulb Receptacles 45.00 / pcs.
Light Switch 1 way 2 gang 140.00 / pc.
Light Switch 1 way 1 gang 140.00 / pc.
Copper Wire #3.50mm2 TW 26.00 / mtrs.
Electrical Tape 40.00 / roll
PVC Pipe Flexible 1/2"dia. 15.00 / mtrs.
PVC Coupling PNS 14,1/2" dia. 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. 70.00 / pcs.
PVC Pipe PNS 14 1"dia. 140.00 / pcs.
PVC Adapter PNS 14,1/2"dia. 15.00 / pcs.
Entrance cap # 1/2"Ø 65.00 / pcs,
Junction Box (Deep tape w/ Cover) 30.00 / pcs.
Utility Box (Deep tape) ………………………… 25.00 / pcs.
PVC Pipe Flexible 1/2"dia. ………………………… 15.00 / mtrs.
1 set enclosed Panel box w/ 30 AT 2,450.00 / set
main Breaker and 2-20 AT Branch
Convenience outlet/w plate 150.00 / pcs.

Compact flourescent lamp ………………………… 110.00 / sets


Porcelain socket # 4"Ø ………………………… 30.00 / pcs.

Light Switch 1 way 2 gang ………………………… 150.00 / pcs.


Light Switch 1 way 1 gang ………………………… 150.00 / pcs.
Duplex Convenient Outlet ………………………… 200.00 / pcs.
Copper Wire #3.50mm2 TW ………………………… 24.00 / mtrs.
Electrical Tape ………………………… 50.00 / roll
PVC Coupling PNS 14,1/2" dia. ………………………… 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. ………………………… 70.00 / pcs.
PVC Adapter PNS 14,1/2"dia. ………………………… 25.00 / pcs.
Entrance cap # 1/2"Ø ………………………… 80.00 / pcs,
Junction Box (Deep tape w/ Cover) ………………………… 30.00 / pcs.
Air circuit breaker 20 AT ………………………… 600.00 / sets
Lighting Fixture GI pipe Hanger ………………………… 350.00 / sets

Flat wall Latex (Boysen) ………………………… 490.00 / gals.


Latex Paint Semi- Gloss ………………………… 490.00 / gals.
Flatwall Enamel (White Boysen) ………………………… 600.00 / gals.
Quick Drying Enamel ………………………… 500.00 / gals.
Paint Thinner ………………………… 250.00 / gals.
Paint Brush 4" ………………………… 90.00 / pcs.
Paint roller 12" ………………………… 160.00 / pc.
Assorted Acry Color (Latex) ………………………… 135.00 / ltr.
Assorted Tintin Color (Enamel) ………………………… 150.00 / ltr.
Sandpaper #100 ………………………… 1,600.00 / roll
Calsumine powder ………………………… 15.00 / kg.
Concrete Neutralizer ………………………… 220.00 / gals.
Plasalux GlazingPutty 550.00 gal.
LABOR COST

Designation Rate per Day


Construction Foreman ………………………… 530.00
Skilled Laborer ………………………… 400.00
Semi-skilled Laborer ………………………… 350.00
Unskilled Laborer ………………………… 290.00
First Aider ………………………… 290.00
Part time Safety Practitioner ………………………… 530.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor ………………………… 610.00
Bar Cutter (manually operated) ………………………… 350.00
Concrete Mixer (1-Bagger) ………………………… 1,390.00
Concrete Vibrator ………………………… 510.00
Water truck (1000 gal) ………………………… 7,750.00
Welding machine ………………………… 500.00
Cutting Outfit w/ complete accessories ………………………… 150.00
Demountable Beam w/ Ropes ………………………… 700.00
Electric Drill ………………………… 100.00
Riveter ………………………… 100.00
Angle Grinder ………………………… 100.00

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

DETAILED ESTIMATES
Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan

Item No.103 Structure Excavation


QTY. = 12.10 CU.M.

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 4 2.00 530.00 4,240.00
Semi-skilled Laborer (Leadman) 2 2.00 350.00 1,400.00
Unskilled Laborer 0 2.00 290.00 -

Sub-total 5,640.00

Total Direct Cost 5,640.00


Mark-up 2,100.07
Total Item Cost 7,740.07
Unit Cost 639.68

Item No. 404 Reinforcing Steel Bars


QTY. = 2,103.41 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB (12mm & 10mm) 2,103.41 kgs. 52.00 109,377.32
Tie wire (#16 G.I.) 34.00 kgs. 55.00 1,870.00

Sub-total 111,247.32

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 3 1.00 530.00 1,590.00
Skilled Laborer (Steelman) 2 1.00 400.00 800.00
Unskilled Laborer 0 1.00 290.00 -

Sub-total 2,390.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 3 1.00 350.00 1,050.00

Sub-total 1,050.00

Total Direct Cost 114,687.32


Mark-up 4,218.79
Total Item Cost 118,906.11
Unit Cost 56.53
Item No. 405 Structural Concrete
QTY. = 426.72 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 4,054.00 bags 220.00 891,880.00
Washed Sand 213.40 cu. m. 500.00 106,700.00
3/4" Crushed Gravel 427.00 cu. m. 600.00 256,200.00
Gravel fill 4.00 cu. m. 450.00 1,800.00
Forms All LS 5,000.00 5,000.00

Sub-total 1,261,580.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 4.00 530.00 -
Skilled Laborer (Mason/Carpenter) 0 4.00 400.00 -
Unskilled Laborer 0 4.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 4.00 1,390.00 5,560.00
Minor tools (10% of Labor) 0.00

Sub-total 5,560.00

Total Direct Cost 1,267,140.00


Mark-up 34,822.39
Total Item Cost 1,301,962.39
Unit Cost 3,051.09

Item No. 1003 Carpentry & Joinry Works


QTY. = 1.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 1.00 pcs. 355.00 355.00
Ceiling joists (Nailers/Hangers) 6.00 bd. Ft. 75.00 450.00
Assorted CWN 35.00 kgs. 70.00 2,450.00

Sub-total 3,255.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 12.00 530.00 -
Skilled Laborer (Carpenter) 0 12.00 400.00 -
Unskilled Laborer 0 12.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings LS All 3,000.00 3,000.00

Sub-total 3,000.00

Total Direct Cost 6,255.00


Mark-up 62,155.68
Total Item Cost 68,410.68
Unit Cost 68,410.68
Item No. 1010 Doors and Windows
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0.00 0.00 0.00 1,850.00 -
#REF! #REF! #REF! 920.00 #REF!
#REF! #REF! #REF! 6,500.00 #REF!
0.00 0.00 0.00 2,850.00 -
#REF! #REF! #REF! 75.00 #REF!
#REF! #REF! #REF! 450.00 #REF!
#REF! #REF! #REF! 35.00 #REF!
MAIN Circuit Breaker Plug In type 250 amp. 1.00 set 70.00 70.00
0.00 0.00 0.00 1,000.00 1,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 530.00 -
Skilled Laborer (Carpenter) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric drill 1 0.00 100.00 -
Minor tools (10% of Labor) -

