Technological Institute of the Philippines

Quiapo, Manila

COLLEGE OF ENGINEERING

CIVIL ENGINEERING DEPARTMENT

CONSTRUCTION COST ENGINEERING

MIDTERM QUIZ NO. 2

Submitted by

DIMPLE B. MANIPON

Submitted to

ENGR. JOEVANNIE EMMANUEL LUMAGAS

October 27, 2022


ROUGH ESTIMATE USING PLAN SWIFT

CE 303 1
Construction Cost Engineering
CCE 2
ROUGH ESTIMATE USING PLAN SWIFT

A. Determine the total Construction cost if the client preferred a luxury finish.

The total Construction cost = 106.13 sq. m. + 116.76 sq. m. = 222.89 sq. m.
= 222.89 sq. m. (Php 40,000 per sq. m.) = Php 8, 915, 600

B. Determine the possible Contract price for the contractor for its labor service only.
assume 50% of the construction cost is for the labor cost.

Labour Price = Php 8, 915, 600 (50%) = Php 4, 457, 800

C. If the distribution of the construction cost is as follows, determine the cost


discipline.

Architecture Finishes - 38%


Php 8, 915, 600 (38%) = Php 3, 387, 928

Civil/structural - 42%
Php 8, 915, 600 (42%) = Php 3, 774, 522

Electrical - 8%
Php 8, 915, 600 (8%) = Php 713, 248

Plumbing - 8%
Php 8, 915, 600 (8%) = Php 713, 248

Engineering and Permits - 4%


Php 8, 915, 600 (4%) = Php 356, 624

“I affirm that I have not given or received any unauthorized help on


this assignment and that this work is my own.”