Professional Documents
Culture Documents
Last Day
Last Day
A PROJECT REPORT
Submitted by
BACHELOR OF TECHNOLOGY
IN
CIVIL ENGINEERING
Guided by
June 2022
ii
BONAFIDE CERTIFICATE
Signature of the Supervisor with date Signature of the HOD with date
Mr. T Nelson Ponnu Durai, M.E., Dr. A. Geetha Selvarani, M.E., Ph.D.
Assistant Professor Professor and Head
Department of Civil Engineering Department of Civil Engineering
Vel Tech Rangarajan Dr. Sagunthala R&D Vel Tech Rangarajan Dr. Sagunthala R&D
Institute of Science and Technology Institute of Science and Technology
Chennai - 600062. Chennai - 600062
iii
CERTIFICATE OF EVALUATION
The report of the project work submitted by the above students in partial fulfilment for the
award of Bachelor of Technology in Civil Engineering of Vel Tech Rangarajan Dr.
Sagunthala R&D Institute of Science and Technology for the Viva – Voice examination held
on _____________ has been evaluated and confirmed.
ABSTRACT
Bridge is a structure providing passage over an obstacle without closing the way
beneath. Bridges are mainly categorized based how the forces are distributed through
the structure, purpose and material availability etc. This project mainly focuses on
bridges. For the study, an existing bridge near Lalpur Village, district Rampur (U.P.)
which is in structurally poor condition, is identified. Work has been carried out to
propose a new post-tensioned PSC I-Girder Bridge with an increased height for the
above mentioned site. The various parameters like selection of design vehicle and load
combination is decided as per IRC: 6-2000 and the girder is designed with reference to
IRC: 18-2000. Parabolic tendon profile is adopted. The parametric study has been
carried out by altering the effective span of the PSC I-Girder, effective span of 30.4 m.
This present paper describes the analysis and design of longitudinal PSC I-Girder
ACKNOWLEDGMENT
We deem it as a great pride in expressing our heart full gratitude to our beloved
Vice Chancellor Prof. Dr. S SALIVAHANAN, Ph.D., for providing us with an
environment to complete our project work successfully.
We would also thank our project coordinator Mr. M. SRIDHAR. M.E., and
project guide Mr. T NELSON PONNU DURAI. M.E., Assistance Professor for his
support and guidance which helped me in completing the project, in time for being
instrumental in the completion of my project with his encouragement and unwavering
support during the entire course of this project.
Special thanks to external supervisor Mr. R.K. SINGH Deputy Project Manager
for his encouragement, constant support and guidance.
Finally, we would like to thank all the teaching and non-teaching faculty
members and lab staff of the Department of Civil Engineering for their encouragement.
I also extend our thanks to all those who have helped us directly or indirectly in the
completion of this project.
TABLE OF CONTENTS
CHAPTER PAGE
TITLE
NO. NO.