Sub-total -

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item No. 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flourescent Lighting Fixtures (40 watts) with box
type housing 1.00 pcs. 650.00 650.00
Compact flourescent lamp 1.00 pcs. 150.00 150.00
Porcelain socket # 4"Ø 1.00 pcs. 45.00 45.00
Light Switch 1 way 3 gang - pcs. 140.00 -
Light Switch 1 way 2 gang - pcs. 140.00 -
Light Switch 1 way 1 gang 2.00 pcs. 140.00 280.00
PVC Coupling PNS 14,1/2" dia. 15.00 pcs. 15.00 225.00
PVC Pipe PNS 14,1/2"dia. 30.00 pcs. 70.00 2,100.00
PVC Pipe PNS 14,1"dia. 1.00 pcs. 140.00 140.00
PVC Adapter PNS 14,1/2"dia. 1.00 pcs. 15.00 15.00
Entrance cap # 1/2"Ø 1.00 pcs, 65.00 65.00
Junction Box (Deep tape w/ Cover) 17.00 pcs. 30.00 510.00
Copper Wire #3.50mm2 TW 350.00 mtrs 26.00 9,100.00
Electrical Tape 3.00 pcs. 40.00 120.00
Utility Box (Deep tape) 20.00 pcs. 25.00 500.00
PVC Pipe Flexible 1/2"dia. 80.00 mtrs 15.00 1,200.00
Ligthing Panel Air circuit breaker 1.00 set 2,450.00 2,450.00
Miscellaneous materials 500.00 500.00

Sub-total 18,050.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 5.00 530.00 2,650.00
Skilled Laborer (Electrician) 1 5.00 400.00 2,000.00
Unskilled Laborer 1 5.00 290.00 1,450.00

Sub-total 6,100.00

Total Direct Cost 24,150.00


Mark-up (24,150.00)
Total Item Cost -
Unit Cost -
Item No. 1002 Plumbing Works
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Wall Fan 4.00 sets 6,750.00 27,000.00
Equipment for Fire Alarm Bell / with accessories 1.00 sets 80.00 80.00
0 0.00 0 25.00 -
0 0.00 0 125.00 -
0 0.00 0 125.00 -
0 0.00 0 110.00 -
0 0.00 0 60.00 -
0 0.00 0 290.00 -
0 0.00 0 580.00 -
0 0.00 0 290.00 -
0 0.00 0 185.00 -
DESCRIPTION NO HOURS 500.00 500.00

Sub-total 27,580.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 530.00 -
Skilled Laborer (Plumber) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 27,580.00


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl-1 Masonry Works


QTY. = #REF! sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0 #REF! 0 10.00 #REF!
Safety Helmet #REF! Man-Days 220.00 #REF!
Safety Gloves #REF! Man-Days 500.00 #REF!
Safety Shoes #REF! Man-Days 52.00 #REF!
0 25.00 0 55.00 1,375.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 #DIV/0! 530.00 #DIV/0!
Skilled Laborer (Mason) NO #DIV/0! 400.00 #DIV/0!
Unskilled Laborer 0 #DIV/0! 290.00 #DIV/0!

Sub-total #DIV/0!

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Output rate: 1 #DIV/0! 1,390.00 #DIV/0!
Minor tools (10% of Labor) #DIV/0!

Sub-total #DIV/0!

Total Direct Cost #REF!


Mark-up 101,233.34
Total Item Cost #REF!
Unit Cost #REF!
Item Spl 2 Cement Plaster Finish
QTY. = #VALUE! sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs #VALUE! bags 220.00 #VALUE!
Washed Sand #VALUE! cu.m 500.00 #VALUE!

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 #REF! 530.00 #REF!
Skilled Laborer (Mason) 0 #REF! 400.00 #REF!
Unskilled Laborer NO #REF! 290.00 #REF!

Sub-total #REF!

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost #VALUE!


Mark-up 79,235.22
Total Item Cost #VALUE!
Unit Cost #VALUE!

Item Spl 3 Roofing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0.00 198.00 l.m. 220.00 43,560.00
0.00 0.00 0 250.00 -
DESCRIPTION NO HOURS 180.00 #VALUE!

#REF!
#REF! #REF! #REF! 430.00 #REF!
#REF! #REF! #REF! 80.00 #REF!
Miscellaneous #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 530.00 -
Skilled Laborer (Tinsmithman) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 0 0.00 100.00 -
Riveter 0 0.00 100.00 -
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost #REF!


Mark-up #VALUE!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl 4 Occupational Safety & Health


QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 5,000.00 5,000.00
Signages, Barricades & Medicines All LS 8,000.00 8,000.00

Sub-total 13,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
First Aider 1.00 6.00 290.00 1,740.00
Part time Safety Practitioner 1.00 4.00 530.00 2,120.00

Sub-total 3,860.00

Total Direct Cost 16,860.00


Mark-up #VALUE!
Total Item Cost #VALUE!
Unit Cost #VALUE!
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name : Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF TOTAL BID AMOUNT

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
Item No. Description Amount
804 (a) Backfilling of excavated materials 7,740.07
404 (a.1) Reinforcing Steel for Column Footing & WF 118,906.11
1010 Door 1,301,962.39
1102 Panel Boards & Cabinets 68,410.68
SPL1 Personal Protective Equipments (PPE) #REF!
0 0 -
SPL2 Safety Health Officer #REF!
Spl. 1 Railings #REF!
#REF! #REF! #VALUE!
#REF! #REF! #REF!
#REF! #REF! #VALUE!

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Three Thousand Four Hundred Three & 23/100 pesos.

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang,
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

BILL OF QUANTITIES
Part No. Part Description:

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
(Columns (1), (2), (3) and (4) are to be filled up by the
Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


five hundred seventy four & 89/100 pesos six thousand one hundred eighty &
07/100 pesos
Backfilling of excavated
804 (a) CU.M. 12.10
materials
In figures: In figures:

Php 639.68 Php 7,740.07


In words: Pesos In words: Pesos
eighty five & 29/100 pesos eighteen thousand seven hundred eighty
nine & 39/100 pesos
404 (a.1) Reinforcing Steel Bars kgs. 2,103.41
In figures: In figures:

Php 56.53 Php 118,906.11


In words: Pesos In words: Pesos
six thousand thirty eight & 10/100 pesos one hundred thirty two thousand two
hundred thirty four & 39/100 pesos
1010 Door cu.m 426.72
In figures: In figures:

Php 3,051.09 Php 1,301,962.39


In words: Pesos In words: Pesos
one thousand forty four & 65/100 pesos two hundred three thousand three hundred
thirty & 68/100 pesos
1102 Panel Boards & Cabinets sq.m 1.00
In figures: In figures:
Php 68,410.68 Php 68,410.68
In words: Pesos In words: Pesos
one hundred fifty eight thousand seven one hundred fifty eight thousand seven
hundred forty two & 59/100 pesos hundred forty two & 59/100 pesos
SPL1 Personal Protective Equipments (PPE) LS All
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
fifty one thousand one hundred twenty fifty one thousand one hundred twenty
eight & 12/100 pesos eight & 12/100 pesos
0 0 LS All
In figures: In figures:

Php 0.00 Php 0.00


In words: Pesos In words: Pesos
twenty three thousand four hundred twenty three thousand four hundred
twenty one & 02/100 pesos twenty one & 02/100 pesos
SPL2 Safety Health Officer LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
nine hundred sixty two & 45 pesos three hundred thirty five thousand one
hundred forty four & 34/100 pesos
Spl. 1 Railings sq.m #REF!
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
three hundred fifty four & 62/100 pesos
two hundred sixteen thousand four
hundred thirty five & 22/100 pesos
#REF! #REF! sq.m #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos

twenty six thousand sixteen & 42/100 twenty six thousand sixteen & 42/100
#REF! #REF! LS All
pesos pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

twenty one thousand nine hundred eighty twenty one thousand nine hundred eighty
#REF! #REF! LS All
& 99/100 pesos & 99/100 pesos
In figures: In figures:
Php #VALUE! Php #VALUE!
TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Three Thousand Four Hundred Three & 23/100 pesos.
Php #REF!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
STATEMENT OF WORK ACCOMPLISHED
as of August 25, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang, Pangasinan, Contract Amount: 3,777,072.52
Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-
Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI) Contract Effectivity: JULY 30, 2012
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP
ITEM NO. DESCRIPTION UNIT TOTAL QTY: UNIT COST ITEM COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

804 (a) Backfilling of excavated materials cu.m. 12.10 639.68 7,740.07 #REF! 10.75 10.75 6,876.51 6,876.51 #REF!
404 (a.1) Reinforcing Steel for Column Footing & WF kgs 2,103.41 56.53 118,906.11 #REF! 178.78 178.78 10,106.46 10,106.46 #REF!
1010 Door sq.m 426.72 3,051.09 1,301,962.39 #REF! 3.65 3.65 11,136.49 11,136.49 #REF!
1102 Panel Boards & Cabinets set 1.00 68,410.68 68,410.68 #REF! - - - - #REF!
SPL1 Personal Protective Equipments (PPE) Mandays/proj. 480.00 #REF! #REF! #REF! - - #REF! #REF! #REF!
0 0 L.S. All - - #REF! 0.20 0.20 - - #REF!
SPL2 Safety Health Officer hrs./proj. #REF! #REF! #REF! #REF! - - #REF! #REF! #REF!
Spl. 1 Railings SQ.M. #REF! #REF! #REF! #REF! 279.72 279.72 #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #VALUE! #VALUE! #VALUE! - - #VALUE! #VALUE! #VALUE!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! - - #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #VALUE! #VALUE! #VALUE! 0.27 0.27 #VALUE! #VALUE! #VALUE!

TOTAL #REF! #REF! #REF! #REF! #REF!


I hereby certify that the accounts and the work accomplished stated above are correct and I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
the labor and materials in connection with this project were already paid, and payment thereof undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Section. OIC-Chief MQC Section

RECOMMENDING APPROVAL: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
BACK-UP COMPUTATION
Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


WALL FOOTING (WF)
60.75 0.30 0.40 1.00 7.29
SEPTIC VAULT
2.40 1.20 1.20 1.00 3.46

TOTAL 10.75 CU.M

ITEM 404 REINFORCING STEEL BARS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


WALL FOOTING (WF)
60.75 3.00 1.00 0.616 1.10 123.49
0.40 204.00 1.00 0.616 1.10 55.29
SEPTIC VAULT (COVER)
3.10 7.00 1.00 0.888 1.10
1.30 16.00 1.00 0.888 1.10

TOTAL 178.78 Kgs.

ITEM 405 STRUCTURAL CONCRETE

LENGTH WIDTH DEPTH # SETS QUANTITY


WALL FOOTING (WF)
60.75 0.30 0.20 1.00 3.65
FLOORING SLAB
15.00 10.00 0.10 1.00
entrance 10.00 2.25 0.10 1.00
SLAB (SEPTIC VAULT)
3.00 1.20 0.10 1.00
2.00 1.20 0.10 1.00
WALL FOOTING (SEPTIC VAULT)
9.00 0.30 0.15 1.00

TOTAL 3.65 CU.M


ITEM 1003 CARPENTRY & JOINERY WORKS

LENGTH WIDTH # SETS QUANTITY


CEILING (interior)
15.00 10.00 1.00
CEILING (eaves)
55.80 0.80 1.00

TOTAL 0.00 SQ.M

ITEM 1010 DOORS & WINDOWS

Q = ALL Q = ALL

ITEM 1002 PLUMBING WORKS

Q = ALL Q = ALL

ITEM 1100 ELECTRICAL WORKS

Q = ALL Q = ALL

ITEM SPL-1 MASONRY WORKS

LENGTH HEIGHT # SETS QUANTITY


EXTERIOR WALL
40.00 3.10 1.00 124.00
WALL PARTITION
60.75 3.30 1.00 200.48
APEX
10.00 2.40 2.00
LESS WINDOWS & DOOR
2.40 1.20 3.00 -8.64
1.20 1.20 7.00 -10.08
1.50 1.20 1.00 -1.80
0.60 0.60 2.00 -0.72
1.80 2.10 1.00 -3.78
1.00 2.10 7.00 -14.70
0.80 2.10 3.00 -5.04
SEPTIC VAULT
9.00 1.50 1.00

TOTAL 279.72 SQ.M


ITEM SPL-2 PLASTERING WORKS

LENGTH HEIGHT # SETS #FACES QUANTITY


EXTERIOR WALL
40.00 3.10 1.00 2.00
WALL PARTITION
60.75 2.90 1.00 2.00
APEX
10.00 2.40 2.00 1.00
LESS WINDOWS & DOOR
2.40 1.20 3.00 2.00
1.20 1.20 7.00 2.00
1.50 1.20 1.00 2.00
0.60 0.60 2.00 2.00
1.80 2.10 1.00 2.00
1.00 2.10 7.00 2.00
0.80 2.10 3.00 2.00
SEPTIC VAULT
9.00 1.50 1.00 1.00

TOTAL 0.00 SQ.M

ITEM SPL-3 ROOFING WORKS

Q = ALL Q = ALL

ITEM SPL.4 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL
STATEMENT OF WORK ACCOMPLISHED
as of August 25, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Contract Amount: 3,777,072.52
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Contract Effectivity: JULY 30, 2012
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP


NO. NAME OF PROJECT TOTAL COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

Construction of Multi-Purpose Building at Brgy. Sanlibo,


I 596,702.26 15.80% 76,967.61 76,967.61 2.04%
Bayambang, Pangasinan
Improvement of Multi-purpose Bldg. at Doyong NHS, San
II 298,349.65 7.90% - - 0.00%
Carlos City, Pangasinan
Completion of Bayambang District Hospital
III 1,193,403.23 31.60% #REF! #REF! #REF!
(OPD/Laboratory Complex Bldg.), Bayambang, Pangasinan
Construction of Multi-Purpose Bldg. at Bureau of Jail
IV 497,243.12 13.16% - - 0.00%
Management and Penology, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
V 397,799.76 10.53% 397,799.76 397,799.76 10.53%
Sapinit, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VI 396,787.25 10.51% 201,089.11 201,089.11 5.32%
Polo, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VII 396,787.25 10.51% - - 0.00%
Turac, San Carlos City, Pangasinan

