Professional Documents
Culture Documents
Supply, Delivery & Testing and Installation of Two Chillers and One Detention & Retention Cold Room at Nomotio Slaughter House, Samburu County
Supply, Delivery & Testing and Installation of Two Chillers and One Detention & Retention Cold Room at Nomotio Slaughter House, Samburu County
_____________________________________________________________________
OPEN TENDER
FOR
_____________________________________________________________________
COUNTY SECRETARY
MARALAL
Em ail: info@samburu.go.ke/procurement@samburu.go.ke
ABBREVIATIONS AND ACRONYMS
PE Procuring Entity
PM Project Manager
S OR Statement of Requirements
SP Service Provider
ii
NEWSPAPER ADVERTISEMENT
iii
REPUBLIC OF KENYA SAMBURU COUNTY GOVERNMENT
Samburu County Government has obtained a Grant from the European Union, through the
Ministry of Devolution and ASAL, under the EU-IDEAS programme for the Establishment of
Nomotio Abattoir at Nomotio LIC, Samburu County. The Samburu County Government invites
interested and eligible bidders for the S up p ly, Deliver y & Installation, Testing and
C ommissioning of Two C hillers and One Detention & Retention C old Ro om at Nomotio
A battoir . Interested bidders may download the bid documents from the Samburu County
Government website, www.samburu.go.ke/tenders or www.tenders.go.ke free of charge . This
bid is open to both local and national bidders.
The interested bidders are also advised to assemble at the Supply Chain Management Office
located at County Treasury Building, Samburu County Headquarters on Wed nesd ay 10 t h
November 20 21 10 :0 0 A M E ast A fr ic an Time, for a site visit. A visit certificate will be issued.
The duly completed bids should be enclosed in plain sealed envelopes clearly marked with
Tender Number and Tender Name and deposited in the tender box situated at the entrance of
Samburu County Headquarters offices and be addressed to:
C OUNTY S E C RE TA RY
S A MB URU C OUNTY G OV E RNME NT
P.O. B OX 3-20 60 0
MA RA LA L
Kenya
So as to be received on or before …19 t h November 20 21 at 10 .0 0 A M East African time.
Opening of bids will take place immediately thereafter at Procurement Offices Samburu County
Headquarters building in the presence of bidders or their representatives who choose to attend.
Successful bidders will be selected in accordance with evaluation criteria and terms and
conditions set out in the bidding documents. For any additional information, please contact the
County Secretary on email: info@samburu.go.ke or procurement@samburu.go.ke.
…………………………………………………..
A g . HE A D OF S UPPLY C HA IN-MA NA G E ME NT
FOR: Ag. CHIEF OFFICER-AGRICULTURE, LIVESTOCK & FISHERIES
iv
TABLE OF CONTENTS
A. Introduction .................................................................................5
1. Scope of Tender ................................................................................................ 5
2. Source of Funds ................................................................................................. 5
3. Eligible Tenderers .............................................................................................. 5
4. One Tender per Tend erer .................................................................................. 7
5. Alternative Tenders by Tenderer s........................................................................ 7
6. Cost of Tendering .............................................................................................. 7
7. Site Visit and Pre-Tender Meeting ....................................................................... 8
B. Tendering Documents ........................................................................8
8. Content of Tendering Documents ....................................................................... 8
9. Clarification of Tendering Documents ............................................................... 10
10. Amendments of the Tendering Documents ........................................................ 10
C. Preparation of Tenders.................................................................. 10
11. Language of Tend er ......................................................................................... 10
12. Documents Constituting the Tend er ................................................................... 11
13. Documents Establishing Eligibility and Qualifications of the Tend erer .................... 11
1. 11
14. Lots Package.....................................................................................................13
15. Form of Tender ................................................................................................13
16. Tender Pric es....................................................................................................13
17. Tender Currencies.............................................................................................13
18. Tender Validity Period ......................................................................................14
19. Tender Security and Tender Securing Declar ation ................................................14
20. Format and Signing of Tender ...........................................................................16
D. Submission of Tenders................................................................... 16
21. Sealing and Marking of Tender s .........................................................................16
22. Deadline for Submission of Tenders....................................................................17
23. Late Tenders.....................................................................................................17
24. Modific ation, Substitution and Withdrawal of Tender s ........................................17
E. Opening and Evaluation of Tenders .................................................... 18
25. Opening of Tenders ..........................................................................................18
26. Confidentiality ................................................................................................ 20
27. Clarification of Tenders .................................................................................... 20
v
28. Preliminary Examination of Tend ers .................................................................. 20
29. Correction of Errors ..........................................................................................21
30. Conversion to Single Currency .......................................................................... 22
31. Comparison of Tenders .................................................................................... 22
32. National Preference ......................................................................................... 23
33. Determination of the Lowest Evaluated Tender .................................................. 23
34. Post-qualification of Tenderer ........................................................................... 23
F. Award of Contract ..........................................................................24
35. Criteria of Award ............................................................................................ 24
36. Clarifications ................................................................................................... 24
37. Procuring Entity‘s Right to Accept any Tender and to Reject any or all Tender s .... 25
38. Procuring Entities Right to Vary Quantities at the Time of Award ........................ 25
39. Notification of Award ...................................................................................... 25
40. Signing of Contract .......................................................................................... 26
41. Performance S ecurity ....................................................................................... 26
42. Advance Payment............................................................................................ 27
43. Adjudicator ..................................................................................................... 27
G. Review of Procurement Decisions ....................................................27
44. Right to Review .............................................................................................. 28
45. Time Limit on Review ...................................................................................... 28
46. Submission of Applications for Review by the Public Procurement Administrative
Review Board ......................................................................................................... 28
47. Decision by the Public Procurement Administrative Review Board ....................... 29
48. Appeal on the decision of the Review Board ..................................................... 29
A. General .....................................................................................42
1. Definitions ...................................................................................................... 42
2. Interpretation.................................................................................................. 43
vi
3. Language, Law, Fraud and Corruption............................................................... 44
4. Confidentiality ................................................................................................ 45
5. Project Manager‘s Decisions.............................................................................. 46
6. Deleg ation ...................................................................................................... 46
7. Communications ............................................................................................. 46
8. Subcontracting ................................................................................................. 46
9. Other Contractors ........................................................................................... 46
10. Personnel ........................................................................................................ 46
11. Procuring Entity‘s and Contractor‘s Risks ........................................................... 46
12. Procuring Entity‘s Risks..................................................................................... 46
13. Contractor‘s Risks ............................................................................................ 47
14. Insurance ........................................................................................................ 47
15. Site Investigation Reports ................................................................................. 47
16. Queries about the Contract Data Sheet .............................................................. 47
17. Contractor to Construct the Works ................................................................... 48
18. Commencement and Completion ..................................................................... 48
19. Approval by the Project Manager ..................................................................... 48
20. Protection of the E nvironment.......................................................................... 48
21. Labour Laws.................................................................................................... 48
22. Health and Safety ............................................................................................ 48
23. Discoveries ...................................................................................................... 49
24. Possession of the Site........................................................................................ 49
25. Access to the S ite ............................................................................................. 49
26. Instructions, Inspections and Audits ................................................................... 49
27. Disputes .......................................................................................................... 49
28. Procedure for Disputes ..................................................................................... 49
29. Replacement of Adjudic ator ............................................................................. 49
B. Time Control.................................................................................50
30. Programme ..................................................................................................... 50
31. Extension of the Intended Completion Date ...................................................... 50
32. Acceleration .....................................................................................................51
33. Delays Ordered by the Project Manag er .............................................................51
34. Manag ement Meetings......................................................................................51
35. Early Warning ..................................................................................................51
C. Quality Control........................................................................... 51
36. Identifying Defects ............................................................................................51
37. Tests ................................................................................................................51
38. Correction of Defects ....................................................................................... 52
39. Uncorrected Defects......................................................................................... 52
D. Cost Control...............................................................................52
40. Bill of Quantities.............................................................................................. 52
41. Chang es in the Quantities ................................................................................. 52
42. Variations ....................................................................................................... 52
vii
43. Payments for Variations ................................................................................... 52
44. Cash Flow Forecasts......................................................................................... 53
45. Payment Certificates ........................................................................................ 53
46. Payments ........................................................................................................ 53
47. Compensation Events....................................................................................... 54
48. Taxes .............................................................................................................. 55
49. Currencies ....................................................................................................... 55
50. Price Adjustment ............................................................................................. 55
51. Retention........................................................................................................ 57
52. Liquidated Damages......................................................................................... 57
53. Bonus ............................................................................................................. 58
54. Advance Payment............................................................................................ 58
55. Performance S ecurities ..................................................................................... 58
56. Day works ...................................................................................................... 58
57. Cost of Repairs ................................................................................................ 59
E. Finishing the Contract ......................................................................59
58. Completion Certific ate ..................................................................................... 59
59. Taking Over .................................................................................................... 59
60. Final Account .................................................................................................. 59
61. Operating and Maintenanc e Manuals ................................................................ 59
62. Termination .................................................................................................... 59
63. Payment upon Termination.............................................................................. 60
64. Property ..........................................................................................................61
65. Release from Performance .................................................................................61
66. Suspension of Financing ....................................................................................61
A. General .....................................................................................63
B. Time Control.................................................................................64
C. Quality Control...........................................................................65
D. Cost Control...............................................................................65
E. Finishing the Contract ......................................................................66
viii
2. Material tests................................................................................................... 69
3. Manufactured Plant and Equipment — Work Tests............................................. 70
4. Pressure Testing ............................................................................................... 70
I. Colour Coding ...............................................................................70
J. Welding .......................................................................................70
1. Preparation ..................................................................................................... 70
2. Method .......................................................................................................... 70
3. Weld ing Code and Construction ........................................................................71
4. Weld ers Qualific ations ......................................................................................71
ix
C. BILLS OF QUANTITIES..................................................................83
1. BILLSNo. 1: PRICING OF PRE LIMINARIES ITEMS ............................................... 83
2. BILL NO. 2: REFRIGERATION WORKS ............................................................. 87
3. BILL NO.3-FREEZER ROOM ( NOT TO BE QUOTED) .......................................102
4. BILL NO 4. SUSPECT COLD ROO ....................................................................109
5. SCHEDULE OF UNIT RATES............................................................................ 115
x
SECTION I: INVITATION FOR TENDERS (IFT)
1
S UPPLY, DE LIVERY & INSTALLATION, TESTING A ND COMMISSIONING OF TWO C HILLERS
A ND ONE DE TE NTION & RE TE NTION C OLD ROOM A T NOMOTIO A B A TTOIR IN
S A MB URU C OUNTY
1.1. The County Government of Samburu, here and in the subsequent sections referred
to as the procuring entity, in partnership with European Union (EU) now invites
sealed Tenders from eligible candidates for the PROPOS E D S UPPLY,
INS TALLATION, TESTING A ND C OMMISSIONING OF TWO C HILLE RS A ND ONE
DE TENTION & RETENTION C OLD ROOM A T NOMOTIO S LA UG HTE R HOUS E ,
S A MB URU C OUNTY. The tender is National Open Tender;
1.2. Interested eligible candidates may obtain further information and inspect Tender
Documents and the Design Drawings from the Supply Chain Management offices,
Located at the County Government of Samburu, county treasury building during
normal working hours or they may download the same from the county
website Samburu.go.ke/Tenders and the national government tenders web-portal
https://tenders.go.ke free of charge;
1.3. Prices quoted should be net inclusive of all taxes, must be in Kenya shillings and
shall remain valid for 90 days from the closing date of tender;
1.5. Completed tender documents are to be enclosed in plain sealed envelopes marked
with tender name and reference number as per Instructions to Tenders and
addressed to:
C OUNTY S E C RE TA RY
S A MB URU C OUNTY G OV E RNME NT
P.O. B OX 3-20 60 0
MA RA LA L
Kenya
1.6. To be deposited in the tender box situated at the Supply Chain Management
offices, County Headquarters ground floor so as to be received on or before
F r i d a y , 1 9 t h N o v e m b e r 2 0 2 1 , 10 .0 0 a.m. Tenders will be opened promptly
thereafter in the presence of the tend er er s or their representatives who choose to
attend.
2 |Page
1.7. Late Tenders shall not be accepted
3 |Page
SECTION II: INSTRUCTIONS TO TENDERERS (ITT)
4 |Page
A. Introduction
1. S c ope of 1.1 The Procuring Entity indicated in the Tend er Data S heet (TDS) invites
Tend er Tenders for the construction of works as specified in the Tend er Data
S heet and Sections VI (Technical Specifications) and VII (Drawings).
1.3 The objectives of the works are listed in the Tend er Data S heet. These
are mandatory requirements. Any subsequent detail is offered to
support these objectives and must not be used to dilute their
importance.
2. S ource of 2.1 The Government of Kenya has set aside funds for the use of the
Fund s Procuring Entity named in the Tend er Data S heet during the Financial
Year indicated in the Tend er Data S heet. It is intended that part of the
proceeds of the funds will be applied to cover eligible payments
under the contract for the works as described in the Tend er Data
S heet.
3.2 The Invitation for Tenders is open to all suppliers as defined in the
Public Procurement and Disposal Act, 2015 and the Public
Procurement and Disposal Regulations, 2006 except as provided
hereinafter.
5 |Page
3.4 A Tenderer shall not have a conflict of interest. All Tenderers found to
have a conflict of interest shall be disqualified. A Tenderer may be
considered to have a conflict of interest with one or more parties in
this Tendering process, if they:
6 |Page
4. One Tender 4.1 A firm shall submit only one Tender, in the same Tendering process,
p er either individually as a Tenderer or as a partner in a joint venture
Tend erer pursuant to ITT Clause 5.
5. A lternative 5.1 Tenderers shall submit offers that comply with the requirements of the
Tend ers by Tendering documents, including the basic Tenderer‘s technical design
Tend erers as indicated in the specifications and Drawings and Bill of Quantities.
Alternatives will not be considered, unless specifically allowed for in
the Tend er Data S heet. If so allowed, sub-Clause 5.2 and 5.3 shall
govern.
6. C ost of 6.1 The Tenderer shall bear all costs associated with the preparation and
Tend ering submission of its Tender, and the Procuring Entity shall in no case be
responsible or liable for those costs, regardless of the conduct or
outcome of the Tendering process.
7 |Page
7. S ite V isit 7.1 The Tenderer, at the Tenderer‘s own responsibility and risk, is advised
and Pre- to visit and examine the Site of Works and its surroundings and obtain
Tend er all information that may be necessary for preparing the Tender and
Meeting entering into a contract for construction of the Works. The costs of
visiting the Site shall be at the Tenderer‘s own expense.
7.2 The Procuring Entity may conduct a site visit and a pre-Tender
meeting. The purpose of the pre-Tender meeting will be to clarify
issues and to answer questions on any matter that may be raised at
that stage.
7.5 Minutes of the pre-Tender meeting, including the text of the questions
raised and the responses given together with any responses prepared
after the pre-Tender meeting will be transmitted within the time
stated in the Tend er Data S heet to all purchasers of the Tendering
documents. Any modification of the Tendering documents listed in
sub-Clause 8.1 that may become necessary as a result of the pre-
Tender meeting shall be made by the Procuring Entity exclusively
through the issue of an Addendum pursuant to ITT sub Clause 10.2
and not through the minutes of the pre-Tender meeting.
7.6 Non attendance during the site visit or pre-Tender meeting will not
be a cause for disqualification of a Tenderer unless specified to the
contrary in the Tend er Data S heet.
B. Tendering Documents
8. C ontent of 8.1 The works required, Tendering procedures, and contract terms are
Tend ering prescribed in the Tendering Documents. In addition to the Section I
Doc uments Invitation for Tenders, Tendering documents which should be read
in conjunction with any addenda issued in accordance with ITT sub
Clause 10.2 include:
8 |Page
Section III Tender Data Sheet
Section IV General Conditions of Contract
Section V Contract Data Sheet
Section VI Specifications
Section VII Drawings
Section VIII Bill of Quantities
Section IX Forms of Tender
Form of Tender
Appendix to Tender
Confidential Business Questionnaire
Integrity Declaration
Letter of Acceptance
Form of Contract Agreement
Section X Forms of Security
Tender Security Form
Tender Securing Declaration
Performance Bank or Insurance Guarantee
Advance Payment Guarantee
Section XI Form RB 1 Application to Public Procurement
Administrative Review Board
8.3 The Invitation for Tenders (Section I) issued by the Procuring Entity
is not part of the Tendering Documents and is included for reference
purposes only. In case of discrepancies between the Invitation for
Tenders and the Tendering Documents listed in sub-Clause 8.1
above, the said Tendering Documents will take precedence.
8.4 The Procuring Entity is not responsible for the completeness of the
Tendering Documents and their addenda, if they were not obtained
directly from the authorized staff of the Procuring Entity.
9 |Page
9. C lar ification 9.1 A prospective Tenderer requiring any clarification of the Tendering
of Tendering documents may notify the Procuring Entity in writing, e-mail or
Doc uments facsimile at the Procuring Entity‘s address indicated in the Tend er
Data S heet.
9. 2 The Procuring Entity will within the period stated in the Tend er
Data S heet respond in writing to any request for clarification
provided that such request is received no later than the period
indicated in the Tend er Data S heet prior to the deadline for the
submission of Tenders prescribed in sub-Clause 22.1.