ABSTRACT iv
LIST OF TABLES viii
LIST OF FIGURES ix
LIST OF SYMBOLS xi
LIST OF ABBREVIATION xii
1 INTRODUCTION 01
1.1 GENERAL 01
1.2 CLASSIFICATION OF BRIDGES 01
1.2.1 Classification of Materials 01
1.2.2 Classification by Objectives 03
1.2.3 Classification by Structural Systems (Superstructures) 04
1.2.4 Classification by Span Length 07
1.3 FACTORS INFLUENCING SELECTION OF BRIDGE 07
1.4 I-GIRDER 08
1.5 PRESTRESSED CONCRETE 09
1.6 METHODS OF PRESTRESSING 10
1.6.1 Pre-Tensioning 10
1.6.2 Post-Tensioning 10
1.7 PRE-TENSIONING VS POST-TENSIONING 11
1.8 OBJECTIVE OF STUDY 12
1.9 NEED AND SCOPE OF THE STUDY 12
2 REVIEW OF LITERATURE 13
2.1 GENERAL 13
2.2 LITERATURE REVIEW 13
2.2.1 Analysis of I-Girder 13
2.2.2 Define I.R.C Loading 13
2.2.3 Economical Comparison 14
2.3 LITERATURE SUMMARY 16
3 METHODOLOGY 17
vii
3.1 GENERAL 17
3.2 SEQUENCE OF POST-TENSIONING 17
3.3 PRESTRESSING EQUIPMENT 20
3.3.1 Sheathing Pipes 20
3.3.2 Tendons 20
3.3.3 Hydraulic Jacks 21
3.4 DETAILS OF STUDY AREA 24
3.5 ACQUISITION OF DATA 24
3.5.1 Location 24
3.5.2 Topographical Survey 25
3.5.3 Geotechnical Investigation And Hydrological Data 25
3.6 DESCRIPTION OF LOADING 26
3.6.1 Dead Load 26
3.6.2 Live Load 26
3.7 LIVE LOAD CONTRIBUTIONS 27
3.8 DESCRIPTION OF BRIDGE SUPERSTRUCTURE 28
3.8.1 Wearing Surface 29
3.8.2 Deck Slab 29
3.8.3 Primary Members 29
3.8.4 Secondary Members 30
3.9 DESIGN AND ANALYSIS OF PSC I-GIRDER 32
3.9.1 Modelling of I-Girder 32
3.9.2 Modelling of Cable Profile 34
3.10 STAAD MODEL AND ANALYSIS OF I-GIRDER 35
3.10.1 Staad Editor File 38
4 RESULTS AND DISCUSSION 40
4.1 GENERAL 40
4.2 RESULTS ON LONGITUDINAL GIRDER 40
5 CONCLUSIONS 44
5.1 FUTURE AND SCOPE 44
REFERENCES 45
viii
LIST OF TABLES
TABLE PAGE
TITLE
NO. NO.
1.1 Comparisons between Pre-Tensioning and Post-Tensioning 11
3.1 Design Parameters for Detailed Design 24
3.2 Hydrological and Geotechnical Data 25
3.3 Live Load Contributions 28
3.4 Structural Details of Superstructure 31
4.1 Comparison of Outer and Inner Girder for Dead Load 40
4.2 Comparison of Outer and Inner Girder for Live Load 41
ix
LIST OF FIGURES
FIGURE PAGE
TITLE
NO. NO.
1.1 Timber Bridge 01
1.2 Steel Bridge 02
1.3 Concrete Bridge 02
1.4 Composite Bridge 02
1.5 Highway Bridge 03
1.6 Railway Bridge 03
1.7 Combined Bridge 03
1.8 Pedestrian Bridge 04
1.9 Aqueduct Bridge 04
1.10 Plate Girder 04
1.11 Box Girder Bridge 05
1.12 T-Beam Bridge 05
1.13 Truss Bridge 05
1.14 Arch Bridge 06
1.15 Cable Stayed Bridge 06
1.16 Suspension Bridge 06
1.17 Major Bridge 07
1.18 I-Girder 08
1.19 Prestressed Concrete Concept 09
1.20 Pre Tensioning Bed 10
1.21 Post-Tensioning 11
3.1 Post-Tensioning Effect 18
3.2 Formwork 18
3.3 Arrangements of Ducts 18
3.4 Pouring of Concrete 19
3.5 Prestressing of Concrete 19
3.6 Grouting 19
3.7 Corrugated Sheathing Ducts 20
3.8 Strands 21
x
LIST OF SYMBOLS
& And
, Comma
- Dash
“” Double Quotation
. Full Stop
; Semi colon
() Small Bracket
: Colon
xii
LIST OF ABBREVIATION
CHAPTER 1
INTRODUCTION
1.1 GENERAL
These include barriers that divide people, societies, and nations, and bring them
closer together. They shorten distances, speed transportation and facilitate commerce.
