Uncommon
Group Formation Members Common Lithology
Lithology
Drilling Problems Mitigations Guidance
Top Group
Seepage and Complete Losses ( Unconsolidate Sand).
- Use spud mud system with no control Fluid Loss Property till finish unconsolidated sand. Bit Balling.
- Maintaining high Bentonite content (30-35 ppb MBT) during Drilling unconsolidated sand. - Prepare Pill with 1-2 % by Volume of Drilling detergent with 4-5 % by volume of C-Mul
- Minimize Solids/cuttings loading by using SCE and Dump and dilute Technique (Solid (surfactant) pill.
Content Less than 1%). - Keep fine to medium nut plug on board
- Using high viscous sweeps ( Bentonetic Pill with LCM Pill). - Use center jet nozzle.
- Losses plan should be ready to use.
- Have enough mud chemicals and Drill/Fresh watert for mixing mud.
Tights Spots (Shale-Gumbo, Shale-5). Hole Cleaning (23", 20", 17.5" Hole).
- Mud system should be switched to KCL/Polymer system in stages while drilling before - Increase Flow rate for hole cleaning, if losses encountred , as min use MOF.
hitting Zeit FM. - YP Sholud less than 30 to compensate the slow annular velocity.
- It is Recommended to Maintain KCL/Polymer mud as following: Fluid loss will be - adjust and Monitor LSYP to clean cutting amount over lowside if hole angle over 35 deg.
1
controlled less than 10 cc/30 min) - Close monitoring of cutting amount over shale shaker, TQ/Drag.
( within Zeit. 3-5 % Glycol, 2-3 ppb Soltex and 3-5 % KCL. - Close monitoring for hole Cleaning Trends.
% - Try to minimize Direction Work in surface hole to avoid Hole Ledge. - Sweep hole with viscous pills.( PHP if needs).
Bit dull due to Sand Fieldspare .
& #
- Optimize down hole rotation with ROP To complete section as on run. Differential Sticking.
/ - Use low speed mud motor if Sand FieldSpare percentage is high. - Minimize connection time specially with running casing.
- Bit should be design for wear protection Features like (Shairtail Protection, MTR Hard - Minimize survey time (1.5 min static)
Facing and Log Bullets). - Try to avoid increase MWT in surface hole more than planned by dumping & dilute.
- It is recommended to Minimze Sliding percenatge in surface Hole if Sand FieldSpare - IF Stuck happen, displace hole to sea water WBM.
( % percentage is high. - Try to minimize Direction Work in surface hole to avoid Hole Ledge.
RAS MALAB GROUP
Differential Sticking.
- Min connection time (Rotate Pipe While Connection in sand).
Seepage and Complete Losses. - Minmize survey time (max. 1.5 min. static)
- Mud system should be loaded with 40-50 PPB LCM, as per Required - Try to avoid increase MWT, maintain m.wt as per program.
* ## # - IF Severe losses or complete loss, PBL Sub must be use to pump high Concentration - IF Stuck happen, U-Tube Technique, Pipe Lax Pill and Reduce MWT is a solutaion to
LCM pills. free.
- Losses plan should be ready to use. - Perform PPT to determine the Best Bridging Material Recipe.
- Maintain bridging materials as per program by performing PSD Test on daily basis.
- Keep good monitor on P/U weight after connection to see if hole is showing tendency to
differential sticking.
$#
Stuck. Tights (Salt Creeps).
- Keep mud salinity between 165 -170 K mg/l.( Undersaturattion to avoid salt sticking and
Shale Stability (Active Shale), Tights Spots, Stuck.
Gauge Hole).
' - Keep M.WT as per Program.
- Monitor Hole Condition and increase MWT Depend On hole Dictate.
- For Hole Stability and Hole Break out , the Wellbore Stability Study Must be initiated.
- Work on stuck or Tight spot as per freeing stuck best Practise.
- Perform Direction plan to be away for safe distance from Stressed Area ( Fault Zone).
- Enhance work on tight hole gradually and in steps and confirm free before and after each
- Monitor Hole Trends ( TQ& Drags).
step. Back ream
- OBM will be used as a solution for Shale inhibtion.
with full parameters (if required).
- Pore Pressure Engineer to be on board.( If Required)
- Contingency plan to pump Low salinity pill with weighted mud ahead and behind.
Differential Sticking.
- Mininimize connection time (Rotate Pipe While Connection).
Seepage and Complete Losses.
- IF Stuck happen, U-Tube Technique, Pipe Lax Pill and Reduce MWT is a solutaion to
- Stress cage sand may be required to Increase Rock Strengthing incase Sand Exsiting
!"# !"# free.
- Mud system should be loaded with 40-50 PPB LCM ( If Required)
- Maintain M.WT as per program, avoid increasing MWT.
- IF Severe losses or complete loss, PBL Sub must be use to pump high Concentration
- Perform PPT with Maximum Overbalance to determine the Best Bridging Material can be
LCM Pills.
used.
!"# !"# - Losses plan should be ready to use.
- Keep bridging materials concentration as per program by performing PSD Test.
- Incase OBM used, the oil Compressability Shall be Calcualted (Difference Between
- Minimize survey time (max. 1.5 min's static)
. # Surface and Down Hole Density).
- Keep good monitor on P/U weight after connection to see if hole is showing tendency to
/ $ ( differential sticking
- Minimize connection time specially with running casing.
Differential Sticking.
- Mininimize connection time (Rotate Pipe While Connection).
- IF Stuck happen, U-Tube Technique, Pipe Lax Pill and Reduce MWT is a solutaion to
Seepage and Complete Losses.
free.
- Stress cage sand may be required to Increase Rock Strengthing incase Sand Exsiting.
* - Maintain M.WT as per program, avoid increasing MWT.
- Mud system should be loaded with 40-50 PPB LCM (If Required).
- Perform PPT with Maximum Overbalance to determine the Best Bridging Material can be
- IF Severe losses or complete loss, PBL Sub must be use to pump high Concentration
used.
LCM Pills.
- Keep bridging materials concentration as per program by performing PSD Test.
- Losses plan should be ready to use.
- Minimize survey time (max. 1.5 min's static)
- Keep good monitor on P/U weight after connection to see if hole is showing tendency to
GHARANDAL GROUP
differential sticking
- Minimize connection time specially with running casing.
Differential Sticking.
NEZZAZAT
GROUP
Seepage and Complete Losses. - Minimize connection time (Rotate Pipe While Connection).
- Perform PPT with Maximum Overbalance to determine the Best Bridging Material. - IF Stuck happen, U-Tube Technique, Pipe Lax Pill and Reduce MWT is a solutaion to
0 - Keep and Maintain bridging materials as per program by performing PSD Test. free.
- Mud system should be loaded with 40-50 PPB LCM. - Perform PPTwith Maximum Overbalance to determine the Best Bridging Material can use
- IF Severe losses or complete loss, PBL Sub must be use to pump high Concentration to support Overbalance
LCM Pill. - Keep and Maintain bridging materials as per program by performing PSD Test.
- - Losses plan should be ready to use. - Minimize survey time (max. 1.5 min's static)
- Keep good monitor on P/U weight after connection to see if hole is showing tendency to
( ( - differential sticking
By M.Ragab