CHECKLIST ON TECHNICAL REQUIREMENT FOR HEAVY CARGO HANDLING OPERATION (AMAN - 2022)

TRANSPORTER : AMAN LOGISTIK


COMPLIANCE
ITEM DESCRIPTION REMARKS
YES (Y) NO (N)
1 KP Application Form & Processing fee
2 KP Safe Work Permit (SWP) Form Submission
3 Cargo packing list (by manufacturer)
Project Insurance Policy (Coverage to Principal
4 Existing Property, Marine Cargo Insurance & P&I
Insurance)
Work Deposit on dismantle, removal and reinstate
KP's road furnitures, accessories and services
5
(Amount : RM TBA)
[Deposit-refundable subject to T&C]
Job Schedule, JMS & JSA
      i.    Job Schedule
     ii.    Job Method Statement (JMS) - LAND
6
     iii.    Job Method Statement (JMS) - MARINE
    iv.    HIRARC (LOLO & RORO)
- LAND & MARINE
Logistic & Traffic Management Plan:-
     i.    Logistic & Traffic Management Plan
7    ii.     Propose temporary storage area c/w
temporary support detail inside Port area (operation
& non-operation area)
Loading Method (Ship Crane/ Floating Crane)
a. Crane detail & Load Chart
8
b. Wharf & Ship interface cross-section diagram
c. Ballast calculation

Loading Method (Ro-Ro)


a. Project Information including barge details, etc
b. Steel bridge thickness, installation and connection
method on jetty and barge including butt weld
details on steel beam connection
(must be fixed on barge side – weld hinged to the
barge)
c. Detail roll-on procedure from jetty to Barge
d. Detail cross-section drawings
(Jetty, RC platform for crawler crane, fender & barge
view)
e. Monitoring deformation of steel beam deflection
f. Barge detail information (ballastable barge &
ballast pump on board meet ballasting requirement)
g. Tug Boat detail information
h. Detail design calculation and drawings including
9
checking and endorsement from local Professional
Engineer of Steel bridge calculation (maximum
deflection VS actual deflection)
i. Mooring arrangement & Ballasting Stability
calculations
j. Berth condition inspection report (before, during
and after complete roll-on process)
k. Stowage arrangement & lashing / sea fastening &
other voyage preparation

(Review and approved c/w endorsement by


Marine Warranty Surveyor appointed by the
Contractor but final acceptance & approval
subject to:-
1)satisfaction by KP on technical & safety aspect
2)consent from Kuantan Port Authority (KPA)

Detail Calculation & Drawing consist of cargo &


10 trailer c/w total imposed load (Cargo + Accessories
+ Trailer)
11 Vessel / Barge particular detail & Stowage Plan
12 Customs - IED,K2,COR
Heavy Cargo advance payment to KP prior start
13
operation