Building bridges is very important in communication and an important element in the
development of civilization. Bridges stand as an illustration of the work of civil
engineers. In order to supply safer and larger speed of traffic, the route is made as
straight as possible. Box girder bridges have gained wide acceptance in superhighway
and bridge systems owing to their structural potency, higher stability, useableness,
economy of construction and pleasing aesthetics.
Timber Bridges: Wooden bridges are used when the span is relatively short. The fig.1.1
represents timber bridge.
Steel Bridge: It may use a wide variety of structural steel components and systems:
girders, frames, trusses, arches and suspension cables. The fig.1.2 represents steel
bridge shown as below.
Concrete Bridges: There are two primary types of concrete bridges: reinforced and pre-
stressed. The fig.1.3 represents concrete bridge shown as below.
Composite Bridge: Bridges using both steel and concrete as structural material. The
below fig.1.4 represent composite bridge.
Combined bridges: Bridges carrying vehicles and trains. The fig.1.7 represents
combined bridge shown as below.
Aqueduct Bridges: Bridges supporting pipes with channel water flow. Bridges can
alternatively be classified into movable for ships to pass the river or fixed and
permanent or temporary categories. The fig.1.9 represents aqueduct bridge shown as
below.
Plate Girder Bridges: The main girders consist of a plate assemblage of upper and
lower flanges and a web. H or I-cross-sections effectively resist bending and shear. The
fig.1.10 represents plate girder.
Box Girder Bridges: The single or multiple main girder consists of a box beam
fabricated from steel plates or formed from concrete, which resists not only bending and
shear but also torsion effectively. The fig. 1.11 represents box girder bridge.
T-Beam Bridges: A number of reinforced concrete T-beams are placed side by side to
support the live load. The fig.1.12 represents T-beam bridge.
Truss Bridges: Truss bar members are theoretically considered to be connected with
pins at their ends to form triangles. Each member resists an axial force, either in
compression or tension. The fig. 1.13 represent truss bridge shown as below.
Composite Girder Bridges: The concrete deck slab works in conjunction with the steel
girders to support loads as a united beam. The steel girder takes mainly tension, while
the concrete slab takes the compression component of the bending moment
Arch Bridges: The arch is a structure that resists load mainly in axial compression. In
ancient times stone was the most common material used to construct magnificent arch
bridges. The fig.1.14 represents arch bridge shown as below.
Cable-Stayed Bridges: The girders are supported by highly strengthened cables often
composed of tightly bound steel strands which stem directly from the tower. These are
most suited to bridge long distances. The fig.1.15 represents cable stayed bridge.
Suspension Bridges: The girders are suspended by hangers tied to the main cables
which hang from the towers. The load is transmitted mainly by tension in cable. The
fig.1.16 represents suspension bridge.
1.4 I-GIRDER
When a beam bends the top of the beam is in compression and the bottom is in
tension. These forces are greatest at the very top and the very bottom. So to make the
stiffest beam with the least amount of material you would want the material to be only
at the top and the bottom sides. However, you still need to connect them together or
they would just be two separate plates and would not be stiff at all. So you put a web in
the middle to connect them and make them work together. The resulting shape is the
traditional “I-beam” or a wide flange beam. I-shape is an ideal shape for beams that is
for resisting flexure. It’s an extremely efficient shape for resisting bending; which is
another way of saying it has a lot of strength for a small amount of material and
expense.
1.6.1 Pre-Tensioning
In pre tensioned members, the tendons are tensioned even before casting the
concrete. One end of the reinforcement is secured to an abutment while the other end of
the reinforcement is pulled by using a jack and this end is then fixed to another
abutment. The concrete is then poured. After the concrete has cured and hardened the
ends of the reinforcement are released from the abutment. The reinforcement which
tends to resume its original length will compress the concrete surrounding it by bond
action. The prestress is thus transmitted to concrete entirely by the action of bond
between reinforcement and surrounding concrete. A typical pre tensioning bed is as
shown in the Fig. 1.20.
