EVA Formulas

BAC: Budget at Completion

AC: Actual Cost

PV: Planned Value = (Time Spent/Total Time)*BAC

EV: Earned Value = (Work Completed/Total Work)*BAC

CV: Cost Variance = EV – AC

CPI: Cost Performance Index = EV / AC

SV: Schedule Variance = EV – PV

SPI: Schedule Performance Index = EV / PV

EAC: Estimate at Completion = BAC / CPI

ETC: Estimate to complete = EAC - AC

VAC: Variance at Completion = BAC - EAC

TCPI: To Complete Performance Index = ( BAC – EV ) / ( BAC – AC )

Estimate Time to Complete = Original time / SPI