TOTAL 3,777,072.52 100.00% #REF! #REF! #REF!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were already undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Se OIC-Chief MQC Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
STATEMENT OF WORK ACCOMPLISHED
as of September 27, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang, Contract Amount: 3,777,072.52
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI) Contract Effectivity: JULY 30, 2012
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP
ITEM NO. DESCRIPTION UNIT TOTAL QTY: UNIT COST ITEM COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

804 (a) Backfilling of excavated materials cu.m. 12.10 639.68 7,740.07 #REF! 10.75 1.35 12.10 6,180.07 1,560.00 7,740.07 #REF!
404 (a.1) Reinforcing Steel for Column Footing & WF kgs 2,103.41 56.53 118,906.11 #REF! 178.78 1,924.63 2,103.41 15,248.15 103,657.96 118,906.11 #REF!
1010 Door sq.m 426.72 3,051.09 1,301,962.39 #REF! 3.65 423.07 426.72 22,039.07 1,279,923.32 1,301,962.39 #REF!
1102 Panel Boards & Cabinets set 1.00 68,410.68 68,410.68 #REF! 1.00 1.00 68,410.68 68,410.68 #REF!
SPL1 Personal Protective Equipments (PPE) Mandays/proj. 480.00 #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
0 0 L.S. All - - #REF! 0.20 0.80 1.00 10,225.62 (10,225.62) - #REF!
SPL2 Safety Health Officer hrs./proj. #REF! #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
Spl. 1 Railings SQ.M. #REF! #REF! #REF! #REF! 279.72 #REF! #REF! 269,211.70 #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #VALUE! #VALUE! #VALUE! #REF! #REF! #VALUE! #VALUE! #VALUE!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #VALUE! #VALUE! #VALUE! 0.27 0.73 1.00 5,934.87 #VALUE! #VALUE! #VALUE!

TOTAL #REF! #REF! 328,839.48 #REF! #REF! #REF!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
already paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Section. OIC-Chief MQC Section

RECOMMENDING APPROVAL: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
STATEMENT OF WORK ACCOMPLISHED
as of September 27, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Contract Amount: 3,777,072.52
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Contract Effectivity: JULY 30, 2012
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP


NO. NAME OF PROJECT TOTAL COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

Construction of Multi-Purpose Building at Brgy. Sanlibo,


I 596,702.26 15.80% 76,967.61 519,734.65 596,702.26 15.80%
Bayambang, Pangasinan
Improvement of Multi-purpose Bldg. at Doyong NHS, San
II 298,349.65 7.90% - - 0.00%
Carlos City, Pangasinan
Completion of Bayambang District Hospital
III 1,193,403.23 31.60% 328,839.48 #REF! #REF! #REF!
(OPD/Laboratory Complex Bldg.), Bayambang, Pangasinan
Construction of Multi-Purpose Bldg. at Bureau of Jail
IV 497,243.12 13.16% 497,243.12 497,243.12 13.16%
Management and Penology, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
V 397,799.76 10.53% 397,799.76 - 397,799.76 10.53%
Sapinit, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VI 396,787.25 10.51% 201,089.11 195,698.14 396,787.25 10.51%
Polo, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VII 396,787.25 10.51% 320,429.80 320,429.80 8.48%
Turac, San Carlos City, Pangasinan

TOTAL 3,777,072.52 100.00% 1,004,695.96 #REF! #REF! #REF!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were already undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Secti OIC-Chief MQC Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0017
Contract Name : Completion of Multi-Purpose Building at Buenlag 1st & Manabong Sur, Bayambang, Pangasinan, Construction of 2-Cl at
Arenas NHS, Ambayat 2nd, Bayambang, Pangasinan, Construction of 1-Cl at Bogaoan E/S, San Carlos City and Completion
of Multi-Purpose Building (Gym) at Brgy. Coliling & Brgy. Quintong, San Carlos City, Pangasinan (CLUSTER I)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


C-Rafter 46mm x 148mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 75mm (1.00mm) ………………………… 460.00 / pcs.
C-Purlins 44mm x 100mm (1.00mm) ………………………… 510.00 / pcs.
C-Purlins 50mm x 150mm (1.40mm) ………………………… 1,075.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x 200mm ………………………… 150.00 / pcs.
Anchor Bolt, 16mmØ x 250mm ………………………… 170.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
20mm dia. X 50 Machine Bolts w/ nuts ………………………… 100.00 / pcs.
20mm dia. X 500 Straight Bolts w/ nuts ………………………… 250.00 / pcs.
16mm dia. X 200 Anchor Bolts w/ nuts ………………………… 120.00 / pcs.
10mm Thk. Steel Plate ………………………… 18,500.00 / pcs.
Gusset Plates 4 x 8 x 4mm ………………………… 12,550.00 / pcs.
Base Plate 150mm x 300mm x 4mm ………………………… 300.00 / pcs.
Base Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 250mm x 200mm x 4mm ………………………… 200.00 / pcs.
71.2 x 71.2 x 5.00mm Angle Bar ………………………… 2,425.00 / pcs.
46.8 x 46.8 x 5.00mm Angle Bar ………………………… 1,400.00 / pcs.
46.8 x 46.8 x 4.25mm Angle Bar ………………………… 980.00 / pcs.
46.8 x 46.8 x 3.50mm Angle Bar ………………………… 800.00 / pcs.
38.0 x 38.0 x 3.50mm Angle Bar ………………………… 685.00 / pcs.
20mm dia. Tension Rod (Strut 1) ………………………… 50.00 / kgs.
Plain 12mm dia w/ nuts & washer at both ends (Sag Rod) ………………………… 80.00 / pcs.
Plain 12mm dia (Cross bracing) ………………………… 50.00 / kgs.
Std. Turn Buckel 12mm dia. ………………………… 200.00 / pcs.
C-Rafter 46mmx150mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 100mm (1.0mm) ………………………… 510.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x .200mm ………………………… 150.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
Base / Sole Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 300mm x 150mm x 4mm ………………………… 300.00 / pcs.
Cleats 48.1 x 48.1 x 3.5mm Angular bar ………………………… 950.00 / pcs.
Sag Rod(10mm ø) Plain bar with Bolts & Washers ………………………… 80.00 / pcs.
Paint brush 4" ………………………… 90.00 / pcs.
Thinner ………………………… 250.00 / gal
Red Lead Primer ………………………… 550.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 65.00 / pcs.
150X150X4mm, Base Plate ………………………… 150.00 / pcs.
10mm dia.Sag rod w/n/b ………………………… 80.00 / pcs.
10mm dia,x0.70m.Dowels ………………………… 25.00 / pcs.
12mm dia. X 150mm long Anchor Bolt ………………………… 80.00 / pcs.

Ceramics Glazed Tiles & Trims ………………………… 750.00 / sq.m.


Ceramics Unglazed Tiles & Trims ………………………… 850.00 / sq.m.
Tile Grout ………………………… 70.00 / kls.

Paint brush 4" ………………………… 90.00 / pcs.