10. A mendments 10 .1 Before the deadline for submission of Tenders, the Procuring Entity
of the may, for any reason, whether at its own initiative or in response to
Tend ering a clarification requested by a prospective Tenderer, modify the
Doc uments Tendering documents by issuing addenda.
C. Preparation of Tenders
11. Lang uage of 11.1 The Tender, and all correspondence and documents related to
Tend er the Tender exchanged by the Tenderer and the Procuring Entity
shall be written in the Tender language stipulated in the Tend er
Data S heet. Supporting documents and printed literature
furnished by the Tenderer may be in another language provided
they are accompanied by an accurate translation of the relevant
passages in the above stated language, in which case, for
10 | P a g e
purposes of interpretation of the Tender, the translation shall
prevail.
12. Doc uments 12.1 The Tender submitted by the Tenderer shall consist of the
C onstituting the following components:
Tend er
13. Doc uments 13.1 Pursuant to ITT Clause 13, the Tenderer shall furnish, as part of
E stablishing its Tender, documents establishing the Tenderer‘s eligibility to
E ligibility and Tender and its qualifications to perform the contract if its
Qualifications of Tender is accepted.
the Tenderer
11 | P a g e
13.3 If the Procuring Entity has not undertaken pre-qualification of
potential Tenderers, to qualify for award of the contract,
Tenderers shall meet the minimum qualifying criteria specified in
the Tender Data Sheet:
The Tender shall include all the information listed in the Tender
Data Sheet pursuant to sub-Clause 13.3 above for each joint
venture partner;
12 | P a g e
14. Lots Package 14.1 When Tendering for more than one contract under the lots
arrangements, the Tenderer must provide evidence that it meets
or exceeds the sum of all the individual requirements for the lots
being tendered in regard to:
14.2 In case the Tenderer fail to fully meet any of these criteria, it
may be qualified only for those lots for which the Tenderer
meets the above requirement.
15. Form of Tender 15.1 The Tenderer shall fill the Form of Tender furnished in the
Tendering Documents. The Form of Tender must be completed
without any alterations to its format and no substitute shall be
accepted.
16. Tend er Prices 16.1 The Contract shall be for the whole Works, as described in sub-
Clause 1.1, based on the priced Bill of Quantities submitted by
the Tenderer.
16.2 The Tenderer shall fill in rates and prices for all items of the
Works described in the Bill of Quantities. Items for which no
rate or price is entered by the Tenderer will not be paid for by
the Procuring Entity when executed and shall be deemed
covered by the other rates and prices in the Bill of quantities.
16.3 All duties, taxes and other levies payable by the Contractor
under the Contract, or for any other cause, as of the date 15
days prior to the deadline for submission of Tenders, shall be
included in the rates, prices and total Tender price submitted by
the Tenderer.
16.4 The rates and prices quoted by the Tenderer shall be subject to
adjustment during the performance of the Contract if provided
for in the Tend er Data S heet and the provisions of the
Conditions of Contract. The Tenderer shall submit with the
Tender all the information required under the C ontr ac t Data
S heet.
17. Tend er 17.1 The unit rates and prices shall be quoted by the Tenderer in the
C urrencies currency as specified in the Tend er Data S heet.
13 | P a g e
deadline for submission of Tenders. These exchange rates shall
apply for all payments so that no exchange risk will be borne by
the Tenderer. In any case, payments will be computed using the
rates quoted in the Tender.
18. Tend er V alidity 18.1 Tenders shall remain valid for the period specified in the Tend er
Period Data S heet after the Tender submission deadline prescribed by
the Procuring Entity, pursuant to ITT Clause 22. A Tender valid
for a shorter period shall be rejected by the Procuring Entity as
non- responsive.
19. Tend er S ecurity 19.1 Pursuant to ITT Clause 12, where required in the Tend er Data
and Tender S heet, the Tenderer shall furnish as part of its Tender, a Tender
S ec uring Security in original form and in the amount and currency
Dec laration specified in the Tend er Data S heet .
A Tender Securing Declaration as specified in the Tend er Data
S heet in the format provided in section X shall be provided as a
mandatory requirement.
a) Cash;
14 | P a g e
b) A Bank Guarantee;
c) An Insurance Bond issued by an insurance firm approved by
the PPOA located in Kenya;
d) An irrevocable letter of credit issued by a reputable bank.
19.4 The Tender Security shall be in accordance with the Form of the
Tender Security included in Section X or another form approved
by the Procuring Entity prior to the Tender submission.
19.8 The Tender Security shall be forfeited and the Tender Securing
Declaration executed if the Tenderer:
15 | P a g e
a) If the Tenderer withdraws its Tender, except as provided in
ITT sub-Clauses 18.2 and 29.2; or
20. Format and 20 .1 The Tenderer shall prepare one original of the documents
S ig ning of comprising the Tender as described in ITT Clause 12 of these
Tend er Instructions to Tenderers, with the Form of Tender, and clearly
marked ―ORIG INA L‖. In addition, the Tenderer shall submit
copies of the Tender, in the number specified in the Tend er
Data S heet, and clearly marked as ―C OPIE S ‖. In the event of
discrepancy between them, the original shall prevail.
D. Submission of Tenders
21. S ealing and 21.1 The Tenderer shall seal the original and each copy of the Tender
Mark ing of in separate envelopes, duly marking the envelopes as
Tend ers ―ORIG INA L‖ and ―C OPY‖. The envelopes shall then be sealed in
an outer envelope securely sealed in such a manner that opening
and resealing cannot be achieved undetected.
16 | P a g e
a) Be addressed to the Procuring Entity at the address given in
the Tend er Data S heet; and
b) Bear the Project name indicated in the Tend er Data S heet, the
Invitation for Tenders (IFB) title and number indicated in the
Tend er Data S heet, and a statement: ―DO NOT OPE N
B E FORE ,‖ to be completed with the time and the date
specified in the Tend er Data S heet, pursuant to ITT sub-Clause
22.1.
21.4 If the outer envelope is not sealed and marked as required by ITT
sub clause 21.2, the Procuring Entity shall assume no responsibility
for misplacement or premature opening of the Tender.
22. Dead line for 22.1 Tenders shall be received by the Procuring Entity at the address
S ubmission of specified under ITT sub-Clause 21.2 no later than the date and
Tend ers time specified in the Tend er Data S heet.
22.3 The extension of the deadline for submission of Tenders shall not
be made later than the period specified in the Tend er Data S heet
before the expiry of the original deadline.
23. Late Tenders 23.1 The Procuring Entity shall not consider for evaluation any Tender
that arrives after the deadline for submission of Tenders, in
accordance with ITT Clause 22.
23.2 Any Tender received by the Procuring Entity after the deadline
for submission of Tenders shall be declared late, rejected and
returned unopened to the Tenderer
24. Mod ification, 24.1 A Tenderer may modify or substitute or withdraw its Tender
17 | P a g e
S ubstitution after it has been submitted, provided that written notice of the
and modification, including substitution or withdrawal of the Tender,
Withdrawal of is received by the Procuring Entity prior to the deadline
Tend ers prescribed for submission of Tenders prescribed under ITT sub-
Clause 22.1.
24.5 Tenderers may only offer discounts to, or otherwise modify the
prices of their Tenders by submitting Tender modifications in
accordance with this Clause, or included in the original Tender
submission.
25. Op ening of 25.1 The Procuring Entity will open all Tenders including
Tend ers modifications, substitution or withdraw notices made pursuant to
ITT Clause 24, in public, in the presence of Tenderers or their
representatives who choose to attend and other parties with
legitimate interest and Tender proceedings, at the place on the
date and at time specified in the Tend er Data S heet. The
Tenderers‘ representatives who are present shall sign a register as
proof of their attendance.
18 | P a g e
has been submitted pursuant to ITT Clause 24 shall not be
opened but returned to the Tenderer. If the withdrawal
envelope does not contain a copy of the ―Power of Attorney‖
confirming the signature as a person duly authorized to sign on
behalf of the Tenderer, the corresponding Tender will be
opened. Subsequently, all envelopes marked ―MODIFIC A TION‖
shall be opened and the submissions therein read out in
appropriate detail. Thereafter all envelopes marked or
―S UB S TITUTION‖ opened and the submissions therein read out
in appropriate detail.
25.4 Tenders or modifications that are not opened and not read out
at Tender opening shall not be considered further for evaluation,
irrespective of the circumstances. In particular, any discount
offered by a Tenderer which is not read out at Tender opening
shall not be considered further.
19 | P a g e
signature on the record shall not invalidate the contents and
affect the record.
27.2 The request for clarification and the response shall be in writing.
No change in the prices or substance of the Tender shall be
sought, offered, or permitted except to confirm the correction of
arithmetic errors discovered by the Procuring Entity in the
evaluation of Tenders in accordance with ITT Clause 29.
27.3 From the time of Tender opening to the time of Contract award
if any Tenderer wishes to contact the Procuring Entity on any
matter related to the Tender it should do so in writing.
28. Preliminary 28.1 Prior to the detailed evaluation of Tenders, the Procuring Entity
E x amination of will determine whether:
Tend ers
20 | P a g e
b) Any Tender Security submitted is in the required form,
amount and validity period;
c) The Tender has been signed by the person lawfully
authorized to do so;
d) The required number of copies of the Tender have been
submitted;
e) The Tender is valid for the period required;
f) All required documents and information have been
submitted; and
g) Any required samples have been submitted.
28.2 The Procuring Entity will confirm that the documents and
information specified under ITT Clause 12 and ITT Clause 13
have been provided in the Tender. If any of these documents or
information is missing, or is not provided in accordance with the
Instructions to Tenderers, the Tender shall be rejected.
21 | P a g e
a) If there is a discrepancy between unit prices and the total
price that is obtained by multiplying the unit price and
quantity, the unit price shall prevail, and the total price shall
be corrected, unless in the opinion of the Procuring Entity
there is an obvious misplacement of the decimal point in the
unit price, in which the total price as quoted shall govern and
the unit price shall be corrected;
30. C onversion to 30 .1 To facilitate the evaluation and comparison, the Procuring Entity
S ingle C urrency will convert all Tender prices expressed in the amounts in various
currencies in which the Tender prices are payable to Kenya
Shillings at the selling exchange rate established for similar
transactions by the Central Bank of Kenya ruling on the date
specified in the Tend er Data S heet.
31. C omparison of 31.1 The Procuring Entity shall evaluate and compare only the
Tend ers Tenders determined to be substantially responsive in accordance
with ITT Clause 28.
31.2 In evaluating the Tenders, the Procuring Entity will determine for
each Tender the evaluated Tender price by adjusting the Tender
price as follows:
Making any correction for errors pursuant to ITT Clause 29;
Excluding provisional sums and the provision, if any for
contingencies in the Bill of Quantities, but including Day work ,
where priced competitively ; and
Making appropriate adjustments to reflect discounts or other
price modifications offered in accordance with sub-Clause 24.5.
31.3 The Procuring Entity may waive any minor informality or non-
conformity, which does not constitute a material deviation,
provided such waiver does not prejudice or affect the relative
standing of any Tenderer. Variations, deviations, and alternative
offers and other factors, which are in excess of the requirements
of the Tendering documents or otherwise result in unsolicited
benefits for the Procuring Entity will not be taken into account in
22 | P a g e
Tender evaluation.
32. National 32.1 In the evaluation of Tenders the Procuring Entity shall apply
Preference exclusive preference to citizens of Kenya where:
33. Determination 33.1 The Tender with the lowest evaluated price from among those
of the Lowest which are eligible, compliant and substantially responsive shall be
E valuated the lowest evaluated Tender.
Tend er
34. Post- 34.1 If specified in the Tend er Data S heet, post-qualification shall be
qualification of undertaken.
Tend erer
23 | P a g e
included in these Tendering documents shall not be used in the
evaluation of the Tenderer‘s qualifications.
F. Award of Contract
35. C riteria of A ward 35.1 Subject to ITT Clause 35 and 36, the Procuring Entity will
award the Contract to the Tenderer whose Tender has
been determined to be substantially responsive to the
Tendering documents and who has offered the lowest
Evaluated Tender Price, provided that such Tenderer has
been determined to be:
24 | P a g e
d) Finalizing payment arrangements;
e) Mobilization arrangements;
f) Agreeing final delivery or work schedule to
accommodate any changes required by the Procuring
Entity;
g) The methodology or staffing; or
h) Clarifying details that were not apparent or could not
be finalized at the time of Tendering
37. Procuring E ntity‘s Right 37.1 Notwithstanding ITT Clause 35, the Procuring Entity
to A c cept any Tender reserves the right to accept or reject any Tender, and to
and to Reject any o r cancel the Tendering process and reject all Tenders, at any
all Tenders time prior to the award of Contract, without thereby
incurring any liability to the affected Tenderer or
Tenderers.
38. Procuring E ntities Right 38.1 The Procuring Entity reserves the right at the time of
to V ary Quantities at contract award to increase or decrease the quantity of
the Time of Award goods or related services originally specified in these
Tendering documents (schedule of requirements)
provided this does not exceed by the percentage
indicated in the Tend er Data S heet, without any change
in unit price or other terms and conditions of the Tender
and Tendering documents.
39. Notification of A ward 39.1 The Tenderer whose Tender has been accepted will be
notified of the award by the Procuring Entity prior to
expiration of the Tender validity period by e-mail or
facsimile confirmed by registered letter. This letter
(hereinafter and in the Conditions of Contract called the
―Letter of Acceptance‖) will state the sum that the
Procuring Entity will pay the Contractor in consideration
of the provision and maintenance of the Work(s) as
prescribed by the Contract (hereinafter and in the
Contract called the ―Contract Price‖).
25 | P a g e
39.2 The notification of award will constitute the formation of
the Contract, subject to the Tenderer furnishing the
Performance Security in accordance with ITT Clause 41
and signing the Contract in accordance with sub-Clause
40.2
40. S ig ning of C ontract 40 .1 Promptly, and in no case later than 14 days, after
notification, Procuring Entity shall send the successful
Tenderer the Agreement and Contract Data Sheet,
incorporating all agreements between the parties
obtained as a result of Contract negotiations.
41. Performance S ecurity 41.1 Within thirty (30) days but after 14 days after receipt of
the Letter of Acceptance, the successful Tenderer shall
deliver to the Procuring Entity a Performance Security in
the amount and in the form stipulated in the Tender Data
Sheet and the Contract Data Sheet, denominated in the
type and proportions of currencies in the Letter of
Acceptance and in accordance with the Conditions of
Contract.
26 | P a g e
41.2 If the Performance Security is provided by the successful
Tenderer in the form of a Bank Guarantee or Insurance
Bond, it shall be issued either:
42. A d vance Payment 42.1 The Procuring Entity will provide an Advance Payment as
stipulated in the Conditions of Contract, subject to a
maximum amount, as stated in the Tender Data Sheet.
43. A d judicator 43.1 The Procuring Entity proposes the person named in the
Tender Data Sheet to be appointed as Adjudicator under
the Contract, at an hourly fee specified in the Tender
Data Sheet, plus reimbursable expenses. If the Tenderer
disagrees with this proposal, the Tenderer should so state
in the Tender. If, in the Letter of Acceptance, the
Procuring Entity has not agreed on the appointment of
the Adjudicator, the Adjudicator shall be appointed by
the Appointing Authority designated in the Contract Data
Sheet at the request of either party.
27 | P a g e
44. Rig ht to Review 44.1 A Tenderer who claims to have suffered or risk suffering, loss
or damage or injury as a result of breach of a duty imposed
on a Procuring Entity or an Approving Authority by the Public
Procurement and Disposal Act, 2005 and the Public
Procurement and Disposal Regulations 2006, the procurement
proceedings or processes, may seek administrative review as
prescribed by the Act. The following matters, however, shall
not be subject to the administrative review:
45. Time Limit on 45.1 The Tenderer shall submit an application for review in the
Review number of copies and pay fees as prescribed by the Public
Procurement and Disposal Regulations 2006 within fourteen
(14) days of the time the Tenderer became or should have
become aware of the circumstances giving rise to the
complaint or dispute.
46. S ubmission of 46.1 Any application for administrative review shall be submitted
A p plications for in writing to the Secretary, Public Procurement Administrative
Review by the Review Board on Form RB 1 at the address shown in the
Public Tender Data Sheet. The secretary to the review board shall
Procurement immediately after filing of the request, serve a copy thereof on
A d ministrative the Procuring Entity or Director-General as the case may be.
Review B oard
28 | P a g e
support of its request;
d) Remedies sought;
e) Any other information relevant to the complaint.
47. Dec ision by the 47.1 The Administrative Review Board shall within thirty days after
Public receipt of an application for administrative review deliver a
Procurement written decision which shall indicate:
A d ministrative
Review B oard
a) Annulling anything the Procuring Entity has done in the
procurement proceedings, including annulling the
procurement proceedings in their entirety;
47.2 The decision made by the Review Board shall, be final and
binding on the parties unless judicial review thereof
commences within fourteen (14) days from the date of the
Review Board‘s decision.