1.6.2 Post-Tensioning
The table 1.1 illustrate the difference between pre-tensioning and post-tensioning in a
concrete are listed below.
Pre-Tensioning Post-Tensioning
First tensioning and then casting. First casting and then tensioning.
Loss in prestress not less than 18% Loss in tensioning is not more than
15%.
While travelling into the city, there is no direct way to reach the city have to
cover large distance. The State government has decided to introduce the Major district
road (MDR) from Lalpur village to Rampur (U.P). In any aspect while travelling from
Lalpur village to Rampur it is mandatory to cross Kosi river. As a result, the state
administration has a proposed a major bridge across the river.
13
CHAPTER 2
REVIEW OF LITERATURE
2,1 GENERAL
Amit (2017), It represents two types of bridge systems, i.e., I-girder and Box-girder
bridge based on loadings and other various parameters. Calculation of material that is
steel and concrete consumption in construction is calculated. The analysis is carried out
by using software STAAD PRO. After examining manually and by software has been
selected out of these two.
Chirag (2016), analyzed the several positions in type of girders where the pre-stressed
tendons can be added. By keeping constant loading and varying the positions of tendons
a comparative study has been done so as to understand the most effective positions of
prestressed tendons.
Kalpana (2017), discussed the analysis and results of steel and reinforced steel bridge
girders based on STAAD PRO analysis and manual analysis
Jegan (2020), discussed about prestressed concrete box girder which is analyzed for
moving loads by wing of Indian road congress and code of practice for concrete
bridges. Found the result the dead load , shear force and bending moment is higher as
14
compared to other loading one lane of IRC 70R and class A under the live load analysis
is found to be more critical 3 lane of class A. Here they have found deflection obtained
due to various loading conditions.
Kwang et.al (2019), discussed that the assessment of load carrying capacity and safety
of PSC girder bridge decks. It has been observed from the load test and analysis that the
differential deflection between girder greatly reduces the negative bending moment in
the deck slab, tensile stresses of top slab is reduced and compared with experimental
studies for PSC girder.
Phani and Adithya (2016), has conducted analysis of girder bridge and designed the
sections as per IRC 112 specifications, its explained for a span of 30m and carriageway
width 7.5 m adopted and results showed that deflections, stresses are in safe permissible
limits. And it also concluded that depth of girder decreases, the no. of prestressing
strands and prestressing forces decreased, more strength of concrete utilized.
Catrodale et.al (2016), described the details that to overcome the problems of
transportation and erection of long and heavy precast girders, provided a precast I-
girder system that was far more competitive with the steel plate girder and box girder,
This detail eliminated end anchorage zone and congestion of reinforcement at ends in
the girder section, post tensioning operation was found to expensive but this was
balanced with fewer substructure units and wider spacing between girders.
Han and Hwan (2015), have performed study to achieve more economical PSC
girders. In this article it has been stated that, PSC I-type girders are generally restricted
for short and medium span bridges and girder depths are increased for long span
bridges. So, in order to reduce the girder depth, for any span given, method of
multistage prestressing for different loading cases is introduced. From the results, it
concluded that, the developed girders have shown the satisfactory behavior for the
strength and ductility and it can be used as economical alternative to other type of PSC
girder.
Sudhir (2018), worked on the cost comparison between two bridges forms, RCC girder
and PSC girder. They have design and an analysis different span was carried out for the
15
comparison. From that detailed cost estimation was presented and thus based on the
economic criteria the best bridge was finalized. It was concluded that PSC girder is
more economical compared to a RCC girder bridge.
Stanton et.al (2017), discussed on use of high curing temperatures during fabrication
affects the level of prestress because the strand length is fixed during the heating, the
coefficients of thermal expansion of steel and concrete differ, and the concrete
temperature distribution may not be uniform. For the girders discussed here, these
effects combined to reduce the calculated prestressing stress from the original design
values at release by 3 to 7%, to reduce the initial camber by 26 to 40%, and to increase
the bottom tension stress in service by 12 to 27%.
