Professional Documents
Culture Documents
MST-0010-00 For Pavement Road Works
MST-0010-00 For Pavement Road Works
MST-0010-00 For Pavement Road Works
Contractor’s Review:
Description Discipline Engineer QA/QC OSH Project Manager
Name Bashar Qabbany Michael Macalino Mohamed Abdullah Tarif Elamine
Designation Project Engineer QA/QC Manager OSH Team Leader Project Manager
Signature
Date
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 2 of 13
Engineer’s Comments
Signature
Date
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 3 of 13
Table of Contents
Table of Contents...............................................................................................................................................3
1. Purpose:........................................................................................................................................................4
2. Scope:............................................................................................................................................................4
3. Legislation and code of practice:................................................................................................................4
4. References:...................................................................................................................................................4
5. Definitions:...................................................................................................................................................4
6. Resources:.....................................................................................................................................................5
7. Safety Precautions:......................................................................................................................................7
8. Detailed Construction Sequence (Methodology):......................................................................................7
9. Inspection and Testing...............................................................................................................................12
10. Related Forms:.........................................................................................................................................13
11. Attachments..............................................................................................................................................13
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 4 of 13
1. Purpose:
The purpose of method statement is to define the proper sequence of work and inspection activities
related to construction of pavement roadworks. The aforesaid activities are in accordance with
requirements of the project and authorities’ specification and approved shop drawings.
2. Scope:
This statement covers the various steps involved for asphalt road works.
2.1 All prior activities
2.2 Survey works
2.3 Formation preparation
2.4 Subgrade
2.5 Aggregate sub base course
2.6 Aggregate base course
2.7 Wet Mix Macadam Road Base
2.8 Prime coat
2.9 Asphalt base course
2.10 Tack coat
2.11 Asphalt Wearing course
4. References:
5. Definitions:
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 5 of 13
6. Resources:
6.1. Materials and their Approval
1. Embankment material
2. Subgrade
3. Aggregate sub base course
4. Aggregate base course
5. Wet Mix Macadam road base
6. Prime coat
7. Asphalt base course
8. Tack coat
9. Asphalt wearing course
All material shall be approved by Employer/Engineer prior to commencement of the work.
6.4. Equipment
1. Survey Equipment 12. Milling / Cold-road profile Machine
2. Graders 13. Tipper Truck
3. Dozers 14. Compressor
4. Excavator 15. Saw Cutting Machine
5. Water Tanks 16. Asphalt Paver machines
6. Dump Trucks 17. Asphalt batching plant
7. Wheel Loader 18. Compactors
8. Double drum roller 19. Jack hammer
9. Pneumatic Tire roller 20. Small hand tools as necessary
10. Vibrator roller 21. Asphalt saw cutter
11. Steel roller (Tandem) 22. Safety PPE
All Heavy equipments should have valid third party certificates prior to commencement of the
work.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 6 of 13
2. Site Engineer
3. Safety Officers
4. Equipment operators
5. Labors
The person involved in execution of works, their roles are clearly defined but not limited to the
following:
A. Project Manager
Overall site management, quality & safety;
Full authority and overall responsibility to manage, supervise and control the works.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 7 of 13
7. Safety Precautions:
All PPEs will be worn at site after proper Safety and Daily task briefings by respective
supervisors.
Usage of sharp tools, and removal of heavy objects by crane/ boom loader etc., appropriate
lifting equipment, certified equipment etc.
All site heavy earth moving vehicles fitted with audible reverse alarm/ flash lights/a flag
man guide in case of required operation move around close vicinity of high traffic
movement.
Gas cutting while removal of items will be supported with HOT work Permit.
Any excavation required relevant approval from respective authorities etc.
Special care to be taken while carrying out hand excavation if required removal of
structures/ Obstructions–Approval copy of NOC must be available.
Salvaged items will be kept well separated from debris. Waste items will be segregated and
stored separately and decided for appropriate disposal as per waste management procedure.
Fire precautionary measures, instructions, signs will be displayed as required at site.
All site personnel will receive necessary information about emergency situation and practice
mock drill in case of potential emergency situation like fire/ sand storm/rain/road traffic
incidents/other potential emergencies.
Proper barricading and appropriate hazard signs will be displayed to inform the site
personnel/ road users/ and visitors to the site.
After removal of fence which prevents camels from crossing into roads, additional safety
measures shall be placed well away from such location to prevent camel crossing into such
areas.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 8 of 13
8.2 Methodology:
a. Install survey stakes and demarking the limits and extents of asphalt road works.
b. Dewatering shall be done as per approved method statement (If required).
8.2.4 Embankment
a. Prepare the Embankment layer line, levels and grades as required in approved shop drawings.
b. Spread Embankment layers in 150mm maximum compacted depth.
c. The Embankment material for load bearing area shall be CBR more than 20% .
d. Compact embankment layer to minimum of 95% MDD as per General specification vol.3.A
clause s section 2.5.2.2
8.2.5 Improved Subgrade preparation
a. Prepare the sub-grade layer line, levels and grades as required in approved shop drawings.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 9 of 13
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 10 of 13
a. Site laboratory shall take sample from stock pile of Wet mix macadam road base material and
check that minimum CBR value of 80% at 98% of MDD.
b. Wet mix macadam road base shall be spread on the approved layer of sub base course
layer .Each layer must not exceed 150 mm compacted thicknesses.
c. Care shall be taken while spreading the wet mix macadam road base to avoid segregation .The
segregated material shall be remixed to uniform gradation.
d. The moisture content of the wet mix macadam road material shall be adjusted prior to
compaction, by watering with approved sprinkler trucks or by drying out, as directed by the
Engineer, to that required to obtain the specified density for wet mix macadam road base of 98%
MDD.
e. Hauling trucks for material shall be covered during transportation.
f. Moisturizing of subgrade surface, level control, rolling immediately after spreading, minimum
tolerance from required elevation shall be implemented during construction activities.
g. Field density test shall be carried out as per attached Inspection and Test Plan and project
specification.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 11 of 13
m. Road density and pavement thickness of asphalt base course shall be determined by site
laboratory from asphalt core samples and compacted density shall be minimum 97% of
marshal density.
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 12 of 13
to roll along this line, shifting its position gradually across the joint, in 150 to 200 mm
increments, until the joint has been rolled with the entire width of the roller wheel. Rolling
shall be continued until a thoroughly compacted, neat joint is obtained more than 150 mm of
the rear rolling wheel rides on the edge of the joint.
c. Transverse joints in succeeding layers shall be offset at least 2 m.
9.1 Inspection and Test Plan for asphalt road works shall be conducted in reference to attached ITP
Ref. # 54350-00SIT-GE-BHG119-CIV-ITP-0010-00 ITP and in conjunction with relevant
approved ITP’s
Ref No: 54350-00SIT-GE-BHG119-CRW-MST-0010-00 Method Statement for Pavement Road Works Page 13 of 13
11. Attachments