48. A p peal on the 48.1 Any party to the review aggrieved by the decision of the
d ec ision of the Review Board may appeal to the High Court and the decision
Review B oard of the High Court shall be final.
29 | P a g e
SECTION III: TENDER DATA SHEET & EVALUATION CRITERA
30 | P a g e
A. Tender Data Sheet (TDS)
TDS ITT Amendments of, and Supplements to, Clauses in the Instruction
Reference Clause to Tenderers
Number Number
1. Introduction
4. 1.3 The Objectives of the Works is install cold storage facilities and related
mechanical works
6. 3.1 The tenderer is open to all registered company under the laws of
Kenya. Joint Venture is allowed in which case the partners are
severally liable. A joint venture agreement MUST be provided. Sub-
Contracting is allowed however the portion being sub-contracted
MUST not exceed 30% of the value of the works/contract. The sub-
contractor MUST be disclosed at tendering stage via completion of
Section IX – Standard Forms – Details of Sub-Contractors
8 3.4 Tenders MUST not be conflicted in anyway and in line with THE
PUBLIC PROCUREMENT AND ASSET DISPOSAL ACT of 2015 Section
55
31 | P a g e
10 . 5.2 Alternative time for completion Not A p p lic able
11. 7.2 There shall be a pre-tender site visit in line with Section I – Invitation
for Tenders/Advertisement.
12. 7.5 The minutes of the pre-Tender meeting will be transmitted within 3
days from the date of the meeting. The minutes will be transmitted
via email to all meeting participants. The pre-tender meeting will
involve a mandatory pre-tender site visit.
14. 8.2 This is as provided under Tender Data Sheet reference number 29 below
15. 8.3 The Invitation for Tenders (Section I) issued by the Procuring Entity is part
of the Tendering Documents. In case of discrepancies between the
Invitation for Tenders and other sections, the Invitation for Tenders shall
be the reference
17. 9.2 Period to Respond to request for clarification by the Procuring Entity
Max imum 5 d ays after rec eiving requests
All c larifications that will not result to the amend ment of the Tend er
Doc ument shall instead be posted in the County Government of S amburu
website ………………….
The procuring entity shall not take any responsibility for failure by the
tenderer to access/obtain information relating to amendment of tender
32 | P a g e
documents posted in the procuring entity website.
3. Preparation of Tenders
21. 13.4 In the case of joint venture each partner shall submit information required
under Clause ITT Clause 13.4. In addition the Tenderer shall furnish the
following , A s p er Table of Minimum Requir ements
23. 16.4 The price shall be FIX ED d uring the p roject implementation p eriod and
shall not be subjec t to any c hang e.
24. 17.1 The currency in which the prices shall be quoted shall be: Kenyan Shilling
25. 17.2 The contract shall be in Kenya Shillings and payments shall be made in
Kenya Shillings
26. 18.1 The Tender validity period shall be A s p er Invitation for Tend er s
27. 19.1 The amount of Tender Security shall be A s p er Invitation for Tend er s and
in line with Invitation for Tend er s
4. S ubmission of Tenders
31. 21.2 a) Tenders shall be submitted to address as sp ec ified und er Invitation for
Tend ers
32. 21.2 b) The Project Name and Tend er Number is as specified under Invitation for
Tend ers
33 | P a g e
33. 22.1 The deadline for Tender submission is as sp ec ified und er Invitation for
Tend ers
34. 22.3 The extension of the deadline for submission of Tenders shall be made
not later than 7 days before the expiry of the original deadline.
35. 23.2 Any Tender received by the Procuring Entity after the deadline for
submission of Tenders shall be declared late and shall NOT be received,
Opened or processed in any manner.
36. 25.1 The Tender opening shall take place at as sp ec ified und er Invitation for
Tend ers
37. 25.2 Tender Documents that shall not be clearly labelled as in line with line 29
of Tender Data Sheet shall not be opened
38. 25.7 The Tender Price/Bid Sum shall ONLY be read from the Form of Tender.
Where the Form of Tender has not been completed with the Tender Sum,
in such a case Tender Sum for the bidder shall not be read
39. 28.1 In addition, the procuring entity will examine whether all the tenders
meet the Mand ator y Requirements under the E valuation C r iter ia
requirements
40 . 29.1 The amounts read under Tender Sum shall be final and shall not be
subject to any form of correction. The procuring entity will however
scrutinise the Bills of Quantities for completeness and where
errors/omissions/incompleteness have been identified and the tenderer
will either be automatically disqualified under preliminary or asked to
accept the errors/omissions. This shall be at the sole discretion of the
procuring entity
6. A ward of C ontract
46. 41.1-2 The amount of Performance Security shall be 10% of the tender sum.
47. 42.1 The Advance Payment shall be Z er o/A d vanc e Payment shall not be
G ranted .
48. 43.1 The proposed adjudicator for the project is as per the laws of Kenya
34 | P a g e
7. Review of Procurement Decisions
49. 46.1 The address for submitting appeals to Administrative Review Board :
The Secretary,
Public Procurement Administrative Review Board ,
The Public Procurement Regulatory Authority,
10th Floor ,National Bank House,
P.O. Box 58583-00200,
NAIROBI, Kenya.
Tel: +254 (0) 20 3244000
Email: info@ppra.go.ke Website: www.ppra.go.ke
35 | P a g e
B. EVALUATION CRITERIA
1. PRE LIMINARY - EVALUATION C HECKLIST FOR COMPLETENESS AND RESPONSIVENESS OF
MA NDA TORY REQUIREMENTS
This will involve assessing whether bidders have complied with submission requirements and have
also attached certified copies of mandatory eligibility and statutory documents. Evaluation at this
stage will be conducted on Yes/No, and bidders are expected to comply with ALL required items so
as to proceed to the next stage of evaluation.
36 | P a g e
-C er tified copy of Form CR12 (C er tified by
C ommissioner of Oaths)
8. Eligibility
- Copies of National ID or passport for all
directors
37 | P a g e
2. POS T- PRELIMINARY EVALUATION S CORE
Tenders will be evaluated to ensure that they are substantially responsive to the technical
specifications and contract conditions stated in the Tender Document. The determination of a
tender‘s technical responsiveness will based on the contents of the tender itself, subject to any
clarifications received in the preliminary examination of Tenders. Items of this evaluation will be
scored.
1 E X PE RIE NC E Max 40
Attach reference letters/contracts/purchase orders for different
firms as evidences.
c. Any four projects less than 50% value of the tendered works. 8
2 KE Y PE RS ONNE L Max 20
38 | P a g e
ITE M DE S C RIPTION POINT E valuation
S C ORE S c or e
S C A LE
39 | P a g e
ITE M DE S C RIPTION POINT E valuation
S C ORE S c or e
S C A LE
(2017,2018 & 2019)
TOTA L MA X 10 0
The technical evaluation pass mark shall be 70% of which bidders who pass will be subjected to
tender price comparisons.
( Procuring E ntity) will verify information submitted. A ny form of forgery or misinfor mation fr om
the bid der shall lead to c ancellation of the bid/award, institution of l egal p roceedings and blacklisting
for all future ( Proc uring E ntity) c ontrac ts.
3. Due Diligence
The Tenderer that shall have quoted the lowest price shall be considered for award after a successful
tenderer due diligence whose essence shall be to confirm the correctness of information provided
during the bidding process. If the bidder is found to have given false information, the bidder shall be
disqualified automatically without further reference to the bidder and in such a case the next second
lowest bidder shall be considered subject to the same verification processes.
This will be conducted by either visiting the supplier places where he has supplied/executed similar
machinery/works. The supplier shall make necessary arrangements to ensure that the visit is smooth
and all queries by the client are addressed.
4. A ward
The County Government of Samburu will award the Contract to the tenderer whose tender is
determined to be substantially responsive to the tender documents and who has offered the lowest
evaluated tender price.
40 | P a g e
SECTION IV: GENERAL CONDITIONS OF CONTRACT
41 | P a g e
A. General
42 | P a g e
Materials are all supplies, including consumables, used by the
Contractor for incorporation in the Works.
Plant is any integral part of the Works that shall have a mechanical,
electrical, chemical, or biological function.
The Project Manager is the person named in the C ontract Data S heet
(or any other competent person appointed by the Procuring Entity
and notified to the Contractor, to act in replacement of the Project
Manager) who is responsible for supervising the execution of the
Works and administering the Contract and shall be an ―Architect‖ or a
―Quantity Surveyor‖ registered under the Architects and Quantity
Surveyors Act Cap 525 or an ―Engineer‖ registered under Engineers
Registration Act Cap 530.
The S ite is the area defined as such in the C ontr ac t Data S heet.
S ite Investig ation Rep or ts are those that were included in the
Tendering documents and are factual and interpretative reports about
the surface and subsurface conditions at the Site.
S p ec ific ation means the Specification of the Works included in the
Contract and any modification or addition made or approved by the
Project Manager.
The S tart Date is given in the C ontract Data S heet. It is the latest date
when the Contractor shall commence execution of the Works. It does
not necessarily coincide with any of the Site Possession Dates.
A S ubc ontrac tor is a person or corporate body who has a Contract
with the Contractor to carry out a part of the work in the Contract,
which includes work on the Site.
Temp orary Wor k s are works designed, constructed, installed, and
removed by the Contractor that are needed for construction or
installation of the Works.
A V ariation is an instruction given by the Project Manager that varies
the Works.
The Work s are what the Contract requires the Contractor to
construct, install, and turn over to the Procuring Entity, as defined in
the C ontrac t Data S heet.
―Forc e Majeur e‖ means an event which is beyond the reasonable
control of a Party and which makes a Party‘s performance of its
obligations under the Contract impossible or so impractical as to be
considered impossible under the circumstances.
43 | P a g e
the order of priority given in the C ontr ac t Data S heet:
(1) Agreement;
(2) Letter of Acceptance;
(3) Contract Data Sheet;
(4) Conditions of Contract;
(5) Technical Specifications;
(6) Contractor‘s Tender;
(7) Drawings;
(8) Bill of Quantities; and
(9) Any other document listed in the C ontr ac t Data S heet as
forming part of the Contract.
3. Lang uage, Law, 3.1 The language of the Contract and the law governing the
Fraud and Contract are stated in the C ontr ac t Data S heet.
C orruption
44 | P a g e
impair or harm, directly or indirectly a supplier, contractor or
subcontractor or the property of any of them to influence improperly
the actions of a Procuring Entity;
―Obstruc tive Pr ac tic e‖ means deliberately destroying, falsifying,
altering or concealing of evidence material to the investigation or
making false statements to investigators in order to materially impede
an investigation into allegations of a corrupt, fraudulent, coercive or
collusive practice; and /or threatening, harassing or intimidating any
party to prevent it from disclosing its knowledge of matters relevant
to the investigation or from pursuing the investigation.
A Procuring Entity has the right to require that Tenderers, suppliers,
and contractors and their subcontractors permit persons duly
appointed by KACC/PPOA/KNAO to inspect their accounts and
records and other documents relating to the Tender submission and
contract performance;
The Procuring Entity will reject a proposal for award if it determines
that the Tenderer recommended for award has engaged in corrupt,
fraudulent practices or others stated under Clause 44.1.a in competing
for the contract;
In pursuit of the policy defined in sub-Clause 44.1 the Procuring Entity
will cancel the portion of the funds allocated to a contract for goods,
works, or services if it at any time determines that corrupt or
fraudulent practices were engaged in by representatives of the
Procuring Entity or Approving Authority or of a beneficiary of the
funds during the procurement or the execution of that contract;
In the event that the Procuring Entity or Approving Authority does
not take timely and appropriate action satisfactory to the
Government of Kenya to remedy the situation, then the Director-
General may order an investigation of procurement proceedings for
the purpose of determining whether there has been a breach of the
Public Procurement and Disposal Act, 2005.
4. C onfidentiality 4.1 The Service Providers, their Subcontractors, and the Personnel of
either of them shall not disclose any proprietary or confidential
information relating to the Project, the Services, this Contract, or the
Procuring Entity‘s business or operations without the prior written
consent of the Procuring Entity.
45 | P a g e
5. Project Manager‘s 5.1 Except where otherwise specifically stated, the Project
Dec isions Manager will decide contractual matters between the Procuring Entity
and the Contractor in the role representing the Procuring Entity.
6. Deleg ation 6.1 The Project Manager may delegate any of his duties and
responsibilities to other people except to the Adjudicator, after
notifying the Contractor, and may cancel any delegation after
notifying the Contractor.
8. S ubcontracting 8.1 The Contractor may subcontract with the approval of the
Project Manager, but may not assign the Contract without the
approval of the Procuring Entity in writing. Subcontracting shall not
alter the Contractor‘s obligations.
9. Other C ontractors 9.1 The Contractor shall cooperate and share the Site with other
contractors, public authorities, utilities, and the Procuring Entity
between the dates given in the Schedule of Other Contractors, as
referred to in the C ontr ac t Data S heet. The Contractor shall also
provide facilities and services for them as described in the Schedule.
The Procuring Entity may modify the Schedule of Other Contractors,
and shall notify the Contractor of any such modification
10. Personnel 10.1 The Contractor shall employ the key personnel named in the
Schedule of Key Personnel, as referred to in the C ontr ac t Data S heet,
who shall be appropriately qualified and registered with the
appropriate bodies to carry out the functions stated in the Schedule or
other personnel approved by the Project Manager. The Project
Manager will approve any proposed replacement of key personnel
only if their relevant qualifications and abilities are substantially equal
to or better than those of the personnel listed in the Schedule.
If the Project Manager asks the Contractor to remove a person who is
a member of the Contractor‘s staff or work force, stating the reasons,
the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the work in the
Contract.
11. Procuring E ntity‘s 11.1 The Procuring Entity carries the risks which this Contract states
and C ontractor‘s are Procuring Entity‘s risks, and the Contractor carries the risks which
Risk s this Contract states are Contractor‘s risks.
12. Procuring E ntity‘s 12.1 From the Start Date until the Defects Correction Certificate
Risk s has been issued, the following are Procuring Entity‘s risks:
The risk of personal injury, death, or loss of or damage to property
(excluding the Works, Plant, Materials, and Equipment), which are
due to:
(i) Use or occupation of the Site by the Works or for the purpose
of the Works, which is the unavoidable result of the Works; or
(ii) Negligence, breach of statutory duty, or interference with any
legal right by the Procuring Entity or by any person employed by or
contracted to him except the Contractor.
46 | P a g e
The risk of damage to the Works, Plant, Materials, and Equipment to
the extent that it is due to a fault of the Procuring Entity or in the
Procuring Entity‘s design, or due to war or radioactive contamination
directly affecting the country where the Works are to be executed.
12.2 From the Completion Date until the Defects Correction
Certificate has been issued, the risk of loss of or damage to the Works,
Plant, and Materials is an Procuring Entity‘s risk except loss or damage
due to:
(a) A Defect which existed on the Completion Date;
(b) An event occurring before the Completion Date, which was
not itself an Procuring Entity‘s risk; or
(c) The activities of the Contractor on the Site after the
Completion Date.
13. C ontractor‘s Risks 13.1 From the Starting Date until the Defects Correction Certificate
has been issued, the risks of personal injury, death, and loss of or
damage to property (including, without limitation, the Works, Plant,
Materials, and Equipment) which are not Procuring Entity‘s risks are
Contractor‘s risks.
14. Insurance 14.1 The Contractor shall provide, in the joint names of the
Procuring Entity and the Contractor, insurance cover from the Start
Date to the end of the Defects Liability Period, in the amounts and
deductibles stated in the C ontr ac t Data S heet for the following events
which are due to the Contractor‘s risks:
(a) Loss of or damage to the Works, Plant, and Materials;
(b) Loss of or damage to Equipment;
(c) Loss of or damage to property (except the Works, Plant,
Materials, and Equipment) in connection with the Contract; and
(d) Personal injury or death.
14.2 Policies and certificates for insurance shall be delivered by the
Contractor to the Project Manager for the Project Manager‘s approval
before the Start Date. All such insurance shall provide for
compensation to be payable in the types and proportions of
currencies required to rectify the loss or damage incurred.
14.3 If the Contractor does not provide any of the policies and
certificates required, the Procuring Entity may affect the insurance
which the Contractor should have provided and recover the
premiums the Procuring Entity has paid from payments otherwise due
to the Contractor or, if no payment is due, the payment of the
premiums shall be a debt due.
14.4 Alterations to the terms of insurance shall not be made
without the approval of the Project Manager.
14.5 Both parties shall comply with any conditions of the insurance
policies.
15. S ite Investigation 15.1 The Contractor, in preparing the Tender, shall rely on any
Rep orts Site Investigation Reports referred to in the C ontr ac t Data S heet,
supplemented by any information available to the Tenderers.
16. Queries about the 16.1 The Project Manager will clarify queries on the C ontr ac t Data
47 | P a g e
C ontract Data S heet.
S heet
17. C ontractor to 17.1 The Contractor shall construct and install the Works in
C onstruct the accordance with the Specifications and Drawings.
Works
18. C ommencement 18.1 The Contractor may commence execution of the Works on
and C ompletion the Start Date and shall carry out the Works in accordance with the
Programme submitted by the Contractor, as updated with the
approval of the Project Manager, and complete them by the Intended
Completion Date.