Paint brush 2" ………………………… 45.00 / pcs.
Paint Tinner ………………………… 240.00 / gal
Red Lead Primer ………………………… 580.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 75.00 / pcs.
Portland Cement, 40 kgs ………………………… 225.00 / bags
Washed Sand ………………………… 480.00 / cu. m.
Gravel Fill ………………………… 450.00 / cu. m.
River mix ………………………… 300.00 / cu.m.
Crushed Gravel ………………………… 580.00 / cu. m.
Plywood - 1/2 x 4' x 8' ………………………… 625.00 / pcs.
Plywood - 1/4 x 4' x 8' ………………………… 355.00 / pcs.
Good Lumber ………………………… 75.00 / bd.ft
Coco Lumber ………………………… 28.00 / bd.ft
Air ventillation ………………………… 450.00 / set
Assorted CWN ………………………… 70.00 / kgs
Asstd. RSB ………………………… 55.00 / kgs
Tie wire # 16 GI ………………………… 57.00 / kgs
CHB ( 4" x 8" x 16") ………………………… 10.00 / pcs
Security Steel Grills (10mm) ………………………… 1,200.00 / sq.m.
Sliding Analuk Windows ………………………… 3,000.00 / sq.m.
Jalousie window w/ Aluminum Frame ………………………… 850.00 / sq.m.
Swing type Steel Casement window with glass ………………………… 1,850.00 / sq.m.
Panel type door (2.10m X 0.90m) incl. Door jambs & …………………………
Hinges with screw. 5,000.00 / sets
5/8"Glass Door With Aluminum Frames ………………………… 6,500.00 / sq.m.
Flush hollow core door ………………………… 920.00 / sq.m.
PVC Door (2.10m x 0.80m) incl. Door jambs & Hinges with …………………………
screw. 2,850.00 / units
Improvised Door Lock (Hook-in flat bar 4mm Thk with …………………………
padlock and puller) 380.00 / pcs.
Door lock w/ screw ………………………… 450.00 / pcs.
Hinges ………………………… 35.00 / pcs.
Pre-painted Tri-wave (0.40mm) ………………………… 420.00 / sq.m.
Pre-painted ready made ridge roll (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Flashing S-Type (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made End Flashing (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Gutter (0.40mm) ………………………… 220.00 / L.M.
Tekscrew ………………………… 2.00 / pcs.
Blind rivets ………………………… 250.00 / box
Silicon Sealant ………………………… 180.00 / pcs.
Toilet Bowl ………………………… 1,000.00 / set
Water Closet ………………………… 6,750.00 / set
PVC pipe 4" dia. ………………………… 580.00 / pcs.
PVC pipe 2" dia. ………………………… 290.00 / pc.
PVC pipe 4 x 2 wye ………………………… 95.00 / pc.
PVC pipe 4 x 4 wye ………………………… 125.00 / pc.
PVC pipe 4 x 4 tee ………………………… 125.00 / pc.
PVC pipe 4 x 2 Tee ………………………… 80.00 / pc.
PVC pipe 2" dia. Elbow 1/4 bend ………………………… 25.00 / pc.
PVC pipe 2" dia. Elbow 1/8 bend ………………………… 20.00 / pc.
PVC pipe 4" dia. Elbow 1/4 bend ………………………… 80.00 / pc.
PVC pipe 4" dia. Elbow 1/8 bend ………………………… 55.00 / pc.
PVC pipe 2" dia. P-Trap ………………………… 105.00 / pc.
PVC pipe 4" dia. Cleanout w/ plug ………………………… 60.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. ………………………… 110.00 / pcs.
Solvent ………………………… 185.00 / can
Floor drain 4" x 4" H.D. ………………………… 290.00 / pc.
G I pipe 1/2" dia ………………………… 365.00 / pcs.
G I coupling 1/2" dia. ………………………… 8.00 / pcs.
G I elbow 1/2" dia. ………………………… 10.00 / pcs.
G I tee 1/2" dia ………………………… 22.00 / pcs.
G I adapter 1/2" dia ………………………… 15.00 / pcs.
Faucet 1/2" dia ………………………… 170.00 / pcs.
PVC pipe 3" dia. (downspout) ………………………… 430.00 / pcs.
PVC pipe 3" dia. Elbow 1/4 bend ………………………… 80.00 / pc.

Flourescent Lighting Fixtures (40 watts) with box type housing ………………………… 650.00 / sets
Lighting Fixture (CFL 20 A) 150.00 / sets
Bulb Receptacles 45.00 / pcs.
Light Switch 1 way 2 gang 140.00 / pc.
Light Switch 1 way 1 gang 140.00 / pc.
Copper Wire #3.50mm2 TW 26.00 / mtrs.
Electrical Tape 40.00 / roll
PVC Pipe Flexible 1/2"dia. 15.00 / mtrs.
PVC Coupling PNS 14,1/2" dia. 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. 70.00 / pcs.
PVC Pipe PNS 14 1"dia. 140.00 / pcs.
PVC Adapter PNS 14,1/2"dia. 15.00 / pcs.
Entrance cap # 1/2"Ø 65.00 / pcs,
Junction Box (Deep tape w/ Cover) 30.00 / pcs.
Utility Box (Deep tape) ………………………… 25.00 / pcs.
PVC Pipe Flexible 1/2"dia. ………………………… 15.00 / mtrs.
1 set enclosed Panel box w/ 30 AT 2,450.00 / set
main Breaker and 2-20 AT Branch
Convenience outlet/w plate 150.00 / pcs.

Compact flourescent lamp ………………………… 110.00 / sets


Porcelain socket # 4"Ø ………………………… 30.00 / pcs.

Light Switch 1 way 2 gang ………………………… 150.00 / pcs.


Light Switch 1 way 1 gang ………………………… 150.00 / pcs.
Duplex Convenient Outlet ………………………… 200.00 / pcs.
Copper Wire #3.50mm2 TW ………………………… 24.00 / mtrs.
Electrical Tape ………………………… 50.00 / roll
PVC Coupling PNS 14,1/2" dia. ………………………… 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. ………………………… 70.00 / pcs.
PVC Adapter PNS 14,1/2"dia. ………………………… 25.00 / pcs.
Entrance cap # 1/2"Ø ………………………… 80.00 / pcs,
Junction Box (Deep tape w/ Cover) ………………………… 30.00 / pcs.
Air circuit breaker 20 AT ………………………… 600.00 / sets
Lighting Fixture GI pipe Hanger ………………………… 350.00 / sets

Flat wall Latex (Boysen) ………………………… 490.00 / gals.


