CASE STUDY 2 (DUW10022)

GROUP MEMBERS:
1. MUHAMMAD ALIF HAIKAL BIN MUHAM SAID (14DKA21F1023)

2. MUHAMMAD IRFAN BIN FADHZAIL AHMAD (14DKA21F1027)

3. ABDUL AQIF HAIKAL BIN AZISZE (14DKA21F1030)

1 INTRODUCTION -Location
-Background
-Designed of selected area
2 FIRE SAFETY AND PLANNING -Fire theory and classes of fire
-Fire control and passive protection method
at selected area
-Fire control and active protection method
at selected area
-Emergency evacuation plan and assembly
point at selected area
3 CONCLUSION -Management and level of fire safety of
selected area
-Recommendation to increase fire safety in
Polytechnics as a whole
1)-INTRODUCTION
LOCATION
-Civil engineering department
BACKGROUND&DESIGNED
-Four-story building
-Next to the commerce department

2)-FIRE SAFETY AND PLANNING


FIRE THEORY : A light and heat that occurs from chemical reaction when the three
elements of fire are present in proper conditions and proportions.
-This chain of elements is called as Fire Triangle.
-Take any one these factors away , and a fire will not occur or will be extinguished if it
was already burning.

CLASSES OF FIRE
CLASSES OF TYPES OF FIRE
FIRES
A Woods,paper,fabric,plastic,and most kind of trash
B Flammable liquids (for example, gasoline)
C Burning gases (for example , natural gas)
D Combusttible metals such as magnesium, potassium, titanium ,and
zirconium
E Fires involving potentially energized electrical equipment.
F Unsaturated cooking oils in well insulated cooking appliances
located in commercial kitchens.
2) FIRE CONTROL AND PASSIVE PROTECTION METHOD AT SELECTED
AREA Ground floor : EMERGENCY LANE

1st FLOOR : EMERGENCY LANE

2nd FLOOR: EMERGENCY LANE


3rd FLOOR: EMERGENCY LANE

4th FLOOR : EMERGENCY LANE


FIRE CONTROL AND ACTIVE PROTECTION METHOD AT SELECTED AREA
GROUND FLOOR

HOSE REEL FIREMAN SWITCH

1ST FLOOR

HOSE REEL FIRE ALARM EMERGRNCY BELL

2ND FLOOR
HOSE REEL FIRE ALARM EMERGENCY BELL

3RD FLOOR

HOSE REEL FIRE EXTINGUISHER AND FIRE ALARM BELL

4TH FLOOR

FIRE EXTENGUISHER HOSE REEL


AND FIRE ALARM
EMERGENCY EVACUATION PLAN AND ASSEMBLY POINT

GROUND FLOOR

EMERGENCY PLAN
ASSEMBLE POINT

1ST FLOOR

EMERGENCY PLAN
ASSEMBLY POINT

2ND FLOOR

EMERGENCY PLAN ASSEMBLY POINT


3RD FLOOR

EMERGENCY PLAN
ASSEMBLE POINT

4TH FLOOR

EMERGENCY PLAN ASSEMBLY POINT

3)CONCLUSION
MANAGEMENT AND LEVEL OF FIRE SAFETY OF SELECTED AREA
Management of civil engineering department is totally complete as specified in the fire
safety regulations.The level of fire safety also is at good stage because it has passive and
active control protection method.

RECOMMENDATION TO INCREASE FIRE SAFETY IN POLYTECHNICS AS A


WHOLE
Base on our opinion, we recommend to install fire sprinkler at every floor of the building.
Next , we recommend to install smoke detector at every floor ceiling to make more alert.
Lastly, fire blanket also are our recommendation because it can protect when a person got
burn.