19. A p proval by the 19.1 The Contractor shall submit Specifications and Drawings
Project Manager showing the proposed Temporary Works to the Project Manager,
who is to approve them if they comply with the Specifications and
Drawings.
19.2 The Contractor shall be responsible for the design of
Temporary Works.
19.3 The Project Manager‘s approval shall not alter the
Contractor‘s responsibility for design of the Temporary Works.
19.4 The Contractor shall obtain approval of third parties to the
design of the Temporary Works, where required.
19.5 All Drawings prepared by the Contractor for the execution of
the temporary or permanent Works, are subject to prior approval by
the Project Manager before their use.
20. Protection of the 20.1 The Contractors shall take all reasonable steps to protect the
E nvironment environment and to limit damage and nuisance to people and
property resulting from pollution, noise and other results of his
operations.
21. Labour Laws 21.1 The Contractor shall comply with all the relevant labour laws
applicable in the Country, including laws relating to workers
employment, working hours, health, safety, welfare, and immigration,
and shall allow them all their legal rights.
The Contractor shall require his employees to obey all applicable
laws, including those concerning safety at work.
22. Health and S afety 22.1 The Contractor shall at all times take all reasonable
precautions to maintain the health and safety of his personnel.
22.2 The Contractor shall ensure that first aid facilities are available
at all times at the site and that suitable arrangements are made for all
necessary welfare and hygiene requirements and for the prevention of
epidemics.
22.3 The Contractor shall notify the Procuring Entity details of any
accident as soon as practicable after its occurrence. The Contractor
shall maintain records and make reports concerning health, safety, and
welfare of persons, and damage to the property, as the Procuring
Entity may reasonably require.
48 | P a g e
22.4 The Contractor shall conduct an HIV-Aids awareness
programme, and shall take other such measures as specified in the
C ontrac t Data S heet to reduce the risk of transfer of HIV virus
between and among Contractor personnel, the Procuring Entity‘s Staff
and the surrounding community.
23. Disc overies 23.1 Anything of historical or other interest or of significant value
unexpectedly discovered on the Site shall be the property of the
Procuring Entity. The Contractor shall notify the Project Manager of
such discoveries and carry out the Project Manager's instructions for
dealing with them.
24. Possession of the 24.1 The Procuring Entity shall give possession of all parts of the
S ite Site to the Contractor. If possession of a part is not given by the date
stated in the C ontract Data S heet, the Procuring Entity will be deemed
to have delayed the start of the relevant activities, and this will be a
Compensation Event.
25. A c cess to the Site 25.1 The Contractor shall allow the Project Manager and any
person authorized by the Project Manager access to the Site and to
any place where work in connection with the Contract is being
carried out or is intended to be carried out.
26. Instructions, 26.1 The Contractor shall carry out all instructions of the Project
Insp ections and Manager which comply with the applicable laws where the Site is
A ud its located.
26.2 The Contractor shall permit the Kenya Government to inspect
the Contractor‘s accounts and records relating to the performance of
the Contractor and to have them audited by auditors appointed by
the Kenya Government, if so required by the Kenya Government
27. Disp utes 27. 1 If the Contractor believes that a decision taken by the Project
Manager was either outside the authority given to the Project
Manager by the Contract or that the decision was wrongly taken, the
decision shall be referred to the Adjudicator within 14 days of the
notification of the Project Manager‘s decision.
28. Procedure for 28.1 The Adjudicator shall give a decision in writing within 28
Disp utes days of receipt of a notification of a dispute.
28.2 The Adjudicator shall be paid by the hour at the rate specified
in the Tend er Data S heet and C ontr ac t Data S heet, together with
reimbursable expenses of the types specified in the C ontr ac t Data
S heet, and the cost shall be divided equally between the Procuring
Entity and the Contractor, whatever decision is reached by the
Adjudicator. Either party may refer a decision of the Adjudicator to
an Arbitrator within 28 days of the Adjudicator‘s written decision. If
neither party refers the dispute to arbitration within the above 28
days, the Adjudicator‘s decision will be final and binding.
29. Rep lacement of 29.1 Should the Adjudicator resign or die, or should the Procuring
Entity and the Contractor agree that the Adjudicator is not
49 | P a g e
A d judicator functioning in accordance with the provisions of the Contract, a new
Adjudicator will be jointly appointed by the Procuring Entity and the
Contractor. In case of disagreement between the Procuring Entity and
the Contractor, within 30 days, the Adjudicator shall be designated by
the Appointing Authority designated in the C ontract Data S heet at the
request of either party, within 14 days of receipt of such request.
B. Time Control
30. Programme 30.1. Within the time stated in the C ontr ac t Data S heet, the Contractor
shall submit to the Project Manager for approval a Programme showing
the general methods, arrangements, order, and timing for all the activities
in the Works.
An update of the Programme shall be a programme showing the actual
progress achieved on each activity and the effect of the progress achieved
on the timing of the remaining work, including any changes to the
sequence of the activities.
30.3 The Contractor shall submit to the Project Manager for approval
an updated Programme at intervals no longer than the period stated in the
C ontrac t Data S heet. If the Contractor does not submit an updated
Programme within this period, the Project Manager may withhold the
amount stated in the C ontr ac t Data S heet from the next payment
certificate and continue to withhold this amount until the next payment
after the date on which the overdue Programme has been submitted.
30.4 The Project Manager‘s approval of the Programme shall not alter
the Contractor‘s obligations. The Contractor may revise the Programme
and submit it to the Project Manager again at any time. A revised
Programme shall show the effect of Variations and Compensation Events
31. E x tension of 31.1 The Project Manager shall extend the Intended Completion Date if
the Intended a Compensation Event occurs or a Variation is issued which makes it
C ompletion impossible for Completion to be achieved by the Intended Completion
Date Date without the Contractor taking steps to accelerate the remaining work,
which would cause the Contractor to incur additional cost.
31.2 The Project Manager shall decide whether and by how much to
extend the Intended Completion Date within 21 days of the Contractor
asking the Project Manager for a decision upon the effect of a
Compensation Event or Variation and submitting full supporting
information. If the Contractor has failed to give early warning of a delay
or has failed to cooperate in dealing with a delay, the delay by this failure
shall not be considered in assessing the new Intended Completion Date.
50 | P a g e
32. A c celeration 32.1 When the Procuring Entity wants the Contractor to finish before
the Intended Completion Date, the Project Manager will obtain priced
proposals for achieving the necessary acceleration from the Contractor. If
the Procuring Entity accepts these proposals, the Intended Completion
Date will be adjusted accordingly and confirmed by both the Procuring
Entity and the Contractor.
32.2 If the Contractor‘s priced proposals for acceleration are accepted
by the Procuring Entity, they shall be incorporated in the Contract Price
and treated as a Variation.
33. Delays 33.1 The Project Manager may instruct the Contractor to delay the start
Ord ered by or progress of any activity within the Works.
the Project
Manag er
34. Manag ement 34.1 Either the Project Manager or the Contractor may require the
Meetings other to attend a management meeting. The business of a management
meeting shall be to review the plans for remaining work and to deal with
matters raised in accordance with the early warning procedure.
34.2 The Project Manager shall record the business of management
meetings and provide copies of the record to those attending the meeting
and to the Procuring Entity. The responsibility of the parties for actions to
be taken shall be decided by the Project Manager either at the
management meeting or after the management meeting and stated in
writing to all who attended the meeting.
35. E arly 35.1 The Contractor shall warn the Project Manager at the earliest
Warning opportunity of specific likely future events or circumstances that may
adversely affect the quality of the work, increase the Contract Price or
delay the execution of the Works. The Project Manager may require the
Contractor to provide an estimate of the expected effect of the future
event or circumstance on the Contract Price and Completion Date. The
estimate shall be provided by the Contractor as soon as reasonably
possible.
35.2 The Contractor shall cooperate with the Project Manager in
making and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the work
and in carrying out any resulting instruction of the Project Manager.
C. Quality Control
36. Id entifying 36.1 The Project Manager shall check the Contractor‘s work and notify
Defec ts the Contractor of any Defects that are found. Such checking shall not
affect the Contractor‘s responsibilities. The Project Manager may instruct
the Contractor to search for a Defect and to uncover and test any work
that the Project Manager considers may have a Defect.
37. Tests 37.1 If the Project Manager instructs the Contractor to carry out a test
not specified in the Specification to check whether any work has a Defect
and the test shows that it does, the Contractor shall pay for the test and
51 | P a g e
any samples. If there is no Defect, the test shall be a Compensation Event.
38. C orrection of 38.1 The Project Manager shall give notice to the Contractor of any
Defec ts Defects before the end of the Defects Liability Period, which begins at
Completion, and is defined in the C ontr ac t Data S heet. The Defects
Liability Period shall be extended for as long as Defects remain to be
corrected.
38.2 Every time notice of a Defect is given, the Contractor shall correct
the notified Defect within the length of time specified by the Project
Manager‘s notice.
38.3 If the Contractor has not corrected a defect within the time specified
in the Procuring Entity‘s notice, a penalty for lack of performance will be
paid by the Contractor. The amount to be paid will be calculated as a
percentage of the cost of having the defect correct, assessed as described in
Clause 39.
39. Unc orrected 39.1 If the Contractor has not corrected a Defect within the time
Defec ts specified in the Project Manager‘s notice, the Project Manager will assess
the cost of having the Defect corrected, and the Contractor will pay this
amount.
D. Cost Control
40. B ill of 40.1 The Bill of Quantities shall contain items for the construction,
Quantities installation, testing, and commissioning work to be done by the
Contractor.
40.2 The Bill of Quantities is used to calculate the Contract Price. The
Contractor shall be paid for the quantity of the work done at the rate in
the Bill of Quantities for each item.
41. C hanges in the 41.1 If the final quantity of the work done differs from the quantity in
Quantities the Bill of Quantities for the particular item by more than 25 percent,
provided the change exceeds 1 percent of the Initial Contract Price, the
Project Manager shall adjust the rate to allow for the change.
41.2 The Project Manager shall not adjust rates from changes in
quantities if thereby the Initial Contract Price is exceeded by more than 15
percent, except with the prior approval of the Procuring Entity.
41.3 If requested by the Project Manager, the Contractor shall provide
the Project Manager with a detailed cost breakdown of any rate in the
Bill of Quantities.
42. V ariations 42.1 All Variations shall be included in the updated Programmes
produced by the Contractor.
43. Payments for 43.1 The Contractor shall provide the Project Manager with a
V ariations quotation for carrying out the Variation when requested to do so by the
Project Manager. The Project Manager shall assess the quotation, which
shall be given within seven days of the request or within any longer
period stated by the Project Manager and before the Variation is ordered.
43.2 If the work in the Variation corresponds with an item description
in the Bill of Quantities and if, in the opinion of the Project Manager, the
52 | P a g e
quantity of work is above the limit stated in Sub-Clause 41.1 or the timing
of its execution do not cause the cost per unit of quantity to change, the
rate in the Bill of Quantities shall be used to calculate the value of the
Variation. If the cost per unit of quantity changes, or if the nature or
timing of the work in the Variation does not correspond with items in the
Bill of Quantities, the quotation by the Contractor shall be in the form of
new rates for the relevant items of work.
43.3 If the Contractor‘s quotation is unreasonable, the Project
Manager may order the Variation and make a change to the Contract
Price, which shall be based on the Project Manager‘s own forecast of the
effects of the Variation on the Contractor‘s costs.
43.4 If the Project Manager decides that the urgency of varying the
work would prevent a quotation being given and considered without
delaying the work, no quotation shall be given and the Variation shall be
treated as a Compensation Event.
43.5 The Contractor shall not be entitled to additional payment for
costs that could have been avoided by giving early warning.
44. C ash Flow 44.1 When the Programme is updated, the Contractor shall provide
Forecasts the Project Manager with an updated cash flow forecast. The cash flow
forecast shall include different currencies, as defined in the Contract,
converted as necessary using the Contract exchange rates.
45. Payment 45.1 The Contractor shall submit to the Project Manager monthly
C ertificates statements of the estimated value of the work executed less the
cumulative amount certified previously.
45.2 The Project Manager shall check the Contractor‘s monthly
statement and certify the amount to be paid to the Contractor within
twenty eight 28 days of receipt of the certificate from the contractor.
45.3 The value of work executed shall be determined by the Project
Manager.
45.4 The value of work executed shall comprise the value of the
quantities of the items in the Bill of Quantities completed.
46. Payments 46.1 Payments shall be adjusted for deductions for advance payments
and retention. The Procuring Entity shall pay the Contractor the amounts
certified by the Project Manager within 28 days of the date of each
certificate. If the Procuring Entity makes a late payment, the Contractor
shall be paid interest on the late payment in the next payment Interest
shall be calculated from the date by which the payment should have been
made up to the date when the late payment is made at the prevailing
rate of interest for commercial borrowing for each of the currencies in
which payments are made as indicated in the C ontr ac t Data S heet. .
53 | P a g e
If an amount certified is increased in a later certificate or as a result of an
award by the Adjudicator or an Arbitrator, the Contractor shall be paid
interest upon the delayed payment as set out in this clause. Interest shall
be calculated from the date upon which the increased amount would
have been certified in the absence of dispute.
46.3 Unless otherwise stated, all payments and deductions will be paid
or charged in the proportions of currencies comprising the Contract Price.
46.4 Items of the Works for which no rate or price has been entered
in will not be paid for by the Procuring Entity and shall be deemed
covered by other rates and prices in the Contract.
54 | P a g e
47.3 As soon as information demonstrating the effect of each
Compensation Event upon the Contractor‘s forecast cost has been
provided by the Contractor, it shall be assessed by the Project Manager,
and the Contract Price shall be adjusted accordingly. If the Contractor‘s
forecast is deemed unreasonable, the Project Manager shall adjust the
Contract Price based on the Project Manager‘s own forecast. The Project
Manager will assume that the Contractor will react competently and
promptly to the event.
47.4 The Contractor shall not be entitled to compensation to the
extent that the Procuring Entity‘s interests are adversely affected by the
Contractor‘s not having given early warning or not having cooperated
with the Project Manager.
48. Tax es 48.1 The Project Manager shall adjust the Contract Price if taxes,
duties, and other levies are changed between the date 28 days before the
submission of Tenders for the Contract and the date of the last
Completion certificate. The adjustment shall be the change in the
amount of tax payable by the Contractor, provided such changes are not
already reflected in the Contract Price or are a result of Clause 50.
49. C urrencies 49.1 Where payments are made in currencies other than the Kenya
Shillings, the exchange rates used for calculating the amounts to be paid
shall be the exchange rates stated in the Contractor‘s Tender.
50. Price 50.1 The amounts payable to the Contractor, in various currencies
A d justment pursuant to Sub-Clause 45.1, shall be adjusted in respect of the rise or fall
in the cost of labour, Contractor‘s Equipment, Plant, materials, and other
inputs to the Works, by applying to such amounts the formulae
prescribed in this clause based on the prevailing consumer price index
obtained from the Central Bureau of Statistics or the monthly inflation
rate issued by the Central Bank of Kenya.
50.2 To the extent that full compensation for any rise or fall in costs to
the Contractor is not covered by the provisions of this or other clauses in
the Contract, the unit rates and prices included in the Contract shall be
deemed to include amounts to cover the contingency of such other rise
or fall of costs.
Ln Lo Mn Mo En Eo
Pn a b c d etc.
Lo Mo Eo
where;
55 | P a g e
a is a constant, specified in the A p p end ix to Tend er , representing the
nonadjustable portion in contractual payments;
Ln, Mn, E n, etc., are the current cost indices or reference prices of the cost
elements in the specific currency of origin for month ―n, ‖ determined
pursuant to Sub-Clause 50.5, applicable to each cost element; and
Lo, Mo, E o, etc., are the base cost indices or reference prices
corresponding to the above cost elements at the date specified in Sub-
Clause 50.5
The value of net work done, certified by the Project Manager, in any
monthly Interim or Final Certificate as payable by the Procuring Entity to
the Contractor before deduction of any retention money shall be
increased or decreased by an amount of ‗F‘.
F PnxPc
where;
56 | P a g e
Tend er , as approved by the Engineer. Indices shall be appropriate for
their purpose and shall relate to the Contractor‘s proposed source of
supply of inputs on the basis of which his Contract Price and expected
foreign currency requirements shall have been computed. As the
proposed basis for price adjustment, the Contractor shall have submitted
with his Tender the tabulation of Weightings and Source of Indices in the
A p p end ix to Tend er , which shall be subject to approval by the Engineer.
50.5 The base cost indices or prices shall be those prevailing on the day
28 days prior to the latest date for submission of Tenders. Current
indices or prices shall be those prevailing on the day 28 days prior to the
last day of the period to which a particular Interim Payment Certificate is
related. If at any time the current indices are not available, provisional
indices as determined by the Engineer will be used, subject to subsequent
correction of the amounts paid to the Contractor when the current
indices become available.
50.6 If the Contractor fails to complete the Works within the time for
completion prescribed under Clause 58 adjustment of prices thereafter
until the date of completion of the Works shall be made using either the
indices or prices relating to the prescribed time for completion, or the
current indices or prices, whichever is more favourable to the Procuring
Entity, provided that if an extension of time is granted pursuant to Clause
28, the above provision shall apply only to adjustments made after the
expiry of such extension of time.