Shubham (2017), investigated that bridge construction today has achieved a worldwide
level of importance. Bridges are the key elements in any road network and use of pre-
stress girder type bridges gaining popularity in bridge engineering fraternity because of
its better stability, serviceability, economy, aesthetic appearance and structural
efficiency. I-beam bridges are one of the most commonly used types of bridge and it is
necessary to constantly study, update analysis techniques and design methodology.
Structurally they are simple to construct.
Natraj (2016), worked on the study that they tries to compare the cost of the
superstructure of bridges for 20m and 25m span. Four types of the superstructures are
used for the study purposes, namely; reinforced concrete T-beam, reinforced concrete I-
beam, prestressed concrete I-beam and steel composite I-beam. For the analysis and
design purposes, the loading standards of the Indian Road Congress (IRC) have been
adopted. The study is done by calculating the cost associated with various stages of
construction. To reach at best economical option including the lifecycle cost.
Sami (2018), presented a systematic procedure for selecting the most economic girder
type and spacing for a given span. They conclude that is more economical to space the
girders at their maximum spacing.
Wakchaure et.al (2019), discussed that objective is to minimize the total cost in the
design process of the bridge system considering the cost of materials like steel,
concrete, tendons etc. For a particular problem the design variables considered for the
16
cost minimization of the bridge system, are depth of girder, various cross sectional
dimensions of the girder, number of tendons.
The scope of the review is to get an overview of various studies done so far
related to the topic of PSC I-Girder bridges. The main purpose to get an idea of work
already carried out and to form the basis for formulating objectives and methodology in
this design.
The design of bridge has become very important, Bridges are in favour of
improving the road network Bridges not only help to keep traffic flowing smoothly, but
also maintain the safety of the roads. As a result bridge design become extremely
important.
For span up-to 30m (100ft) pre-stressed concrete girder require extra labours for
fabrication, placing and anchoring cables than reinforced concrete girder. But for span
above 30m pre stressed girder provide the most economical choice. At span above 60m
reinforced concrete girder becomes uneconomical. Pre-stressed concrete girder whether
continuous or simple requires much less steel than reinforced beam girder.
As per research, from IS code book gives information IRC 6:2010 for loading,
IRC 18:2000 for minimum dimension requirement, IRC 21:2000 for concrete stress is
applied,
From this study it is concluded that analysis have to be done on the prestressed
concrete I-Girder bridges for different section and model will have to illustrate its
behaviour attributes and noticed failure and difficulties that occur during construction.
17
CHAPTER 3
METHODOLOGY
3.1 GENERAL
The fig.3.1 illustrate post-tensioning effect that means after introducing tensile forces in
girder, the girder placed on formwork you will see the girder try to lift from the bottom
cracks will produced from the bottom.
18
The below figures will give you the idea of stages of post-tensioning which have
already discussed above. The fig. 3.2 and fig. 3.3 represents formwork and arrangement
of ducts.
The fig. 3.4 and 3.5 represent poring of concrete and prestressing of concrete I-Girder
shown as below.
The fig. 3.6 represents the grouting over ducts shown as below.
A HDPE Pipe which is insert in reinforcement of girder and cable profiling will
done so that we can assemble the pipe horizontal and vertical with proper distance as
per our drawing. Sheathing pipe also known as ducts which are widely used as
insulating the pre-stressing strands or tendons. If we have to join two pieces or sheath, it
can be joined by the help of coupler. HDPE Pipes for a varied range of sizes for use in
prestressed concrete structures and for underground services. The below figure 3.7
represent the corrugated sheathing ducts.
3.3.2 Tendons
The load cell shall be calibrated and shall be provided with an indicator by means of
which the prestressing force in the tendon may be determined.