Latex Paint Semi- Gloss ………………………… 490.00 / gals.
Flatwall Enamel (White Boysen) ………………………… 600.00 / gals.
Quick Drying Enamel ………………………… 500.00 / gals.
Paint Thinner ………………………… 250.00 / gals.
Paint Brush 4" ………………………… 90.00 / pcs.
Paint roller 12" ………………………… 160.00 / pc.
Assorted Acry Color (Latex) ………………………… 135.00 / ltr.
Assorted Tintin Color (Enamel) ………………………… 150.00 / ltr.
Sandpaper #100 ………………………… 1,600.00 / roll
Calsumine powder ………………………… 15.00 / kg.
Concrete Neutralizer ………………………… 220.00 / gals.
Plasalux GlazingPutty 550.00 gal.
LABOR COST

Designation Rate per Day


Construction Foreman ………………………… 540.00
Skilled Laborer ………………………… 400.00
Semi-skilled Laborer ………………………… 350.00
Unskilled Laborer ………………………… 280.00
First Aider ………………………… 280.00
Part time Safety Practitioner ………………………… 540.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor ………………………… 610.00
Bar Cutter (manually operated) ………………………… 350.00
Concrete Mixer (1-Bagger) ………………………… 1,390.00
Concrete Vibrator ………………………… 510.00
Water truck (1000 gal) ………………………… 7,750.00
Welding machine ………………………… 500.00
Cutting Outfit w/ complete accessories ………………………… 150.00
Demountable Beam w/ Ropes ………………………… 700.00
Electric Drill ………………………… 100.00
Riveter ………………………… 100.00
Angle Grinder ………………………… 100.00

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy.
Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose
Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and
Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

DETAILED ESTIMATES
Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan

Item No.103 Structure Excavation


QTY. = 12.10 CU.M.

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 4 2.00 540.00 4,320.00
Semi-skilled Laborer (Leadman) 2 2.00 350.00 1,400.00
Unskilled Laborer 0 2.00 280.00 -

Sub-total 5,720.00

Total Direct Cost 5,720.00


Mark-up 2,169.42
Total Item Cost 7,889.42
Unit Cost 652.02

Item No. 404 Reinforcing Steel Bars


QTY. = 2,103.41 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB (12mm & 10mm) 2,103.41 kgs. 55.00 115,687.55
Tie wire (#16 G.I.) 34.00 kgs. 57.00 1,938.00

Sub-total 117,625.55

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 3 1.00 540.00 1,620.00
Skilled Laborer (Steelman) 2 1.00 400.00 800.00
Unskilled Laborer 0 1.00 280.00 -

Sub-total 2,420.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 3 1.00 350.00 1,050.00

Sub-total 1,050.00

Total Direct Cost 121,095.55


Mark-up 3,606.53
Total Item Cost 124,702.08
Unit Cost 59.29
Item No. 405 Structural Concrete
QTY. = 426.72 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 4,054.00 bags 225.00 912,150.00
Washed Sand 213.40 cu. m. 480.00 102,432.00
3/4" Crushed Gravel 427.00 cu. m. 580.00 247,660.00
Gravel fill 4.00 cu. m. 450.00 1,800.00
Forms All LS 5,000.00 5,000.00

Sub-total 1,269,042.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 4.00 540.00 -
Skilled Laborer (Mason/Carpenter) 0 4.00 400.00 -
Unskilled Laborer 0 4.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 4.00 1,390.00 5,560.00
Minor tools (10% of Labor) 0.00

Sub-total 5,560.00

Total Direct Cost 1,274,602.00


Mark-up 35,032.68
Total Item Cost 1,309,634.68
Unit Cost 3,069.07

Item No. 1003 Carpentry & Joinry Works


QTY. = 1.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 1.00 pcs. 355.00 355.00
Ceiling joists (Nailers/Hangers) 6.00 bd. Ft. 75.00 450.00
Assorted CWN 35.00 kgs. 70.00 2,450.00

Sub-total 3,255.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 12.00 540.00 -
Skilled Laborer (Carpenter) 0 12.00 400.00 -
Unskilled Laborer 0 12.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings LS All 3,000.00 3,000.00

Sub-total 3,000.00

Total Direct Cost 6,255.00


Mark-up 62,581.26
Total Item Cost 68,836.26
Unit Cost 68,836.26
Item No. 1010 Doors and Windows
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0.00 0.00 0.00 1,850.00 -
#REF! #REF! #REF! 920.00 #REF!
#REF! #REF! #REF! 6,500.00 #REF!
0.00 0.00 0.00 2,850.00 -
#REF! #REF! #REF! 75.00 #REF!
#REF! #REF! #REF! 450.00 #REF!
#REF! #REF! #REF! 35.00 #REF!
MAIN Circuit Breaker Plug In type 250 amp. 1.00 set 70.00 70.00
0.00 0.00 0.00 1,000.00 1,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 540.00 -
Skilled Laborer (Carpenter) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric drill 1 0.00 100.00 -
Minor tools (10% of Labor) -

Sub-total -

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item No. 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flourescent Lighting Fixtures (40 watts) with box type
housing 1.00 pcs. 650.00 650.00
Compact flourescent lamp 1.00 pcs. 150.00 150.00
Porcelain socket # 4"Ø 1.00 pcs. 45.00 45.00
Light Switch 1 way 3 gang - pcs. 140.00 -
Light Switch 1 way 2 gang - pcs. 140.00 -
Light Switch 1 way 1 gang 2.00 pcs. 140.00 280.00
PVC Coupling PNS 14,1/2" dia. 15.00 pcs. 15.00 225.00
PVC Pipe PNS 14,1/2"dia. 30.00 pcs. 70.00 2,100.00
PVC Pipe PNS 14,1"dia. 1.00 pcs. 140.00 140.00
PVC Adapter PNS 14,1/2"dia. 1.00 pcs. 15.00 15.00
Entrance cap # 1/2"Ø 1.00 pcs, 65.00 65.00
Junction Box (Deep tape w/ Cover) 17.00 pcs. 30.00 510.00
Copper Wire #3.50mm2 TW 350.00 mtrs 26.00 9,100.00
Electrical Tape 3.00 pcs. 40.00 120.00
Utility Box (Deep tape) 20.00 pcs. 25.00 500.00
PVC Pipe Flexible 1/2"dia. 80.00 mtrs 15.00 1,200.00
Ligthing Panel Air circuit breaker 1.00 set 2,450.00 2,450.00
Miscellaneous materials 500.00 500.00

Sub-total 18,050.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 5.00 540.00 2,700.00
Skilled Laborer (Electrician) 1 5.00 400.00 2,000.00
Unskilled Laborer 1 5.00 280.00 1,400.00

Sub-total 6,100.00

Total Direct Cost 24,150.00


Mark-up (24,150.00)
Total Item Cost -
Unit Cost -
Item No. 1002 Plumbing Works
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Wall Fan 4.00 sets 6,750.00 27,000.00
Equipment for Fire Alarm Bell / with accessories 1.00 sets 80.00 80.00
0 0.00 0 25.00 -
0 0.00 0 125.00 -
0 0.00 0 125.00 -
0 0.00 0 110.00 -
0 0.00 0 60.00 -
0 0.00 0 290.00 -
0 0.00 0 580.00 -
0 0.00 0 290.00 -
0 0.00 0 185.00 -
DESCRIPTION NO HOURS 500.00 500.00

Sub-total 27,580.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 540.00 -
Skilled Laborer (Plumber) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 27,580.00


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl-1 Masonry Works


QTY. = #REF! sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0 #REF! 0 10.00 #REF!
Safety Helmet #REF! Man-Days 225.00 #REF!
Safety Gloves #REF! Man-Days 480.00 #REF!
Safety Shoes #REF! Man-Days 55.00 #REF!
0 25.00 0 57.00 1,425.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 #DIV/0! 540.00 #DIV/0!
Skilled Laborer (Mason) NO #DIV/0! 400.00 #DIV/0!
Unskilled Laborer 0 #DIV/0! 280.00 #DIV/0!