50.7 The weightings for each of the factors of cost given in the
A p p end ix to Tend er shall be adjusted if, in the opinion of the Engineer,
they have been rendered unreasonable, unbalanced, or inapplicable as a
result of varied or additional work already executed or instructed under
Clause 43 or for any other reason.
51. Retention 51.1 The Procuring Entity shall retain from each payment due to the
Contractor the proportion stated in the C ontr ac t Data S heet until
Completion of the whole of the Works.
51.2 On completion of the whole of the Works, half the total amount
retained shall be repaid to the Contractor and the other half when the
Defects Liability Period has passed and the Project Manager has certified
that all Defects notified by the Project Manager to the Contractor before
the end of this period have been corrected.
51.3 On completion of the whole Works, the Contractor may
substitute retention money with an ―on demand‖ Bank guarantee.
52. Liquidated 52.1 The Contractor shall pay liquidated damages to the Procuring
Damag es Entity at the rate per day stated in the C ontr ac t Data S heet for each day
that the Completion Date is later than the Intended Completion Date.
The total amount of liquidated damages shall not exceed the amount
defined in the C ontr ac t Data S heet. The Procuring Entity may deduct
liquidated damages from payments due to the Contractor. Payment of
liquidated damages shall not affect the Contractor‘s liabilities.
57 | P a g e
If the Intended Completion Date is extended after liquidated damages
have been paid, the Project Manager shall correct any overpayment of
liquidated damages by the Contractor by adjusting the next payment
certificate. The Contractor shall be paid interest on the overpayment,
calculated from the date of payment to the date of repayment, at the
rates specified in Sub-Clause 46.1.
If the Contractor has not corrected a defects within the time specified in
the Procuring Entity‘s notice, the Procuring Entity will assess the cost of
having the defect corrected, the Contractor will pay this amount, and a
penalty for lack of performance calculated as described in Clause 38.
53. B onus 53.1 The Contractor shall be paid a Bonus calculated at the rate per
calendar day stated in the C ontract Data S heet for each day (less any days
for which the Contractor is paid for acceleration) that the Completion is
earlier than the Intended Completion Date. The Project Manager shall
certify that the Works are complete, although they may not be due to be
complete.
54. A d vance 54.1 The Procuring Entity shall make advance payment to the
Payment Contractor of the amounts stated in the C ontr ac t Data S heet by the date
stated in the C ontr ac t Data S heet, against provision by the Contractor of
an Unconditional Bank Guarantee in a form and by a bank acceptable to
the Procuring Entity in amounts and currencies equal to the advance
payment. The Guarantee shall remain effective until the advance
payment has been repaid, but the amount of the Guarantee shall be
progressively reduced by the amounts repaid by the Contractor. Interest
will not be charged on the advance payment.
54.2 The Contractor is to use the advance payment only to pay for
Equipment, Plant, Materials, and mobilization expenses required
specifically for execution of the Contract. The Contractor shall
demonstrate that advance payment has been used in this way by
supplying copies of invoices or other documents to the Project Manager.
54.3 The advance payment shall be repaid by deducting
proportionate amounts from payments otherwise due to the Contractor,
following the schedule of completed percentages of the Works on a
payment basis. No account shall be taken of the advance payment or its
repayment in assessing valuations of work done, Variations, price
adjustments, Compensation Events, Bonuses, or Liquidated Damages.
55. Performance 55.1 The Performance Security shall be provided to the Procuring
S ec urities Entity no later than the date specified in the Letter of Acceptance and
shall be issued in an amount and form and by a bank or surety acceptable
to the Procuring Entity, and denominated in the types and proportions of
the currencies in which the Contract Price is payable. The Performance
Security shall be valid until a date 28 days from the date of issue of the
Certificate of Completion in the case of a Bank Guarantee, and until one
year from the date of issue of the Completion Certificate in the case of a
Performance Bond.
56. Day works 56.1 If applicable, the Day works rates in the Contractor‘s Tender shall
be used for small additional amounts of work only when the Project
Manager has given written instructions in advance for additional work to
be paid for in that way.
56.2 All work to be paid for as Day works shall be recorded by the
Contractor on forms approved by the Project Manager. Each completed
58 | P a g e
form shall be verified and signed by the Project Manager within two days
of the work being done.
56.3 The Contractor shall be paid for Day works subject to obtaining
signed Day works forms.
58. C ompletion 58.1 The Contractor shall request the Project Manager to issue a
C ertificate certificate of Completion of the Works, and the Project Manager will do
so upon deciding that the work is completed.
59. Tak ing Over 59.1 The Procuring Entity shall take over the Site and the Works within
seven days of the Project Manager‘s issuing a certificate of Completion.
60. Final Account 60.1 The Contractor shall supply the Project Manager with a detailed
account of the total amount that the Contractor considers payable under
the Contract before the end of the Defects Liability Period. The Project
Manager shall issue a Defects Liability Certificate and certify any final
payment that is due to the Contractor within 56 days of receiving the
Contractor‘s account if it is correct and complete. If it is not, the Project
Manager shall issue within 56 days a schedule that states the scope of the
corrections or additions that are necessary. If the Final Account is still
unsatisfactory after it has been resubmitted, the Project Manager shall
decide on the amount payable to the Contractor and issue a payment
certificate.
61. Op erating 61.1 If ―as built‖ Drawings and/or operating and maintenance manuals
and are required, the Contractor shall supply them by the dates stated in the
Maintenance C ontrac t Data S heet.
Manuals
61.2 If the Contractor does not supply the Drawings and/or manuals
by the dates stated in the C ontr ac t Data S heet, or they do not receive the
Project Manager‘s approval, the Project Manager shall withhold the
amount stated in the C ontr ac t Data S heet from payments due to the
Contractor.
62. Termination 62.1 The Procuring Entity or the Contractor may terminate the
Contract if the other party causes a fundamental breach of the Contract.
62.2 Fundamental breaches of Contract shall include, but shall not be
limited to, the following:
(a) The Contractor stops work for 28 days when no stoppage of
work is shown on the current Programme and the stoppage has not been
authorized by the Project Manager;
(b) The Project Manager instructs the Contractor to delay the
progress of the Works, and the instruction is not withdrawn within 28
days;
(c) The Procuring Entity or the Contractor is made bankrupt or goes
59 | P a g e
into liquidation other than for a reconstruction or amalgamation;
(d) A payment certified by the Project Manager is not paid by the
Procuring Entity to the Contractor within 84 days of the date of the
Project Manager‘s certificate;
(e) The Project Manager gives Notice that failure to correct a
particular Defect is a fundamental breach of Contract and the Contractor
fails to correct it within a reasonable period of time determined by the
Project Manager;
(f) The Contractor does not maintain a Security, which is required;
and
(g) The Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated damages
can be paid, as defined in the C ontr ac t Data S heet.
(h) If the Contractor, in the judgment of the Procuring Entity has
engaged in corrupt or fraudulent practices in competing for or in
executing the Contract.
For the purpose of this paragraph:
―corrupt practice‖ means the offering, giving, receiving or soliciting of
anything of value to influence the action of a public official in the
procurement process or in contract execution and includes inter alia,
bribery and extortion or coercion which involves threats of injury to
person ,property or reputation, and.
―fraudulent practice‖ means a misrepresentation of facts in order to
influence a procurement process or the execution of a contract to the
detriment of the Procuring Entity, and includes collusive practice among
Tenderers (prior to or after Tender submission) designed to establish
Tender prices at artificial non-competitive levels and to deprive the
Procuring Entity of the benefits of free and open competition.
62.3 When either party to the Contract gives notice of a breach of
Contract to the Project Manager for a cause other than those listed under
Sub-Clause 62.2 above, the Project Manager shall decide whether the
breach is fundamental or not.
62.4 Notwithstanding the above, the Procuring Entity may terminate
the Contract for convenience.
62.5 If the Contract is terminated, the Contractor shall stop work
immediately, make the Site safe and secure, and leave the Site as soon as
reasonably possible.
60 | P a g e
Equipment, repatriation of the Contractor‘s personnel employed solely on
the Works, and the Contractor‘s costs of protecting and securing the
Works, and less advance payments received up to the date of the
certificate.
64. Property 64.1 All Materials on the Site, Plant, Equipment, Temporary Works,
and Works shall be deemed to be the property of the Procuring Entity if
the Contract is terminated because of the Contractor‘s default.
65. Release from 65.1 If the Contract is frustrated by the outbreak of war or by any
Performance other event entirely outside the control of either the Procuring Entity or
the Contractor, the Project Manager shall certify that the Contract has
been frustrated. The Contractor shall make the Site safe and stop work as
quickly as possible after receiving this certificate and shall be paid for all
work carried out before receiving it and for any work carried out
afterwards to which a commitment was made.
66. S uspension of 66.1 In the event that the source of financing is suspended to the
Financing Procuring Entity, from which part of the payments to the Contractor are
being made:
(a) The Procuring Entity is obligated to notify the Contractor of such
suspension within 7 days of having received the financing agency‘s
suspension notice.
(b) If the Contractor has not received sums due it within the 28 days
for payment provided for in Sub-Clause 46.1, the Contractor may
immediately issue a 14-day termination notice.
61 | P a g e
SECTION V: CONTRACT DATA SHEET (CDS)
62 | P a g e
C ontr ac t Data S heet
A. General
The Start Date shall be Immediately after signing of the contract and
handover by the Project Manager
The Intended Completion Date for the whole of the Works shall be 24
weeks.
The Site is located at Nomotio, S a m b u r u County
63 | P a g e
The law that applies to the Contract is the Kenyan Law.
8. 15.1 Site Investigation Reports available to the Tenderers are: Not Applicable
9. 22.4 Measures to reduce the risk of HIV Virus; a) Work place sessions by
professionals to workers on HIV
10 . 24.1 & The Site Possession Date shall be after signing of the contract & handover
47.1 by the Project Manager
11. 28.2 Hourly rate of Fees payable to the Adjudicator is as per KIA rates
13. 29.1 Appointing Authority for the Adjudicator: Kenya Institute of Arbitration
B. Time Control
14. 30 .1 The Contractor shall Submit a Programme for the Works within 7 days
after delivery of the Letter of Acceptance and signing of Contract
16. 30 .3 The amount to be withheld by the Project Manager in the case the
contractor does not submit an updated programme is:KES10,000 per
month
S up p ly and Install.
It shall be assumed that all materials supplied shall be installed and used to
construct the specified infrastructure to working condition. The contractor
shall be deemed to have completed the contract works when they
64 | P a g e
provide a ―Working System‖ & mere delivery of materials to site shall not
be payable however removal of materials on site shall require permission
of the employer before removal .
C. Quality Control
D. Cost Control
18. 45.7 Minimum Amount of Interim Payment Certificate will be as per the work
done/ measured on site and at least 10million/milestone delivery as shall
be agreed during contracting stage.
20 . 47.1( a) The Site Possession Date shall be Immediately after signing of the contract
and handover by the Project Manager
22. 51.1 The amount of retention is 10% of value of works of Interim Payment
Certificate‘.
23. 52.1 The rate of liquidated damages is 0.1% of contract price per day
25. 54.1 The amount of advance payment shall be 0 %( A d vanc e p ayment shall
NOT be g ranted) per cent of the contract sum payable by Not ap plicable.
65 | P a g e
26. 55.1 The amount of Performance Security shall be 10% of CONTRACT PRICE
in form of Hard Cash, or a Performance bank Guarantee from a reputable
Commercial Bank acceptable to the Employer, One (1 Number) week after
contract award and before signing of the final contract. The period of the
performance bond shall cover at least the project intended completion
period as described by the employer under Appendix to Conditions of
Contract.
27. 61.1 As built drawings shall be supplied by the contractor by after completion
of works and before the last payment which is not the retention fee.
28. 61.2 The amount to be withheld by the Project Manager in the case the
contractor does not submit as built drawings is: The last payment to the
contractor after completion + the retention fee.
29. 63.1 The percentage to apply to the value of the work not completed,
representing the Procuring Entity's additional cost for completing the
Works, is 15%.
66 | P a g e
SECTION VI - GENERAL MECHANICAL SPECIFICATIONS
67 | P a g e
A. General
This section specifies the general requirement for plant, equipment and materials forming part
of the Subcontract Works and shall apply except where specifically stated elsewhere in the
Specification or on the Contract Drawings.
B. Quality of Materials
All plant, equipment and materials supplied as part of the Sub-contract Works shall be new and
of first class commercial quality, shall be free from defects and imperfections and where
indicated shall be of grades and classifications designated herein.
All products or materials not manufactured by the Sub-contractor shall be products of
reputable manufacturers and so far as the provisions of the Specification is concerned shall be
as if they had been manufactured by the Sub-contractor.
Materials and apparatus required for the complete installation as called for by the Specification
and Contract Drawings shall be supplied by the Sub-contractor unless mention is made
otherwise.
Materials and apparatus supplied by others for installation and connection by the Sub-
contractor shall be carefully examined on receipt. Should any defects be noted, the Sub-
contractor shall immediately notify the
Defective equipment or that damaged in the course of installation or tests shall be rep laced as
required to the approval of the Engineer.
D. Electrical Requirements
Plant and equipment supplied under this Sub-contract shall be complete with all necessary
motor starters, control boards, and other control apparatus. Where control panels
incorporating several starters are supplied they shall be complete with a main isolator.
The supply power up to and including local isolators shall be provided and installed by the
Electrical Subcontractor. All other wining and connections to equipment shall form part of this
Sub-contract and be the responsibility of the Sub-contractor.
68 | P a g e
The Sub-contractor shall supply three copies of all schematic, cabling and wiring diagrams for
the Engineer's approval.
The starting current of all electric motors and equipment shall not exceed the maximum
permissible starting currents described in the Kenya Power and Lighting Company (KPLC) By -
laws.
All electrical plant and equipment supplied by the Sub-contractor shall be rated for the supply
voltage and frequency obtained in Kenya, that is 415 Volts, 50Hz, 3-Phase or 240VoIts, 50Hz,
I-phase.
Any equipment that is not rated for the above voltages and frequencies shall be rejected by the
Engineer.
On arrival at site all plant and equipment shall be examined and any damage to parts and
protective priming coats made good before storage or installation.
Adequate measures shall be taken by the Sub-contractor to ensure that plant and equipment do
not suffer any deterioration during storage.
F. Site Supervision
The Sub-contractor shall ensure that there is an English/Kiswahili-speaking supervisor on the site
at all times during normal working hours.
G. Installation
Installation of all special plant and equipment shall be carried out by the Sub-contractor under
adequate supervision from skilled staff provided by the plant and equipment manufacturer or
his appointed agent in accordance with the best standards of modern practice and to the
relevant regulations and standards described under Clause 2.03 of this Section.
H. Testing
1. G eneral
The Sub-contractor's attention is drawn to Part cc' Clause 1.38 of the "Preliminaries and General
Conditions"
2. Material tests
All material for plant and equipment to be installed under this Sub-contract shall be tested,
unless otherwise directed, in accordance with the relevant B.S Specification concerned.
For materials where no B.S. Specification exists, tests are to be made in accordance with the
best modern commercial methods to the approval of the Engineer, having regard to the
particular type of the materials concerned.
69 | P a g e
The Sub-contractor shall prepare specimens and performance tests and analyses to demonstrate
conformance of the various materials with the applicable standards.
If stock material, which has not been specially manufactured for the plant and equipment
specified is used, then the Sub-contractor shall submit satisfactory evidence to the Engineer that
such materials conform to the requirements stated herein in which case tests of material may be
partially or completely waived. Certified mill test reports of plates, piping and other materials
shall be deemed acceptable.
3. Manufactured Plant and E quipment — Work Tests
The rights of the Engineer relating to the inspection, examination and testing of plant and
equipment during manufacture shall be applicable to the Insurance Companies or Inspection
authorities so nominated by the Engineer.
The Sub-contractor shall give two weeks‘ notice to the Engineer Of the manufacturer's
intention to carry out such tests and inspections.
The Engineer or his representative shall be entitled to witness such tests and inspections. The
cost of such tests and inspections shall be borne by the Sub-contractor.
Six copies of all test and inspection certificates and performance graphs shall be submitted to
the Engineer for his approval as soon as possible after the completion of such tests and
inspections.
Plant and equipment which is shipped before the relevant test certificate has been approved by
the Engineer shall be shipped at the Sub-contractor's own risk and should the test and
inspection certificates not be approved, new tests may be ordered by the Engineer at the Sub-
contractor's expense.
4. Pressure Testing
All pipe work installations shall be pressure tested in accordance with the requirements of the
various sections of this Specification. The installations may be tested in sections to suit the
progress of the works but all tests must be carried out before the work is buried or concealed
behind building finishes. All tests must be witnessed by the Engineer or his representative and
the Sub-contractor shall give 48 hours‘ notice to the Engineer of his intention to carry out such
tests.
Any pipe work that is buried or concealed before witnessed pressure tests have been carried
out shall be exposed at the expense of the Sub-contractor and the specified tests shall then be
applied.
The Sub-contractor shall prepare test certificates for signature by the Engineer and shall keep a
progressive and up-to-date record the section of the work that has been tested.
