Professional Documents
Culture Documents
TWJO-ITP-PRC-0005 Revc ITP For Box Culvert at LB Depot
TWJO-ITP-PRC-0005 Revc ITP For Box Culvert at LB Depot
TWJO-ITP-PRC-0005 Revc ITP For Box Culvert at LB Depot
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
1. Distribution is centralized - in this case through ACONEX. Any improvement suggestions should be forwarded to the Quality Control
Engineer
Approval:
TWJO-ITP-PRC-0005-revC
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Contents
Inspection and Test Plan for Box Culvert at Lebak Bulus Depot Area
2. Checklist
Box Culvert Checklist
Permit To Dig
Jacking Pile Record
Concrete Pour Checklist
Concrete Conctrol on Site
TWJO-ITP-PRC-0005-revC Contents
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
1 Documentation
Approved Mix
The achieved stregth Design &
Before QC Engineer
Establishing the Concrete Design TWJO-ITP-GEN- for mix design shall relavent
1.3 commencemnet of with QC P NA I
mix 0002 achieve the targeted Compressive
Concreting Manager
strength of fc 32 Strength
results
Before Work Method
Staking Out for positioning Civil Engineer Survey
2 commencement of Statement for Box Approved drawings P NA NA
temporary and new culvert with Surveyor Records
Excavation activity Culvert
Preparation of Temporary
3
diverson
Before TWJO-ITP-
Completed Permit to Civil Engineer
3.1 Obtain Permit to Dig commencement of Appendix 28 of ER GEN-0008- P NA NA
Dig with Surveyor
Excavation activity CHK-002
Work Method
Gradient level check for temporary During Excavation Civil Engineer Survey
3.2 Statement for Box As per design drawing P NA I
diversion activity with Surveyor Records
Culvert
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
Position: 100 mm in
any direction at cut-off
During jacking Driving tolerances as TWJO-ITP-
Checking of Spun Pile jacking level
5.3 operation for each PC per OCS Clause Civil Engineer PRC-0005- P NA I
position and verticality Verticality: 1 in 75
Spun Pile 4.2.4 CHK-001
deviation from vertical
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
Thickness of layer ≤
Vol 5 Outline TWJO-ITP-
Checking for thickness of concrete 0.45 m
7.1 For every casting Construction Specs Civil Engineer GEN-0003- P NA I
and height of concrete pour Height of placing ≤ 1.5
clause 5.15.1 CHK-001
m
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
INSPECTION AND TEST PLAN FOR BOX CULVERT AT LEBAK BULUS DEPOT
Description of Activity: Details the inspection and test plan for construction of WMS No: TWJO-MST-0012 ITP NO: TWJO-ITP-PRC-0005 revC
Box Culvert at Lebak Bulus Depot Area
Name: Name:
Signature: Signature:
All approved ITPs and related records shall be stored on TWJO server under Quality Assurance folder with a hard copy in office file.