Sub-total #DIV/0!

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Output rate: 1 #DIV/0! 1,390.00 #DIV/0!
Minor tools (10% of Labor) #DIV/0!

Sub-total #DIV/0!

Total Direct Cost #REF!


Mark-up 98,932.26
Total Item Cost #REF!
Unit Cost #REF!
Item Spl 2 Cement Plaster Finish
QTY. = #VALUE! sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs #VALUE! bags 225.00 #VALUE!
Washed Sand #VALUE! cu.m 480.00 #VALUE!

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 #REF! 540.00 #REF!
Skilled Laborer (Mason) 0 #REF! 400.00 #REF!
Unskilled Laborer NO #REF! 280.00 #REF!

Sub-total #REF!

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost #VALUE!


Mark-up 79,043.70
Total Item Cost #VALUE!
Unit Cost #VALUE!

Item Spl 3 Roofing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
0.00 198.00 l.m. 220.00 43,560.00
0.00 0.00 0 250.00 -
DESCRIPTION NO HOURS 180.00 #VALUE!

#REF!
#REF! #REF! #REF! 430.00 #REF!
#REF! #REF! #REF! 80.00 #REF!
Miscellaneous #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 540.00 -
Skilled Laborer (Tinsmithman) 0 0.00 400.00 -
Unskilled Laborer 0 0.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 0 0.00 100.00 -
Riveter 0 0.00 100.00 -
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost #REF!


Mark-up #VALUE!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl 4 Occupational Safety & Health


QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 5,000.00 5,000.00
Signages, Barricades & Medicines All LS 8,000.00 8,000.00

Sub-total 13,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
First Aider 1.00 6.00 280.00 1,680.00
Part time Safety Practitioner 1.00 4.00 540.00 2,160.00

Sub-total 3,840.00

Total Direct Cost 16,840.00


Mark-up #VALUE!
Total Item Cost #VALUE!
Unit Cost #VALUE!
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name : Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy.
Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose
Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and
Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF TOTAL BID AMOUNT

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
Item No. Description Amount
804 (a) Backfilling of excavated materials 7,889.42
404 (a.1) Reinforcing Steel for Column Footing & WF 124,702.08
1010 Door 1,309,634.68
1102 Panel Boards & Cabinets 68,836.26
SPL1 Personal Protective Equipments (PPE) #REF!
0 0 -
SPL2 Safety Health Officer #REF!
Spl. 1 Railings #REF!
#REF! #REF! #VALUE!
#REF! #REF! #REF!
#REF! #REF! #VALUE!

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Five Thousand One Hundred Ninety Eight & 76/100 pesos.

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang,
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

BILL OF QUANTITIES
Part No. Part Description:

Construction of 1-Storey, 1 CL.Rm. School Building at Coliling NHS,Coliling,San Carlos City, Pangasinan
(Columns (1), (2), (3) and (4) are to be filled up by the
Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


five hundred seventy five & 76/100 pesos six thousand one hundred eighty nine &
42/100 pesos
Backfilling of excavated
804 (a) CU.M. 12.10
materials
In figures: In figures:

Php 652.02 Php 7,889.42


In words: Pesos In words: Pesos
eighty five & 42/100 pesos eighteen thousand eight hundred eighteen
& 03/100 pesos
404 (a.1) Reinforcing Steel Bars kgs. 2,103.41
In figures: In figures:

Php 59.29 Php 124,702.08


In words: Pesos In words: Pesos
six thousand forty seven & 20/100 pesos one hundred thirty two thousand four
hundred thirty three & 68/100 pesos
1010 Door cu.m 426.72
In figures: In figures:

Php 3,069.07 Php 1,309,634.68


In words: Pesos In words: Pesos
one thousand forty six & 22/100 pesos two hundred three thousand six hundred
thirty six & 26/100 pesos
1102 Panel Boards & Cabinets sq.m 1.00
In figures: In figures:
Php 68,836.26 Php 68,836.26
In words: Pesos In words: Pesos
one hundred fifty eight thousand nine one hundred fifty eight thousand nine
hundred eighty two & 02/100 pesos hundred eighty two & 02/100 pesos
SPL1 Personal Protective Equipments (PPE) LS All
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
fifty one thousand two hundred five & fifty one thousand two hundred five &
24/100 pesos 24/100 pesos
0 0 LS All
In figures: In figures:

Php 0.00 Php 0.00


In words: Pesos In words: Pesos
twenty three thousand four hundred fifty twenty three thousand four hundred fifty
six & 35/100 pesos six & 35/100 pesos
SPL2 Safety Health Officer LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
nine hundred sixty three & 90/100 pesos three hundred thirty five thousand six
hundred forty nine & 26/100 pesos
Spl. 1 Railings sq.m #REF!
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
three hundred fifty five & 15/100 pesos
two hundred sixteen thousand seven
hundred fifty eight & 70/100 pesos
#REF! #REF! sq.m #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos

twenty six thousand fifty five & 66/100 twenty six thousand fifty five & 66/100
#REF! #REF! LS All
pesos pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

twenty two thousand fourteen & 14/100 twenty two thousand fourteen & 14/100
#REF! #REF! LS All
pesos pesos
In figures: In figures:
Php #VALUE! Php #VALUE!
TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Five Thousand One Hundred Ninety Eight & 76/100 pesos.
Php #REF!

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
DETAILED ESTIMATES
Item No. Spl.4
Steel Gate & Perimeter Fences QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day
MATERIAL COST

Steel Gate (4.00m width) 3.00 set 30,000.00 90,000.00


Steel Gate (3.00m width) 1.00 set 21,150.00 21,150.00
Steel junior Gate (1.20m width) 1.00 set 9,000.00 9,000.00
Fences (3.00m width) 11.00 set 11,700.00 128,700.00
Miscellaneous materials (primer, paint thinner, welding rod,etc.,) 2,500.00

Sub- Total 251,350.00


unit cost 251,350.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 14.00 524.36 7,341.04


LABOR COST

Skilled Laborer (Welder) 2.00 14.00 380.99 10,667.72


Unskilled Laborer 5.00 14.00 293.96 20,577.20
8.00 14.00 112.00

Note:
Labor includes repair & installation of old fences.