I. Colour Coding
Unless stated otherwise in the Particular Specification all pipe work shall be colour coded in
accordance with the latest edition of B.S 1710 and to the approval of the Eng ineer or Architect.
J. Welding
1. Preparation
Joints to be made by welding shall be accurately cut to size with edges sheared, flame cut or
machined to suit the required type of joint. The prepared surface shall be free from all visible
defects such as lamination, surface imperfection due to shearing or flame cutting operation,
etc., and shall be free from rust scale, grease and other foreign matter.
2. Method
70 | P a g e
All welding shall be carried out by the electric arc processing using covered electrodes in
accordance with B.S. 639.
Gas welding may be employed in certain circumstances provided that prior approval is
obtained from the Engineer.
71 | P a g e
SECTION VII - PARTICULAR SPECIFICATIONS FOR CHILLERS AND
DETENTITION/SUSPECT COLD ROOMS
72 | P a g e
A. PARTICULAR SPECIFICATIONS FOR DETENTION/SUSPECT COLD ROOM
1. S c ope of Work
The work to be carried out comprises the supply, delivery, installation, testing and commissioning of
Detention/Suspect Chiller room equipment, cold room door, wall, ceiling, floor insulation, control panels
with auxiliary equipment and wall finishes as specified in the material schedule.
2. Desig n C onditions for Detention/Suspect room
Mean ambient temperature: 320C DB
Storage temperature -3oC
Storage humidity (minimum): 80%
Cooling load 10KW
73 | P a g e
The door shall be complete with a door latch, a keyed cylinder lock, a safety door release from inside, self-
closing mechanism, hydraulic door closer. The spring action integrated into the door hinge closes the door
by itself if it is left open less than 90 degree. The hydraulic door closure latches the door tightly to prevent
any cold air leakage.
6. C old room E vaporator
The evaporator shall consist of a cooling coil, air-circulating fan, fan guard, and defrost electric heater
element and a thermostatic expansion valve. The valve shall be pressure equalized and manually
adjustable. A timer unit shall be mounted in the control panel to control both the de-frosting intervals and
defrosting period — both of which shall be variable. The evaporator shall have a cooling load capacity of
10KW.
It shall be ceiling type unit with a drip tray fitted with a drain pipe to the outside of the building. The unit
shall be as GUNTNER or equal and approved.
It shall be provided with suitable and-vibration mountings and an initial oil change in the compressor. The
unit shall be complete with compressor, electric motor, air-cooled condenser of non-ferrous construction,
liquid receiver, all mounted on a common base. The unit shall be as BITZER or equal and approved and
shall be mounted in the adjoining compressor room.
8. Refrigeration Pipework.
Pipework shall be approved copper tubing and fitting and shall be properly fixed in conformity with
Trane Refrigeration Manual‘ or any other manufacturer printed installation instructions. The suction line
shall be insulated with at least 25mm thickness of Armaflex or other approved material, which shall not
have insulating properties inferior to those of cork. The condensing unit shall be approximately 3 meters
from evaporator unit.
-Filter drier
-Sight glass with moisture indicator
-Solenoid valve
-HP cut out
74 | P a g e
The control panel shall be fabricated from mild steel sheet of minimum SWG18 with a hinged door and
then powder coated after manufacture. It shall be provided with an integral lock. It shall be complete
with;
1) Isolator fitted on the door
2) Controlling thermostat with temp range from -3OC to 320C
3) 80mm dial thermometer with temp range from -3OC to 320C
4) Contactors for defrosting Coils
5) Motor starters and current overload relays
6) MCB‘s
7) Phase failure relay with over and under voltage protection
8) Timer switch for defrost control
9) Push buttons for Start and stop
10) Audible and visual high temperature alarm with manual reset
11) The panel shall also have green light running indicators, red "―oor open"‖light and
equipment circuit trip lights.
11. E lec trical Installation
The electrical Contractor shall be responsible for providing power to the control panel and for providing
a local Isolator and connecting power to it. The cold room Contractor shall be responsible for the final
connections to the above equipment, all control wiring and for all wiring within the control panel
12. Testing and & c ommissioning
Before insulation of the suction pipe the refrigeration system shall be tested for pressure and leaks using the
combined pressure and leaks testing method. The refrigeration system shall be charged with R134a
refrigerant and entire system raised to test pressure using nitrogen or other inert gas. The test pressure shall
be twice the working pressure for the system.
Leaks shall be checked using soap bubble followed by using of electronic leak detector. After system is
proved leak proof, it shall be maintained under test pressure for 24 hours. If at the end of this time the
gauge pressure has fallen, the complete system shall be re-tested. After the successful completion of the test,
the system shall be evacuated using vacuum for 24 hours. If there is loss of vacuum the system shall be
dehydrated again and left under vacuum for a further 24 hrs until the system is effectively dehydrated.
After this the system shall be charged with the correct type and quantity of the refrigerant. The system shall
then be set to work and adjusted to ensure that it operates correctly and design conditions are archived. It
shall be left to operate for 72 Hrs and room temperatures recorded for this period using an automatic
room temperature sensor/recorder. The compressor shall be provided with identification plates stating the
type of refrigerant used and the quantity required for the system
75 | P a g e
Mean ambient temperature: 320c DB
Storage temperature - 3OC
Storage humidity (minimum): 80% RH
Cooling load large herds‘ chiller 55KW
Small herds Chillers 37KW
3. V ap our B arrier & Water Proofing
Before the application of the insulation to the structure a vapour barrier shall be applied to the entire
internal surface. This shall consist of an even layer of Flinkote type 3 or equal and approved applied to
manufactures instructions. The top surface of the floor insulation shall be water proofed using asphalt
saturated and coated vapour barrier paper of not more than 0.3 perms permeance or other equal and
approved, lapped at least 80mm and tacked in place. The vapour seal must be approved by the Engineer
before insulation work is commenced.
4. Insulation and Final Wall Finishes
The insulating material shall be polystyrene (or equal and approved) with a conductivity of approximately
0.025 W/MOC and density of approx. 25Kg/m 3 for the Walls and ceiling and 40Kgs/m3 for the floor. It
shall be applied in two layers each 75 mm thick with the second layer breaking joints with the first layer.
Care must be taken to avoid breaking the vapour seal when fixing the insulation. Two more coats of
vapour seal shall then be applied after application of insulation
Hardwood battens shall be provided at regular intervals between insulators. Aluminium sheet shall be fixed
as specified on the drawing shall be secured on the wall. The contractor shall then finish Off the floor with
slip guard patterned aluminium checker plate reinforced with polyurethane floor panel with GI steel sheet
finish topped with I .5 mm aluminium checker plate.
5. Insulated Door
The door and frame shall be fabricated from heavy seasoned timber and insulated with two layers of
75mm thick polystyrene sand-witched between 10mm thick seasoned wood strips. The door size shall be
2000 x 2100 mm high being hinged on one side so that it opens outward. The door shall be completed
with sufficient gaskets to ensure an air tight seal. The door shall be fitted with automatic plunger type
switches for operating the fan motors and interior lights such that when it is open, the light shall go on and
the fan shall stop, and when it is closed, the lights shall go off and the fan shall start.
The door shall be such that it can be padlocked from outside but with an inside release such that it can be
opened from inside even when padlocked. All metal parts on the door shall be chrome plated.
The door shall be complete with a door latch, a keyed cylinder lock, a safety door release from inside, self-
closing mechanism, hydraulic door closer. The spring action integrated into the door hinge closes the door
by itself if it is left open less than 90 degree. The hydraulic door closure latc hes the door tightly to prevent
any cold air leakage.
6. C hiller room E vaporators
The evaporator shall consist of a cooling coil, air-circulating fan, fan guard, and defrost electric heater
element and a thermostatic expansion valve. The valve shall be pressure equalized and manually
adjustable. A timer unit shall be mounted in the control panel to control both the de-frosting intervals and
defrosting period — both of which shall be variable. The evaporators shall have a cooling loads capacity
of; large herd‘s chiller 55kw and small herd‘s chiller 38KW.
It shall be ceiling type unit with a drip tray fitted with a drain pipe to the outside of the building. The unit
shall be as GUNTNER or equal and approved.
7. C hiller room C ondensing Unit
76 | P a g e
The condensing unit shall be of capacity to match with the chiller room evaporator-cooling load while
using refrigerant R134a under specified conditions or any other non-ozone depleting refrigerant. The unit
shall be air-cooled semi hermetic with automatic capacity control for evaporator demand.
It shall be provided with suitable anti-vibration mountings and an initial oil change in the compressor. The
unit shall be complete with compressor, electric motor, air-cooled condenser of non-ferrous construction,
liquid receiver, all mounted on a common base. The unit shall be as BITZER or equal and approved and
shall be mounted in the adjoining compressor room.
8. Refrigeration Pipework.
Pipework shall be approved copper tubing and fitting and shall be properly fixed in conformity with Trane
Refrigeration Manual' or any other manufacturer printed installation instructions. The suction line shall be
insulated with at least 25mm thickness of Armaflex or other approved material, which shall not have
insulating properties inferior to those of cork. The condensing unit shall be approximately 3 meters from
evaporator unit.
9. Refrigeration C omponents
The system shall be provided with the following components all similar to or equal to those manufactured
by
DANFOSS
- Filter drier
- Sight glass with moisture indicator
-Solenoid valve
-HP/LP cut out
77 | P a g e
11. E lec trical Installation
The electrical Contractor shall be responsible for providing power to the control panel and for providing a
local Isolator and connecting power to it. The cold room Contractor shall be responsible for the final
connections to the above equipment, all control wiring and for all wiring within the control panel.
12. Testing and C ommissioning
Before insulation of the suction pipe the refrigeration system shall be tested for pressure and leaks using the
combined pressure and leaks testing method. The refrigeration system shall be charged with R134a
refrigerant and entire system raised to test pressure using nitrogen or other inert gas. The test pressure shall
be twice the working pressure for the system.
Leaks shall be checked using soap bubble followed by using of electronic leak detector. After system is
proved leak proof, it shall be maintained under test pressure for 24 hours. If at the end of this time the
gauge pressure has fallen, the complete system shall be re-tested. After the successful completion of the test,
the system shall be evacuated using vacuum for 24 hours. If there is loss of vacuum the system shall be
dehydrated again and left under vacuum for a further 24 hrs until the system is effectively dehydrated.
After this the system shall be charged with the correct type and quantity of the refrigerant. The system shall
then be set to work and adjusted to ensure that it operates correctly and design conditions are archived. It
shall be left to operate for 72 Hrs and room temperatures recorded for this period using an automatic
room temperature sensor/recorder. The compressor shall be provided with identification plates stating the
type of refrigerant used and the quantity required for the system
78 | P a g e
SECTION VII: DRAWINGS
79 | P a g e
SECTION VIII: BILLS OF QUANTITIES AND SCHEDULE OF UNIT RATES
80 | P a g e
1. G E NE RA L NOTE S TO TE NDE RE RS ……………………….…………………………86
2. S TA TE ME NT OF C OMPLIA NC E ……………………………………………………...87
2.
3. B ILLS OF QUANTITIES………………………………………………….88 - 112
4. G RA ND S UMMA RY PA G E …………………………………………………………….113
A. GENERAL NOTES
1) The Bills of Quantities form part of the contract documents and are to be read in conjunction with the
contract drawings and general specifications of materials and works.
2) The prices quoted shall be deemed to include for all obligations under the sub-contract including but not
limited to supply of materials, labour, delivery to site, storage on site, installation, testing, commissioning
and all taxes (including 14% VAT).
3) In ac cordance with G overnment p olicy, the 14% V AT and 3% Withholding Tax shall be deducted from
all p ayments made to the Tenderer, and the same shall be forwarded to the Kenya Revenue A uthority
( KRA).
4) 3 A ll p rices omitted from any item, section or p art of the B ills of Quantities shall be deemed to have been
inc luded to another item, section or p art thereof.
5) The brief description of the items given in the Bills of Quantities are for the purpose of establishing a
standard to which the sub-contractor shall adhere. Otherwise alternative brands of equal and approved
quality will be accepted.
6) S hould the sub-contractor install any material not specified here in before r eceiving written approval
fr om the Project Manager, the sub-contractor shall r emove the material in question and, at his own c ost,
install the proper material.
7) The grand total of prices in the price summary page must be carried forward to the Form of Tender for
the tender to be deemed valid.
8) Tenderers must enclose, together with their submitted tenders, detailed manufacturer's Brochures detailing
9) Tec hnical Literature and specifications on all the equipment they intend to offer.1.
81 | P a g e
B. Statement of Compliance
1. I confirm compliance of all clauses of the General Conditions, General Specific ations and Particular
Specifications in this tender.
2. I confirm I have not made and Will not make any payment to any person, which can be perceived as
an inducement to win this tender.
Date:………………………………………………………………………………………………
82 | P a g e
C. BILLS OF QUANTITIES
1. B ILLSNo. 1: PRICING OF PRELIMINARIES ITEMS
Prices will be inserted against item of preliminaries in the sub-contractor's Bills of Quantities and specification.
These Bills are designated as Bill I in this Section. Where the sub-contractor fails to insert his price in any item
he shall be deemed to have made adequate provision for this on various items in the Bills of Quantities. The
preliminaries form part of this contract and together with other Bills of Quantities covers for the costs
involved in complying with all the requirements for the proper execution of the whole of the works in the
contract.
The Bills of Quantities are divided generally into three sections:-
a. Preliminaries — B ill I
Sub-contractors preliminaries are as per those described in section C — sub-contractor preliminaries and
conditions of contractor. The sub-contractor shall study the conditions and make provision to cover their cost
in this Bill. The number of preliminary items to be priced by the Tenderer has been limited to tangible items
such as site office, temporary works and others. However the Tenderer is free to include and price any other
items he deems necessary taking into consideration conditions he is likely to encounter on site.
83 | P a g e
BILL No. 1 PRELIMINARIES
RATE AMOUNT
ITEM DESCRIPTION QTY UNIT (KSHS) (KSHS)
2 Conditions of sub-contract
3 Agreement clause 1.03
4 Payments clause l .04
5 Site location clause 1.06
6 Scope of Contract Works clause
1.08
Extent of the Contractor's
7
Duties clause 1.09
8
Firm price contract clause 1.12
9
Variation clause 1.13
Prime cost and provisional sum
clause 1.14 (insert profit and
attendance which is a
percentage of expended PC or
provisional sum.)
10 Bond clause 1.15
11 Government Legislation and
Regulations clause 1.16
84 | P a g e
SUB-TOTAL CARRIED TO PAGE 91
RATE AMOUNT
ITEM DESCRIPTION QTY UNIT (KSHS) (KSHS)
85 | P a g e
RATE AMOUNT
ITEM DESCRIPTION QTY UNIT (KSHS) (KSHS)
COLLECTIONS
Sub-total from above
Sub-total brought forward from page 84
Sub-total brought forward from page 85
86 | P a g e
2. B ILL NO. 2: RE FRIGERATION WORKS
Core material shall be non-toxic, does not release gases in a fire and
has a smoke developed rating of zero. It is also water repellent, free of
(H) CFCs and recyclable.
a) Non hygroscopic.
b) Fire-Retardant
c) K-value of 0.035W/M2K
d) 20microns White Polyester Silicon coating ( food quality)
e) sizes : 3400mm x 2500mm UL listed /FM approved
Insulated doors
2000mm x 2100mm high double leaf swing type outward opening
door made out of 150mm thick fire Rated HF (hidden fastener)
B
insulated panels factory-assembled with a fire resistant mineral fiber
core bonded with metal facings, suitable for fire rated wall Panels to
achieve three hour fire resistance ratings with a unique hidden fastener
for increased aesthetic sound attenuated, Core material shall be non-
toxic, does not release gases in a fire and has a smoke developed
rating of zero. It is also water repellent, free of (H) CFCs and
recyclable. Insulating
value as show below
a) Non hygroscopic
b) Fire-Retardant
c) R-value of 0.035W/M2K
d) 20microns White Polyester Silicon coating ( food quality)
e) UL listed /FM approved I
The Door shall made complete with a chiller room door lock and
automatic electric sliding mechanism. and lighting micro switches
4 No
Ditto but door size 900x2100mm high
2 No
87 | P a g e
TOTAL CARRIED TO COLLECTION PAGE 91
A The top surface of the floor insulation shall be water proofed using
SIKA Polyurethane adhesive sealant and coated vapour barrier paper
of not more than 0.3 perms permeance or other equal and approved,
250 SM
lapped at least 80mm and tacked in place.
B Wall assembly material for the above wall and ceiling panels. 1 Item
C Package Condensing unit
1) Rating 55kw cooling Load
2) Refrigerant: R134A or R404,
3) 3) Voltage 415 V 50Hz
Complete with compressor, fan and all the accessories control and
control panel as Guntner GCDC-V shaped condensing unit or Equal 2 No
and approved-Note; The condensing unit casing must be made of
non-rusting material suitable for coastal environment.
