As of September 03 - September 09, 2022

Project Name: Lighting Facility at Mayor Joaquin F. Enriquez Jr. Memorial Sports Complex
Location: Baliwasan, Zamboanga City

P E R C E N T A G E A C C O M P L I S H M E N T
ITEM NO. DESCRIPTION % WEIGHT % COMPLETED TOTAL % % COMPLETED TOTAL %
SPL-1 Project Billboard/Signage 0.07% 100.00% 0.07% 100.00% 0.07%
SPL-2 Safety and Health 1.31% 100.00% 1.31% 100.00% 1.31%
SPL-3 Temporary Facility 0.16% 0.00% 0.00% 0.00% 0.00%
A.) Lighting Facility
SPL-4 Electrical Works 87.19% 23.89% 23.89%
Field Lights 63.98% 25.50% 16.31% 25.50% 16.31%
Line Materials 6.68% 25.50% 1.70% 25.50% 1.70%
Secondary Assembly 5.11% 24.00% 1.23% 24.00% 1.23%
Circuit Protection Assembly 5.45% 24.00% 1.31% 24.00% 1.31%
Distribution Transformer Line 8.01% 26.15% 2.09% 26.15% 2.09%
Metering Outfit 6.93% 18.00% 1.25% 18.00% 1.25%
B.) Construction of Power House
103 Layout and Excavation 0.02% 0.00% 0.00% 0.00% 0.00%
104 Embankment 0.01% 0.00% 0.00% 0.00% 0.00%
404 Reinforcing Steel Bars 0.29% 0.00% 0.00% 0.00% 0.00%
405 Structural Concrete 0.42% 0.00% 0.00% 0.00% 0.00%
SPL-5 Masonry Works 0.34% 0.00% 0.00% 0.00% 0.00%
SPL-6 Steel Works 0.51% 25.76% 0.13% 25.76% 0.13%
SPL-7 Roofing Works 0.82% 0.00% 0.00% 0.00% 0.00%
1032 Painting Works 0.15% 0.00% 0.00% 0.00% 0.00%
C.) Construction of Pedestal
SPL-8 Construction of Pedestal 8.72% 29.40% 2.56% 30.40% 2.65%
TOTAL PERCENTAGE 100.00% 27.97% 28.06%
LIGHTING FACILITY AT GRANDSTAND PROJECT
100.00%

95.00%

90.00%

85.00%

80.00%

75.00%

70.00%

65.00%

60.00%

55.00%

50.00%

45.00%

40.00%

35.00%

30.00%

25.00%

20.00%

15.00%
W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16 W-17 W-18 W-19 W-20 W-21 W-22 W-23 W-24 W-25
MAY JUNE JULY AUGUST SEPTEMBER OCTOBER DECEMBER
Weekly Planned 70.70% 71.51% 72.88% 74.10% 75.15% 76.55% 77.77% 78.72% 80.03% 81.43% 82.91% 84.13% 85.61% 86.66% 87.62% 88.93% 90.06% 91.37% 92.59% 94.16% 95.64% 96.86% 97.99% 98.95% 100.00%
Weekly Planned Increase 1.22% 1.22% 1.37% 1.22% 1.05% 1.40% 1.22% 0.95% 1.31% 1.40% 1.48% 1.22% 1.48% 1.05% 0.96% 1.31% 1.13% 1.31% 1.22% 1.57% 1.48% 1.22% 1.13% 0.96% 1.05%
Weekly Actual 17.22% 19.18% 21.97% 23.43% 24.67% 25.98% 27.01% 27.76% 27.76% 27.76% 27.76% 27.76% 27.76% 27.76% 27.94% 27.97% 28.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Weekly Actual Increase 0.86% 1.96% 2.79% 1.46% 1.24% 1.31% 1.03% 0.75% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Accumulative Planned 70.70% 71.51% 72.88% 74.10% 75.15% 76.55% 77.77% 78.72% 80.03% 81.43% 82.91% 84.13% 85.61% 86.66% 87.62% 88.93% 90.06% 91.37% 92.59% 94.16% 95.64% 96.86% 97.99% 98.95% 100.00%
Accumulative Actual 17.22% 19.18% 21.97% 23.43% 24.67% 25.98% 27.01% 27.76% 27.76% 27.76% 27.76% 27.76% 27.76% 27.76% 27.94% 27.97% 28.06%