Overview of the stressing jack, this jack will insert on the tendons and properly
fixed on it, where the tensile stresses introduces in the multiple strands or tendons, that
will be measure when jack is coming outward that means elongation will be occur after
that reading measure from the scale, at different load will be calculate the elongation up
to the permissible limit we have to apply the load on the tendon. The below figure 3.10
represents the typical multi-strand, centre hole, stressing jack.
From the below flow chart i.e. fig. 3.12 illustrate the methodology of the project where
you will understand the overview of the project what will initial step and final step to
complete the project
Acquisition of data
Topographical Survey
Geotechnical and
Hydrological data
Loading Parameters
Describe basic girder geometry
AutoCAD Modelling
IRC Class A
Loading for 2
Lane
Cross-sections of I-girder
Single I-
Girder Span
Cable Profile at End and
Mid Supports
The table 3.1 shown as below represent the data of the site, where the major
bridge construction across Kosi River is going on. The detailed parameters have been
discuss such as dimensions and types, material, etc. which will used for modelling and
analysis of PSC I-Girder.
3.5.1 Location
Topographical survey was carried out for detailed engineering survey of the
proposed bridge site.
Established benchmark (BM) to start the survey works. The suitable and convenient
place for starting benchmark was marked on the permanent concrete pillar which is
suitable near by the bridge site on right bank of the river. The fig.3.14 represents
reference benchmark.
The table 3.2 indicate hydrological and geotechnical data after several kind of
test which we need and some calculations have been done to find out the behaviour of
particular site in terms of soil and water and this data have been obtained from the site.
A bridge girder has to support its own weight dead weight as well as the dead
weight of the tributary area of the deck slab it supports. Also the girders have to support
the dead weight of some essential items that might not be obvious to the junior
engineer.
Dead loads are static forces that are relatively constant for an extended time; they can
be tension or compression.
By calculating the volume of each member and multiplying by the unit weight of the
materials from which it is composed, an accurate dead load can be determined for each
component. For the purpose of dead load calculation self weight of the PSC I-Girder
will considered. Cross sectional properties of the I-Girders determines the dead load.
Live loads are usually variable or moving loads. These are temporary loads;
they are applied to the structure on and off over the life of the structure. The most
common types of lives loads are occupancy load, workers during construction and
maintenance snow, wind and seismic.
According to IRC: 6-2000, road bridges and culverts are classified on the basis of
loadings that they are designed to carry.
a. Wheeled vehicle
b. Tracked vehicle
One thing we have to remember that under class A loading we are considering wheeled
vehicle are moving on bridge i.e., I-Girder Bridge.
The heavy duty trucks with two trailers transmit loads from 8 axles varying form a
minimum of 27 kN to a maximum of 114 kN. Here, the class A loading is a 554 kN
from of wheeled vehicle of 8 axles. The impact factor is inversely proportional to the
length of the span and is different for steel and concrete bridges.
From below fig.3.15 and 3.16 you can get an idea about what is tracked vehicle and
wheeled vehicle
The carriageway live load combination shall be considered for the design as
shown below in Table 3.3 Live load Contributions.
28
The superstructure of any bridge must be designed such that it satisfies geometric and
load carrying requirements.
Comprises all the components of a bridge above the supports, basic components include
wearing surface, Deck, primary member, secondary member, etc.
29
It is that portion of deck cross section that resists traffic wear. In some instances,
this is a separate layer made of bituminous material, whereas in some other cases, it is
an integral part of concrete deck.
3.8.2 Deck
Secondary members, composed of horizontal crossed frames at the top or bottom flange
of a stringer, are used to resist lateral deformation. In curved girders bridges, the
diaphragms are considered primary members because they are load carrying members
that help resist torsion caused by vertical loads.