D
Evaporator unit
1) rating : 55kw cooling Load
2) Refrigerant: R134A or R404
3) ceiling mounted 4)V01tage 415 V 50Hz complete with
compressor, fan and all the accessories control and control panel As
BITZER evaporator unit or Equal and approved
2 No
88 | P a g e
TOTAL CARRIED TO COLLECTION PAGE 91
Control Panel
A Intelligent digital chiller room control panel manufactured by the
cooling unit’s manufacturer complete with all automatic controls and
all fault alarms. The panel shall be BMS ready on Modbus/Bacne TCP-
IP open protocol 1 No
O
B Chiller room Wi-Fi temperature and humidity data logger -3 C to
+80% complete with probes, a cable connection to a PC and provision
2 No
for GSM sim card slot.
C 20 No
65W vapour proof light fittings
D 2 No
Solenoid valve
E 2 No
Filter drier
F 2 No
Low and high cut-out switch
G 2 No
Low pressure gauge
H 2 No
High pressure gauge
Refrigerant Pipework
I 60 LM
Refrigeration pipework complete with armaflex 50mm
Insulation
Refrigerant
J
Allow for the charging of the refrigeration system with necessary
amount of refrigerant for initial testing and eventual operation of the 1 Item
chiller room.
Anti-Vibration Mountings
L
Anti-Vibration Mountings for the condensing unit as
WOODS P.N.50417 or equal and approved
89 | P a g e
1 Item
90 | P a g e
Associated Electrical Works
A Allow for electrical works including but not limited to wiring and
conduits from the local isolator provided by others within 5metres in
1 Item
the machine room to the control panel, condenser and evaporator. It
shall include a push and turn safety switch near the machines in the
machine room for isolation during servicing and maintenance.
AMOUNT
91 | P a g e
ITEM DESCRIPTION (KSHS)
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
92 | P a g e
BILL NO 2. Chiller Room 2 Installation
Wall Insulations
150mm thick fire Rated HF (hidden fastener)
A Core material shall be non-toxic, does not release gases in a fire and
has a smoke developed rating of zero. It is also water repellent, free of
(H) CFCs and recyclable.
a) Non hygroscopic
b) Fire-Retardant
c) R-value of 0.035W/M2K
d) 20microns White Polyester Silicon coating ( food quality)
d) sizes : 3400mm x 2500mm UL listed /FM approved
200 SM
Insulated door
2000mm x 2100mm high double leaf swing type outward opening
B
door made out of 150mm thick fire Rated Hi (hidden fastener)
insulated panels factory-assembled with a fire resistant mineral fiber
core bonded with metal facings, suitable for fire rated wall Panels to
achieve three hour fire resistance ratings with a unique hidden
fastener for increased aesthetic sound attenuated, Core material shall
be non-toxic, does not release gases in a fire and has a smoke
developed rating of zero. It is also water repellent, free of (H) CFCs
and recyclable. Insulating value as show below
a) Non hygroscopic
b) Fire-Retardant
c) R-value of 0.035W/M2K
d) 20microns White Polyester Silicon coating ( food quality)
e) UL listed /FM approved I
The Door shall made complete with a chiller room door lock and
1 No.
lighting micro switches
93 | P a g e
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
(KSHS) (KSHS)
Wall assembly material for the above wall and ceiling panels 1 Item
B Package Condensing unit
I) rating 37kw cooling Load
2) Refrigerant: R134A or R404,
3) Voltage 415 V 50Hz
Complete with compressor, fan and all the accessories control and
control panel as Guntner GCDC-V shaped condensing unit or
C
Equal and approved-Note; The condensing unit casing must be made
of non-rusting material suitable for coastal environment. 1 No.
Evaporator unit
I) rating : 37kw cooling Load
2) Refrigerant: R134A or R404
3) Ceiling mounted 4) Voltage 415 V 50Hz
complete compressor, fan and all the accessories control and control
D 1 No.
panel As BITZER evaporator unit or Equal and approved
98 | P a g e
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
(KSHS) (KSHS)
Control Panel
A Intelligent digital chiller room control panel manufactured by the
cooling unit’s manufacturer Complete with all automatic controls
1 No
and all fault alarms. The panel shall be BMS ready on
Modbus/Bacnet TCP-IP open protocol
B chiller room Wi-Fi temperature and humidity data logger -IOC to +
IOC complete with probes, a cable connection to a PC and provision
2 No
for GSM sim card slot
C 20 No
65W vapour proof light fittings
D 2 No
Solenoid valve
E 2 No
Filter drier
F 2 No
Low and high cut-out switch
G 2 No
Low pressure gauge
H 2 No
High pressure gauge
Refrigerant Pipework
I 60 LM
Refrigeration pipework complete with armaflex 50mm Insulation
Refrigerant
J
Allow for the charging of the refrigeration system with necessary
amount of refrigerant for initial testing and eventual operation of the 1 ITEM
chiller room.
Anti-Vibration Mountings
Anti-Vibration Mountings for the condensing unit as WOODS
K 1 ITEM
P.N.50417 or equal and approved.
99 | P a g e
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
(KSHS) (KSHS)
A Allow for electrical works including but not limited to Wiring and
conduits from the local isolator provided by others within 5metres in
the machine room to the control panel, condenser and evaporator. It
shall include a push and turn safety switch near the machines in the 1 Item
machine room for isolation during servicing and maintenance.
100 | P a g e
COLLECTION PAGE FOR CHILLER ROOM 2 INSTALLATION
Bill No.2 for total Cost for a chiller room installation works carried forward to grand
summary page 113
101 | P a g e
3. B ILL NO.3-FREEZER ROOM ( NOT TO B E QUOTED)
102 | P a g e
BILL No.3-Freezer Room
Freezer Room Installation: ( Contractors adviced
not to quote for this item)
Wall Insulations
A
150mm thick fire Rated HF (hidden fastener) insulated
panels factory-assembled with a fire resistant mineral
fiber core bonded with metal facings, suitable for fire
rated wall Panels achieve three hour fire resistance
ratings with a unique hidden fastener for increased
aesthetic sound attenuated, insulating value as show
below.
Core material shall be non-toxic, does not release gases
in a fire and has a smoke developed rating of zero. It is
also water repellent, free of (H) CFCs and recyclable.
a) Non hygroscopic 0 SM
b) Fire-Retardant
c) K-value of 0.035W/M2K
d) 20microns White Polyester Silicon
coating ( food quality)
d) sizes : 3400mm x 2500mm UL listed /FM approved
103 | P a g e
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
(KSHS) (KSHS)
Insulated door
104 | P a g e
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
C 0 Item
Wall assembly material for the above wall and ceiling panels
105 | P a g e
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
Evaporator unit
A 1) rating : 80kw cooling Load
2) Refrigerant: R134A or R404
3) ceiling mounted
4) Voltage 415 V 50Hz
complete with compressor, fan and all the accessories control and 0 No
control panel As BITZER evaporator unit or Equal and approved
Control Panel
Intelligent digital Freezer room control panel manufactured by the
B
cooling unit’s manufacturer complete with all automatic controls
and all fault alarms. The panel shall be BMS ready on 0 No
Modbus/Bacnet TCP-IP open protocol
Freezer room Wi-Fi temperature and humidity data logger -200C to
C
+390C complete with probes, a cable connection to a PC and
provision for GSM sim card slot 0 No
D 65W vapour proof light fittings 0 No
E Solenoid valve 0 No
F Filter drier 0 No
G Low and high cut-out switch 0 No
H Low pressure gauge 0 No
I High pressure gauge 0 No
Refrigerant Pipework
J Refrigeration pipework complete with armaflex 50mm Insulation 0 LM
Refrigerant
K Allow for the charging of the refrigeration system with necessary
amount of refrigerant for initial testing and eventual operation of
0 Item
the freezer room.
Stationary
Laptop computers
L
Laptop computers as per the particular specification provided
0 Item
Anti-Vibration Mountings
M
Anti-Vibration Mountings for the condensing unit as
0 Item
WOODS P.N.50417 or equal and approved
106 | P a g e
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
107 | P a g e
COLLECTION PAGE FOR FREEZER ROOM INSTALLATION WORKS
AMOUNT
(KSHS)
ITEM DESCRIPTION
BILL NO.3 FOR TOTAL COST FOR FREEZER ROOM INSTALLATION WORKS
CARRIED FORWARD TO GRAND SUMMARY PAGE 113
108 | P a g e
4. B ILL NO 4. S USPECT COLD ROO
109 | P a g e
TOTAL CARRIED TO COLLECTION PAGE 112
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
Evaporator unit
D
I) rating : 10kw cooling Load
2) Refrigerant: R134A or R404
3) ceiling mounted 4)
Voltage 415 V 50Hz complete with compressor, fan
and all the accessories control and control panel As 1 No.
BITZER evaporator unit or Equal and approved
110 | P a g e
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
Control Panel
A Intelligent digital cold room control panel manufactured by the
cooling units’ manufacturer Complete with all automatic
controls and all fault alarms. The panel shall be BMS ready on
Modbus/Bacnet TCP-IP open protocol 1 No
Refrigerant Pipework
I
Refrigeration pipework complete with armaflex 50mm
Insulation 60 LM
Refrigerant
J Allow for the charging of the refrigeration system with
necessary amount of refrigerant for initial testing and eventual
1 Item
operation of the freezer room.
Anti-Vibration Mountings
L
Anti-Vibration Mountings for the condensing unit as WOODS
P.N.50417 or equal and approved. 1 Item
111 | P a g e
RATE AMOUNT
(KSHS) (KSHS)
ITEM DESCRIPTION QTY UNIT
A Allow for electrical works including but not limited to Wiring and
conduits from the local isolator provided by others within 5metres in
1 Item
the machine room to the control panel, condenser and evaporator. It
shall include a push and turn safety switch near the machines in the
machine room for isolation during servicing and maintenance.
C Allow for a sum of Kenya shillings FOUR Hundred Thousand only for
project management expenses, stationery, airtime and transport to and
1 LS 400,000 400,000
from Nairobi for inspection and site visits for mechanical Engineer
(specialist).
D Allow for setting to work, testing and commission of the cold room 1 Item
installation to the satisfaction of the Project Engineer
112 | P a g e
COLLECTION PAGE FOR SUSPECT COLD ROOM INSTALLATION WORKS
AMOUNT
(KSHS)
ITEM DESCRIPTION
BILL NO.4 FOR TOTAL COST FOR SUSPECT COLD ROOM INSTALLATION
WORKS CARRIED FORWARD TO GRAND SUMMARY PAGE 113
113 | P a g e
GRAND SUMMARY PAGE FOR REFRIGERATION INSTALLATION WORKS
AMOUNT
(KSHS)
ITEM DESCRIPTION
2 Bill No I for total cost of large herds chiller room installation works from page 96
3 Bill No.2 for total cost for small herds chiller room installation works from page 101
4 Bill no.3 for total cost for freezer room installation works from page 107
5 Bill no.4 for total cost for suspect cold room installation works from page 112
Total Cost for refrigeration installation works carried forward to the Form of Tender
Amount in Words:
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
Tenderer’s Name and Stamp•
Sub contract period. Weeks
Signature Date: ……………………………………………………
PIN NO. . VAT CERTIFICATE No.
(Provide copy) (Provide copy)
Witness Address:
114 | P a g e
5. S C HEDULE OF UNIT RATES
RA TE
ITE M DE S C RIPTION UNIT ( KS HS )
No.
1. 80kw Evaporator for the blast freezer
No.
2. 55kw Evaporator for the chiller
No.
3. 37 Evaporator for the chiller
No.
4. 10kw Evaporator for suspect cold room.
No.
5. 80kw Condensing unit for the blast freezers
No.
6. 55kw Condensing unit for the chillers
No.
7. 37kw Condensing unit for the chillers
No.
8. 10kw Condensing unit for suspect cold room.
No.
9. Control panel
No.
10. Centrifugal Fan
No
11. Pressure Gauge
115 | P a g e
SECTION IX: STANDARD FORMS
116 | P a g e
A. Form of Tender
Dear Sir,
2. We undertake, if our tender is accepted, to commence the Works as soon as is reasonably possible
after the receipt of the Employer‘s Representative‘s notice to commence, and to complete the
whole of the Works comprised in the Contract within the time stated in the Appendix to
Conditions of Contract.
3. We agree to abide by this tender until at least the period as stipulated under One Hund r ed Tw enty
( 120number) d ays ) after the d ate of Tender Opening/stip ulated submission Dead line , and it shall
remain binding upon us and may be accepted at any time before that date.
4. Unless and until a formal Agreement is prepared and executed this tender together with your
written acceptance thereof, shall constitute a binding Contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may receive;
3.
6. With our signature, we attest that we have not been debarred in the past by the Public
Procurement Regulatory Authority in line with PPDA 2015, the procuring entity, the EU to
participate in this tender and we have not been associated in the inception phase of this project.
Witness;
Name_____________________________________________________________________________
117 | P a g e
Address___________________________________________________________________________
Signature______________________________________________________________ ____________
Date______________________________________________________________________________
( Amend accordingly if provided by Insurance Company)
B. Tender-Securing Declaration
Tender No.:………………….
We accept that we will automatically be suspended from being eligible for Tendering in any contract
with the Procuring Entity for the period of time of 24 months starting on conclusion of this
procurement process, if we are in breach of our obligation(s) under the Tender conditions, because
we;
a) Have withdrawn our Tender during the period of Tender validity specified in the Form of Tender;
or
b) Having been notified of the acceptance of our Tender by the Procuring Entity during the period of
Tender validity,
(i). Fail or refuse to execute the Contract, if required, or
(ii). Fail or refuse to furnish the Performance Security, in accordance with the ITT.
118 | P a g e
We understand this Tender Securing Declaration shall expire if we are not the successful Tenderer,
upon the earlier of;
1) Our receipt of your notification to us of the name of the successful Tenderer; or
2) Thirty days after the expiration of our Tender.
Witness;
Name_____________________________________________________________________________
Address___________________________________________________________________________
Signature___________________________________________________________________ _______
Date______________________________________________________________________________
119 | P a g e
C. Qualification Information
(To complete parts 1, 2 and 3 where/as appropriate
……………………………………………………………………………………………………
Full address of tenderer to which tender correspondence is to be sent (unless an agent has been
appointed below);
………………………………………………………………………………………………………
………………………………………………………………………………………………………
Telex of tenderer;
………………………………………………………………………………………………………
Name of tenderer‘s representative to be contacted on matters of the tender during the tender
period;
………………………………………………………………………………………………………
Details of tenderer‘s nominated agent (if any) to receive tender notices. This is essential if the
tenderer does not have his registered address in Kenya (name, address, telephone, telex);
………………………………………………………………………………………………………
2. Tend erers C ap ac ity - Ind ivid ual Tend er er s or Ind ivid ual Member s of Joint V entur es
Place of registration:
_____________________________________________________________________
120 | P a g e
Principal place of business
______________________________________________________________________
2.2 Total annual volume of construction work performed in the last ten years
2.3 Work performed as Main Contractor on works of a similar nature and volume over
the last ten years. This may be attached as a separate list but with all the required
information. To be c onsidered for evaluation, this information should be sup p or ted
with ( 1) A ward letters/C ontr ac ts c lear ly stating the value of w or k s in question,
( 2) Work C omp letion c er tific ates. This information should be 3rd party verifiable.
2.4 Major items of Contractor‘s Equipment proposed for carrying out the Works. List all
information requested below. Tenderers may provide a separate attachment but
with all the required information in the form of (1) Lease agreement for leased
equipment, or(2 Ownership document for owned equipment – Logbooks for
movable equipment or purchase receipts for equipment without logbooks. This
information should be 3rd party verifiable.
121 | P a g e
2.5 Qualifications and experience of key personnel proposed for administration and
execution of the Contract in line with evaluation requirements under Tender Data
Sheet. Also attach biographical data. Tenderers may provide a separate attachment
but with all the required information in the form of (1) A CV clearly describing the
person, (2) Copies of Academic Certificates
Project Manager
2.6 Financial reports for the last five years: balance sheets, profit and loss statements,
auditor‘s reports, etc. List below and attach copies
This should be in line with information requested under Tender Data Sheet
2.7 Evidence of access to financial resources to meet the qualification requirements: cash
in hand, lines of credit, etc. List below and attach copies of supportive documents.
Not Applicable
2.8 Proposed Credit Period (In calendar days). This shall form part of the conditions of the
contract.
Not Applicable
2.9 Name, address and telephone, telex and facsimile numbers of banks that may provide
reference if contacted by the Employer.
2.10 Statement of compliance with the requirements of Clause 1.2 of the Instructions to
Tenderers.
Not Applicable
122 | P a g e
Name of Firm or Partner of a joint venture
Firms, including each of the partners of a joint venture, should provide information on
any history of litigation or arbitration resulting from contracts executed in the last five
years or currently under execution. A separate sheet should be used for each partner
of a joint venture
Year Award for or Name of client, cause of litigation and Disputed amount
matter in dispute (current value,
against Firm
Kshs.)
2.12 Proposed program (work method and schedule) for the whole of the Works in line
with Tender Data Sheet
Not Applicable
2.1 The information listed in 2.1 –2.11 above shall be provided for each partner of the joint
venture.