Sub- Total 38,585.96


unit cost 38,585.96
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Welding machine 1.00 14.00 500.00 7,000.00


EQUIPMENT COST

Grinder (handy) 1.00 14.00 150.00 2,100.00


Electricity,Acetylane,oxygen & etc. All LS 5,890.93 5,890.93
Minor tools (10% of Labor) 3,858.60

Sub- Total 18,849.53


unit cost 18,849.53
Direct Unit Cost 308,785.49
PREPARED BY: 12% of total DC OCM 37,054.26
12% of total DC CP 37,054.26
12% of (total DC+OCM+CP) VAT 45,947.28
Total Direct & Indirect Unit Cost 428,841.28
Total Direct & Indirect Cost 428,841.28
DETAILED ESTIMATES
Item No. Spl 1
Roofing Works QTY. 59,828.24 sq.m.
DESCRIPTION QUANTITY UNIT U-PRICE(Pesos) TOTAL(P)
Pre-painted Tri-wave (0.40mm) 59,828.24 sq.m. 450.00 26,922,708.00
Pre-painted ready made Flashing(0.40mm) 5.00 pcs. 462.00 2,310.00
MATERIALS COST

Pre-painted ready made Ridge Roll(0.40mm) 2.00 pcs. 462.00 924.00


Tekscrew 150.00 pcs. 2.00 300.00
Blind Rivets 0.50 boxes 200.00 100.00
Silicone Selant 1.00 pcs. 170.00 170.00
Pre-painted ready made S. Gutter 3.00 pcs. 462.00 1,386.00
Miscellaneous All LS 800.00 800.00

Sub- Total 26,928,698.00


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Const'n. Foreman 1 1.00 524.36 524.36
Tinsmithman 1 1.00 380.99 380.99
LABOPR COST

Laborer 2 1.00 293.96 587.92


4 1.00 4
4 1.00 4

12 1.00 12
Sub- Total 1,493.27
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Electric Drill 1 1.00 85.00 85.00
EQUIPMENT COST

Riveter 1 1.00 85.00 85.00


Scafoldings 1 lot 1,000.00 1,000.00

Sub- Total 1,170.00


Total Direct Cost 26,931,361.27
Total Indirect Cost 10,470,913.26
12% (TDC) 0.15 CP 3,231,763.35
12% (TDC) 0.13 OCM 3,231,763.35
12% (TDC+CP+OCM) VAT 4,007,386.56
Total Item Cost 37,402,274.53
Adjusted Unit Cost 625.16
DETAILED ESTIMATES
Item No. 803
Structural Excavation QUANTITY #VALUE! cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
MATREIAL COST

Sub- Total -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 1.00 524.36 524.36
Semi-skilled Laborer (Leadman) 1.00 1.00 351.21 351.21
Unskilled Laborer 3.00 1.00 293.96 881.88
LABOAR COST

5.00 1.00 5.00

Sub- Total 1,757.45


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Sub- Total -
Total Direct Cost 1,757.45
PREPARED BY: 12% of total DC OCM 210.89
12% of total DC CP 210.89
12% of (total DC+OCM+CP) VAT 261.51
Total Item Cost 2,440.75
Adjusted Unit Cost #VALUE!
DETAILED ESTIMATES
Item No. 104
Structure Backfill QUANTITY #VALUE! cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
River mix #VALUE! cu.m. 300.00 #VALUE!
MATERIAL COST

Sub- Total #VALUE!


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 0.50 524.36 262.18
Unskilled Laborer 2.00 0.50 293.96 293.96
3.00 0.50 1.50
LABOR COST

Sub- Total 556.14


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)

Sub- Total -
Total Direct Cost #VALUE!
PREPARED BY: 12% of total DC OCM #VALUE!
12% of total DC CP #VALUE!
12% of (total DC+OCM+CP) VAT #VALUE!
Total Item Cost #VALUE!
Adjusted Unit Cost #VALUE!
DETAILED ESTIMATES
Item No. 409
Structural Steel QUANTITY All L.S
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
C-Rafter 46mmx150mm (1.20mm) 7.00 pcs. 1,060.00 7,420.00
C-Purlins 44mm x 75mm (1.0mm) 12.00 pcs. 455.00 5,460.00
Facia Board 50mm x 250mm (0.98mm) 5.00 pcs. 1,000.00 5,000.00
Anchor Bolt, 12mmØ x 150mm 12.00 pcs. 100.00 1,200.00
Anchor Bolt, 12mmØ x 100mm 12.00 pcs. 70.00 840.00
Base Plate 150mm x 150mm x 4mm 2.00 pcs. 150.00 300.00
MATERIAL COST

Base Plate 300mm x 150mm x 4mm 4.00 pcs. 300.00 1,200.00


Cleats 48.1 x 48.1 x 3.5mm Angular bar 1.00 pcs. 800.00 800.00
Sag Rod(10mm ø) Plain bar with Bolts & Washers 22.00 pcs. 80.00 1,760.00
Paint brush 4" 2.00 pcs. 85.00 170.00
Thinner 1.00 gal 240.00 240.00
Red Lead Primer 2.00 gal 600.00 1,200.00
Welding Rod 10.00 kgs. 75.00 750.00
Hacksaw blade 2.00 pcs. 65.00 130.00

Sub- Total 26,470.00


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 2.50 524.36 1,310.90
Skilled Laborer (Welder) 1.00 2.50 380.99 952.48
LABOR COST

Unskilled Laborer 3.00 2.50 293.96 2,204.70


5.00 2.50 12.50

Sub- Total 4,468.08


DESCRIPTION NO DAYS Rental(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Welding machine 1.00 2.50 500.00 1,250.00


Scaffolding 1.00 lot 800.00 800.00
Electricity,Acetylane,oxygen & etc. All LS 2,000.00 2,000.00

Sub- Total 4,050.00


Total Direct Cost 34,988.08
PREPARED BY: 12% of total DC OCM 4,198.57
12% of total DC CP 4,198.57
12% of (total DC+OCM+CP) VAT 5,206.23
Total Item Cost 48,591.44
Adjusted Unit Cost 48,591.44
DETAILED ESTIMATES
Item No. 1013
Roofing Works QUANTITY 123.86 sq.m.
DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL(Pesos)
Pre-painted Tri-wave (0.40mm) 123.86 sq.m. 400.00 49,544.00
MATERIAL COST

Pre-painted ready made ridge roll (0.40mm) 3.00 pcs. 475.00 1,425.00
Pre-painted ready made Flashing (0.40mm) 7.00 pcs. 475.00 3,325.00
Pre-painted ready made Gutter (0.40mm) 3.00 pcs. 475.00 1,425.00
Tekscrew 350.00 pcs. 1.85 647.50
Miscellaneous (sealant, blind revits, etc.,) All LS 300.00 300.00

56,666.50
DESCRIPTION NO DAYS RATE TOTAL(Pesos)
Construction Foreman 1.00 1.00 524.36 524.36
Skilled Laborer (Tinsmithman) 1.00 1.00 380.99 380.99
LABOR COST

Unskilled Laborer 2.00 1.00 293.96 587.92


4.00 1.00 4.00

Sub- Total 1,493.27


EQUIPMENT COST

Electric Drill 1.00 1.00 85.00 85.00


Riveter 1.00 1.00 85.00 85.00
Scaffoldings 1.00 lot 500.00 500.00

Sub- Total 670.00


Total Direct Cost 58,829.77
PREPARED BY: 12% of total DC OCM 7,059.57
12% of total DC CP 7,059.57
12% of (total DC+OCM+CP) VAT 8,753.87
Total Item Cost 81,702.78
Adjusted Unit Cost 659.64

You might also like