Bearing also come in category of secondary member, which are provided at the
junction of the girders and the top of pier and abutments, which transmits loads to
substructure in such a way that bearing stresses developed are within the safe
permissible limits. The bearing provide for small movements of the superstructure. The
fig.3.19 indicate bearing on pedestal.
Bridge components that includes substructure and superstructure, the figure 3.20 will
gives you clear view of all components of PSC I-Girder Bridges.
The details of superstructure regarding dimensions of I-Girders and Deck are mentioned
in Table 3.4 below.
Longitudinal girders 3
From 3d AutoCAD the modelling has done for a whole span length 29.30 m (in terms
of bearing to bearing) of I-Girder without solid and with solid from the fig.3.22 and
fig.3.23 as shown as below.
Cable profile has been done from AutoCAD which will help you to understand
where we have placed sheathing ducts in the reinforcement of prestressed concrete I-
Girder. As per our construction site, there is 4 numbers of sheathing ducts having 90
mm diameter different marking have been done for all ducts 1, 2, 3 and 4.
At supports location i.e., end point of girder you can see from bottom with some
elevation to top ducts go with ascending order.
At mid location i.e., mid-point of girder you can see the ducts lying down the ducts no.
1, 3, 2 with elevated 50 mm from centre and ducts no. 4 placed above ducts no. 3 from
the centre and elevation from centre of ducts is 330 mm.
From fig. 3.24, have assume the origin in centre where cable lying between mid span
and elevation of cable from origin is varying with particular interval of distances to end
face.
For the modelling of the bridge superstructure STAAD Pro V8i software is used. The
bridge models are analysed, modelling involves the construction of PSC I-Girder
Bridge model with single span. The bridge models are simple supported at the two ends.
Procedure,
1. Staad Pro in space is operated with unit meter and Kilo Newton. the properties
of section are assigned to the bridge. Fixed Supports are taken.
2. Dimension taken followed by assigning of plate thickness.3D rendering can be
viewed.
3. Loads are taken by the loads and definitions. By Post processing mode, Nodal
displacement, Max. Absolute Stress value for the bridge can be viewed and Run
analysis is operated.
4. Then go through the bridge model creating a deck defining proper carriageway
width in define road way after that IRC loading are applied and then run as load
generator after that for concrete is used that code is applied on all the element
and finally run and analysis command is used to compare the result.
STAAD Pro model has been created and illustrated in the following diagram i.e., figure
3.25.
36
The rendering view of the bridge structure is described in figure 3.26, which shows the
longitudinal outer main I-girders and inner main I-girders, Intermediate cross girders,
and End cross girders.
Providing supports to the I-girder, then the applying loads on single span the analysis
report have been carried out, the figure 3.27 mentions below,
The figure 3.28 below represents the reaction on the supports in X, Y and Z directions.
The editor file prepared in STAAD Pro software after graphical modelling and
inputs is shown below,
STAAD SPACE
START JOB INFORMATION
ENGINEER DATE 19-May-22
END JOB INFORMATION
INPUT WIDTH 79
UNIT METER KN
JOINT COORDINATES
1 0 5 0; 2 30 5 0; 3 30 5 8.75; 4 0 5 8.75; 5 0 5 4.375; 6 30 5 4.375;
7 15 5 0; 8 15 5 4.375; 9 15 5 8.75; 10 0 0 4.375; 11 30 0 4.375;
MEMBER INCIDENCES
1 1 7; 2 2 6; 3 3 9; 4 1 5; 5 5 4; 6 6 3; 7 5 8; 8 7 2; 9 8 6; 10 9 4;
11 7 8; 12 8 9; 13 5 10; 14 6 11;
ELEMENT INCIDENCES SHELL
15 1 2 3 4;
ELEMENT PROPERTY
15 THICKNESS 0.2
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 2.17185e+007