2.2 The information required in 1 & 2.13 above shall be provided for the joint venture.
2.3 Attach the power of attorney of the signatory(ies) of the tender authorizing signature of the
tender on behalf of the joint venture
2.4 Attach the Agreement among all partners of the joint venture ( and which is legally binding on
all partners), which shows that:
a) all partners shall be jointly and severally liable for the execution of the Contract in
accordance with the Contract terms;
b) one of the partners will be nominated as being in charge, authorized to incur liabilities
and receive instructions for and on behalf of any and all partners of the joint venture;
and
c) the execution of the entire Contract, including payment, shall be done exclusively with
the partner in charge.
123 | P a g e
D. Confidential Business Questionnaire
You are requested to give the particulars indicated in Part 1 and either Part 2 (a), 2 (b) or 2 (c) and 2
(d) whichever applies to your type of business.
You are advised that it is a serious offence to give false information on this Form.
Part 1 – G eneral
Country/Town……………………………………………………………………………………………….
Nature of Business…………………………………………………………………………………………..
Maximum value of business which you can handle at any time: KES …………………………………..
Branch…………………………………………………………………………………………………………
124 | P a g e
Give details of partners as follows:
125 | P a g e
Part 2( c ) – Reg istered C omp any:
Issued Kshs……………………………………………………………………………………………………
Is there any person / persons in …………… ( Name of Employer) who has interest in this firm?
Yes/No………………… ( Delete as necessary)
126 | P a g e
E. Code of Ethics
C OMMITME NT TO THE C ODE OF E THIC S
This code may be cited as the Code of Ethics for Suppliers in Public Procurement & Disposal
1. Interp retation
In this c od es, unless the c ontex t other w ise r equir es -
―The A c t‖ ME A NS The Public Procurement and Disposal Act, 2005 or any amendment or modification
thereof
―C and id ate‖ means a person who has obtained the tender documents from a public entity pursuant to
an invitation notice by a procuring entity
―C od e of E thic s‖ means a statement encompassing the set of rules based on values and the standards of
conduct to which suppliers are expected to conform
―C onsultant‖ is a person who provides services of predominantly intellectual, technical or advisory
nature
―C ontrac tor‖ means a person who enters into a procurement contract with a procuring entity to supply
goods, works or services, and includes the main contractor
―E thic s‖ means values, customs, rules or principles, which govern right conduct
―G ift‖ has meaning assigned to it in the Leadership and Integrity Regulations, 2015
―Integ rity‖ means the quality of being honest and having strong moral and ethical principles
―Persons‖ has meaning assigned to it in Article 260 of the Constitution and includes sole proprietorship
―Proc uring E ntity‖ means a public entity making a procurement to which the Public Procurement and
Disposal Act, 2005 or any amendment or modification thereof applies
―Public Offic er ‖ has the meaning assigned to it in Article 260 of the Constitution
―Reg ulatio ns‖ means regulations made under the Public Procurement and Disposal Act, 2005 or any
amendment or modification thereof
―S tate Offic er ‖ has the meaning assigned to it in Article 260 of the Constitution.
―S up p lier‖ means a candidate, bidder, and tenderer, Contractor, service provider or a consultant.
―Tend erer‖ means a person who submitted a tender pursuant to an invitation by a public entity
For purposes of this Code, all terms used, unless expressly defined herein, have the meaning assigned to
them in the Act.
(i) This Code of Ethics is applicable to suppliers participating in public procurement or disposal of
public assets.
(ii) The objective of the Code is to set minimum standards of ethical behaviour for Suppliers to
ensure compliance with the Act and the Regulations and the adoption of good business
practices.
127 | P a g e
3. Laws and Reg ulations
(i) All public procurement & disposal shall be undertaken in accordance with the values and
principles of the Constitution of Kenya, 2010 (Article 10)
(iii) Suppliers shall observe other laws, regulations, rules and practices relating to taxation, labour,
health and safety standards as well as environmental protection.
4. Professionalism
(i) Suppliers are required to comply with professional standards of their industry or of any
professional body of which they are members. Where a supplier is a member of a professional
body, the Supplier shall uphold the code of ethics of the respective profession and be of good
standing.
(ii) Suppliers shall maintain the highest standards of integrity and professionalism in their
operations.
(iii) Suppliers in public procurement shall accord mutual respect and courtesy to the public officer(s)
and other suppliers without compromising their independent and distinct roles.
(iv) Public procurement & disposal activities shall be undertaken with the objective of meeting the
closest public scrutiny.
5. Imp artiality
A supplier shall not engage in acts aimed at encouraging patronage, tribalism, cronyism and nepotism.
(i) A supplier shall not offer or give gifts of any kind to public entities and/or the employees.
(ii) No supplier shall contact, unduly influence or exert pressure on any member of a committee or
any other employee of a procuring entity to take a particular action which favours or tends to
favour them.
(iii) A supplier shall not engage in fraudulent, collusive, or corrupt practices, or inappropriate
influences.
(iv) A supplier shall not act inappropriately by attempting to interfere with the procurement
process
7. C onflic t of Interest
(i) A supplier shall not accept contracts which would constitute a conflict of interest with any
prior or current contract. Suppliers shall disclose to all concerned parties those conflicts of
interest that cannot be reasonably avoided.
(ii) A supplier shall not enter into a contract with a procuring entity if the supplier is:
o An employee of the procuring entity or a member of a board or committee of the
procuring entity;
o A State Officer, public Officer or a member of a board or committee of the
Government or any department of the Government or a person appointed to any
position by the President or a Cabinet Secretary;
o A person, including a corporation, who is related to a person described in paragraph
(i) or (ii). A relative has meaning assigned to it in section 33(2) of the Public
128 | P a g e
Procurement and Asset Disposal Act, 2015 or any amendment or modification thereof
applies;
o Debarred from participating in procurement proceedings.
8. Performanc e of Duties
8.1. A supplier shall:
(i) Duly sign this code of ethics and include it in a tender, proposal or quotation submitted.
(ii) Obtain and submit bid documents in the manner prescribed in the tender notice and tender
documents
(iii) Supply the right quantity and quality of the contracted item and deliver at the stipulated
time(s) and shall not abandon the work that they have been contracted to do.
(i) Ensure that their deliverables provide value for money in terms of cost, quality, quantity and
timeliness of the delivered works, goods or services.
(ii) Ensure that competent persons carry out the contractual obligations of the supplier.
(iii) Accept full responsibility for all works, services or supplies provided
8.5. A supplier shall not
(i) Obstruct or hinder an officer of the Authority or any other authorized person from carrying
out a duty or function or exercising a power relating to procurement and disposal.
(ii) Knowingly or in collusion with others lie to or mislead a person carrying out a duty or function
or exercising a power relating to procurement and disposal.
9. C ommunic ation and A c c urac y of Infor mation
A supplier shall:
(i) Observe strict communication limitations during the bidding process and as provided for in the
Act
(ii) Respond promptly and courteously to all proper requests for information, clarifications,
complaints or enquiries from procuring entities, the Authority or any law enforcement agency.
(iii) Ensure that all information provided to procuring entities is given in writing by Authorized
Officers.
(iv) Ensure that certified copies of all mandatory certificates are availed
(v) Ensure that information given while participating in public procurement or disposal is true,
accurate and fair, and not designed to mislead.
10. C onfid entiality
Information obtained in the course of performance of a procurement contract in shall not be
disclosed to unauthorized persons and shall not be used for the Supplier‘s advantage or
material gain or for furtherance of private interest. The obligation to preserve the confidential
information continues even after the business/contractual relationship with the Procuring Entity
ends.
129 | P a g e
11. Duty to rep ort imp rop riety/c orrup tion
A supplier shall reject and report to the PPOA and/or the relevant agency any procurement
practice which might be deemed improper.
130 | P a g e
15.1. I ………………………………………………………………………………………. (Supplier)
Confirm that I have read and fully understood the contents of the Public Procurement & Asset
Disposal Act 2015 and the Code of Ethics for Suppliers and my responsibilities under the Code.
15.2. I also certify that I am duly authorized to sign this Code on my own behalf and on behalf of
my organization, and agree to comply with the Code of Ethics.
Name…………………………………………………Sign
…………………………………………………………
Position……………………………………………………………………………………………………………
…
Office
address………………………………………Telephone……………………………………………………
E-
mail…………………………………………………………………………………………………………………
Name of the
Firm……………………………………………………………………………………………………
Sworn
at……................………………………………………………………………………………………….....
By the
said………………………………...……………………………………………………………..................
Deponent
This……………………………………………day of………………………………………………20……….…
131 | P a g e
F. Letter of Acceptance
[ date]
This is to notify you that your Tender dated [ date] for execution of the [ name of the Contract and
identification number, as given in the Contract Data Sheet] for the Contract Price of the equivalent of
[ amount in numbers and works] [ name of currency ], as corrected and modified in accordance with the
Instructions to Tenderers is hereby accepted by us.
We confirm that [ insert name proposed by the procuring entity] to be the Adjudicator.
You are hereby instructed to proceed with the execution of the said works in accordance with the
Contract documents.
Authorized Signature:
Name of Agency:
132 | P a g e
G. Form of Contract Agreement
This Agreement, made the [ day] day of [ month], [ year] between [ name and address of Procuring
Entity] (hereinafter called ―the Procuring Entity‖) and [ name and address of Contractor ] (hereinafter
called ―the Contractor‖) of the other part.
Whereas the Procuring Entity is desirous that the Contractor execute [name and identification
number of contract] (hereinafter called ―the Works‖) with the objectives of [insert functional
objectives of the works] and the Procuring Entity has accepted the Tender by the Contractor
for the execution and completion of such works and the remedying of any defects therein in
the sum of [contract price in words and figures] (hereinafter called ―Contract Price‖).
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to,
and they shall be deemed to form and be read and construed as part of this
Agreement;
2. Information prescribed under General Conditions of Contract and Contract Data shall be
deemed to form and shall be read and construed as part of this Agreement;
3. In consideration of the payments to be made by the Procuring Entity to the
Contractor as hereinafter mentioned, the Contractor hereby covenants with the
Procuring Entity to execute and complete the Works and remedy any defects therein
in conformity in all respects with the provisions of the Contract;
4. The Procuring Entity hereby covenants to pay the Contractor in consideration of the
execution and completion of the Works and the remedying of defects wherein the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the Contract.
In Witness whereof the parties thereto have caused this Agreement to be executed the day
and year first before written.
133 | P a g e
Binding Signature of Contractor
134 | P a g e
SECTION IX: FORMS OF SECURITY
135 | P a g e
1. TE NDER SECURITY
( B ank or Insuranc e G uarantee)
[If required, the Bank or Insuranc e C omp any /Tend erer shall fill in this Guarantee form in
accordance with the instructions indicated in brackets.]
[insert bank‘s or insurance company‘s name, and address of issuing branch or office]
136
Consequently, any demand for payment under this Guarantee must be received by us at the
office on or before that date.
_____________________________
[signature(s) of authorized representative(s) ]
137
2. PE RFORMANCE B ANK OR INSURANCE GUARANTEE [ UNCONDITIONAL]
[insert bank‘s or insurance company‘s name, and address of issuing branch or office]
We have been informed that [insert name of Contractor] (hereinafter called "the Contractor")
has entered into Contract No. [insert reference number of the Contract] dated with you, for
the execution of [insert name of Contract and brief description of Works] (hereinafter called
"the Contract").
At the request of the Contractor, we [insert name of Bank or Insurance Company] hereby
irrevocably undertake to pay you any sum or sums not exceeding in total an amount of [insert
amount in figures] ( [insert amount in words]) , such sum being payable in the types and
proportions of currencies in which the Contract Price is payable, upon receipt by us of your
first demand in writing accompanied by a written statement stating that the Contractor is in
breach of its obligation(s) under the Contract, without your needing to prove or to show
grounds for your demand or the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change, addition or other modification of the terms of the Contract
or of the Works to be performed there under or of any of the Contract documents which may
be made between you and the Contractor shall in any way release us from any liability under
this Guarantee, and we hereby waive notice of any change, addition, or modification.
138
This guarantee shall expire not later than thirty days from the date of issuance of the Certificate
of Completion.
139
3. B A NK OR INSURANCE GUARANTEE FOR ADVANCE
[Bank‘s or Insurance Company‘s Name and Address of Issuing Branch or Office]
We have been informed that [name of Contractor] (hereinafter called "the Contractor") has
entered into Contract No. [reference number of the contract] dated ______ with you, for the
execution of [ name of contract and brief description of Works] (hereinafter called "the
Contract").
We further agree that no change or addition to or other modification of the terms of the
Contract or of the Works to be performed thereunder or of any of the Contract documents
which may be made between ________________________[ name of Procuring Entity ] and the
Contractor, shall in any way release us from any liability under this guarantee, and we hereby
waive notice of any such change, addition or modification.
No drawing may be made by you under this guarantee until we have received notice in
writing from you that an advance payment of the amount listed above has been paid to the
Contractor pursuant to the Contract.
The maximum amount of this guarantee shall be progressively reduced by the amount of the
advance payment repaid by the Contractor as indicated in copies of interim statements or
140
payment certificates which shall be presented to us. This guarantee shall expire, at the latest,
upon our receipt of a copy of the interim payment certificate indicating that eighty (80)
percent of the Contract Price has been certified for payment, or on the ___ day of _____, 2___,
whichever is earlier. Consequently, any demand for payment under this guarantee must be
received by us at this office on or before that date.
Yours truly,
Address:
Date:
141
4. DE TAILS OF S UB-CONTRACTORS
If the Tenderer wishes to sublet any portions of the works under any heading, he must give
below the details of the sub-contractors he intends to employ for each portion.
……………………………………………………………. ………………………………
( Title) ( Signature) ( Date)
142
6. FORM OF WRITTEN POWER-OF-ATTORNEY
The Tenderer consisting of a joint venture shall state here below the name and
address of his representative who is authorised to receive on his behalf
correspondence in connection with the Tender.
………………………………………………………………
(Name of Tenderer‘s Representative in block letters)
………………………………………………………………
(Address of Tenderer‘s Representative)
………………………………………………………………
(Signature of Tenderer‘s Representative)
143
7. S C HEDULE OF KEY PERSONNEL
Headquarters:
1. Director
2.
3.
4.
5.
etc.
Site Office:
1. Site Agent
2.
3.
4.
5.
etc.
144
8. S C HEDULE FOR MA JOR ITEMS OF C ONSTRUCTION PLANT AND E QUIPMENT
Arrival on
of
(Days after
commence)
Project
Date
Ratin
Pow
er
g
Owned
Leased/
Import
ed
/
Sour
ce
(If to be
sa Value
Estimate
Importe
Momba
d CIF
d)
t or m3
Capaci
ty
Use
Ne
or
w
d
Manufact
Year of
ure
. of
Eac
No
h
on Type,
Descripti
Model,
Make
The Bidder shall enter in this schedule all major items of plant and equipment which he
proposes to bring to site. Only reliable plant in good working order and suitable for the work
required of it shall be shown on this Schedule. Summary of the same shall be entered in Section
5: Qualification Criteria,
………………………… ………………………
(Signature of Bidder) (Date)
145
9. S C HEDULE OF C OMPLETED RE FRIGERATION WORKS
I certify that the above Refrigeration Works were successfully carried out and completed by
ourselves.
………………………… ………………………… ………………
146
10. S C HEDULE OF ONGOING PROJECTS
I certify that the above Civil Works are being carried out by ourselves and that the above
information is correct.
147
11. LITIGATION FORM
a)
b)
c)
d)
148
12. LE TTER OF NOTIFICATION OF A WARD
______________________________________________________________
To:
___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
This is to notify that the contract/s stated below under the above mentioned tender have been
awarded to you.
2. The contract/contracts shall be signed by the parties within 30 days of the date of this
letter but not earlier than 14 days from the date of the letter.
3. You may contact the officer(s) whose particulars appear below on the subject matter
of this letter of notification of award.
(FULL PARTICULARS)
___________________________________________________________________________________
SIGNED FOR ACCOUNTING OFFICER
149
13. C E RTIFICATE OF BIDDER‘S PRE-BID S ITE V ISIT
of ………………………………………………………………………………………………
(Name of Firm bidding)
visited the site in connection with bid for the……………………………………………….
3. Having previously studied the Tender Documents, I carefully examined the Sites for
the above works;
4. I have made myself familiar with the local conditions likely to influence the works and
cost thereof;
4.
5. I have raised all pertinent issues on site and I have been satisfactorily answered except
for
5.
…………………………………………………………………………………………………
……………………………………………………………………………… …………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
6. I further certify that I am satisfied with the description of the work and that I
understand perfectly the work to be done as specified and implied in the execution of
the contract.
Signature ………………………………………………………………………………………………
150
14. A FORM RB : PPLICATION TO PUBLIC PROCUREMENT A DMINISTRATIVE REVIEW
B OA RD
APPLICATION NO…………….OF……….….20……...
BETWEEN
……………………………………………………….APPLICANT
AND
Request for review of the decision of the…………… ( Name of the Procuring Entity) of
……………dated the…day of ………….20……….in the matter of Tender No………..…of
…………..20…
RE QUE S T FOR RE V IE W
1.
2.
etc.
By this memorandum, the Applicant requests the Board for an order/orders that: -
1.
2.
etc
151
FOR OFFIC IA L US E ONLY
Lodged with the Secretary Public Procurement Administrative Review Board on ………… day
of ………....20….………
SIGNED
Board Secretary
152