POISSON 0.17
DENSITY 23.5616
ALPHA 1e-005
DAMP 0.05
TYPE CONCRETE
STRENGTH FCU 27579
END DEFINE MATERIAL
MEMBER PROPERTY
1 TO 12 PRIS YD 1.2 ZD 0.3
13 14 PRIS YD 1
39
CONSTANTS
MATERIAL CONCRETE ALL
SUPPORTS
10 11 FIXED
DEFINE MOVING LOAD
TYPE 1 LOAD 350 350
DIST 1.2 WID 1.2
LOAD 1 LOADTYPE Dead TITLE LOAD CASE 1
SELFWEIGHT Y -1 LIST ALL
LOAD GENERATION 150 ADD LOAD 1
TYPE 1 0 5 4.25 XINC 0.15 YRANGE 0
PERFORM ANALYSIS PRINT ALL
FINISH
40
CHAPTER 4
4.1 GENERAL
In this chapter, by using calculations as per Indian Standards (IS) and Indian
Road Congress (IRC) rules, the output data for the IRC Class A Loadings are
considered from STAAD Pro which include nodal displacement summary, reaction
summary, live load effects and many more effect are consider by STAAD Pro, the
design and analysis of bending moment and shear force of PSC I-Girder has thoroughly
done, by using STAAD Pro, it is easy to find out data which is beneficial.
Post tensioned I-Girder Bridge was analysed and designed for dead load and
moving live load. Here, we have studied the effective span of girder of 30 m. A
comparative study have been done considering bending moments (BM), shear forces
(SF) & deflection has been carried out to better understand. The girder forces are
summarised in table 4.1 and table 4.2 below.
Table 4.1 Comparison of Outer and Inner Girder For Dead Load
Table 4.2 Comparison of Outer and Inner Girder For Live Load
From the above table 4.1 and 4.2 it is observed, maximum bending moment occurs for
dead load. Hence dead load case is the most critical for maximum bending moment in
longitudinal girder. In case of dead load the S.F in external girder is moderately higher
than the internal girder but in case of moving load the S.F in external girder is twice as
that of internal girder.
The below mentioned figure 4.1 and 4.2 illustrate when moving load is defined on a
span on the starting of span and after reached to the centre how the bending moment
diagram will be varying.
The figure 4.3 and 4.4 represents the shear force diagram when moving load is applied
to span how its behave
CHAPTER 5
CONCLUSION
The main aim of the study was to learn and understand the concept of analysis
and design of prestressed concrete I-Girder bridge. For this study, an existing bridge
near Lalpur Village, district Rampur (U.P.) was identified. The bridge was designed for
the traffic over the Kosi River.
In the present study, longitudinal prestressed concrete I-Girder single span has been
drawn in AutoCAD software and designed using STAAD Pro software by using cross
sections, here I considered effective span 29.30 m and designed for two lane of Class A
Loading or one lane of class 70R which gives the average result. The dead load and live
load are calculated using IRC: 6-2000, concrete grade M45 and TMT bars (Grade
Fe500D) conforming to IS: 1786-1985 are used.
The conclusion of the projects shows: From the analysis, specified reinforcement and
spacing for the bridge are going to be figure out from STAAD Pro. The software are
very helpful for constructing the economically bridge structure.
REFERENCES
16. Vrushali and Sujay (2021), “A Study on The Structural Analysis And Design Of
A Post-Tensioned Girder Bridge Proposed Near Khangaon Village”, vol. 09, no.
09, pp. 45-51.
17. Wakchaure, Bhawar and Nagare (2015), “Optimization of pre-stressed concrete
girder”, International Journal of research in engineering and technology, vol. 04,
no. 03, pp. 2319-1163.
18. Wilast, Christopher and Maher (2008), “curved, precast, pretension concrete I-
girder bridges”, PCI journal. vol. 4, pp. 2277-9655.
19. Zonaa and Ragni (2009), “Simplified method for the analysis of externally
prestressed steel concrete composite beams”, Journal of constructional steel
research, vol. 65, no. 2, pp. 308-313.