No.

Facilities Specifications Notes


1 Area 00
 MRSS and ECRs of process plant This units shall be of RCC framed construction with concrete slab at
roof & sides covered by brick/block masonry wall (as applicable) and
supported on RCC foundations. Internal partition wall shall be of
brick/block masonry wall construction. Suitable fire barrier walls to
be provided around transformer facility wherever required. Flooring
and surrounding drainage facilities shall be provided for draining out
storm water. For roof drainage system, the roof will have screed
concrete with slope towards edge of building with down-comers.
Lean to shed of steel construction with insulated cladding to be
provided in transformer area with all security facilities. Necessary
protection facilities shall be provided in the MRSS yard. All supports
for necessary electrical equipment shall be provided with RCC
foundation
 Central Control Room This control room will be of multi storey steel framed construction
with cover at roof by insulated cladding/sandwich panel & sides
covered by brick/block masonry wall (as applicable) and supported
on RCC foundations. Internal partition wall shall be of brick/block
masonry construction. Suitable vision panel shall be provided in
front of control desk. Floors will be of RCC construction supported
on steel beams and ground floor will be of concrete. Access for each
floor shall be provided suitably. Roof drainage system will be
provided along with downcomers and surrounding drainage facilities
shall be provided for draining out storm water
 Guard House Steel framed construction with cover at roof by insulated
cladding/sandwich panel and sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. Guard
house shall be facilitated with locker room and toilets with all
plumbing & sanitary fittings including furniture. Ground floor will be
of concrete
 Security House Steel framed construction with cover at roof by insulated
cladding/sandwich panel and sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. Internal
partition wall shall be of brick/block masonry construction. Security
house shall be facilitated with office, locker room, pantry, prayer
room, toilets etc with all plumbing & sanitary fittings including
furniture. Ground floor will be of concrete
 Capacitor Bank Foundation Concrete Foundation with pilling (if any)
 Isolator Foundation Concrete Foundation with pilling (if any)
 Transformer 40 Mva Foundation Concrete Foundation with pilling (if any)
 Transformer 1 mva Foundation Concrete Foundation with pilling (if any)
 EDG Foundation Concrete Foundation with pilling (if any)
 Fence & Gate
 Plant Side \walk
 Access Road & Ditch

2 Area 30
 Chemical storage house This will be a one storied reinforced concrete framed building with
RCC foundations. Proper drainage arrangement needs to be
considered for draining out storm water. Proper protection
arrangement for floors and walls needs to be considered to prevent
corrosion
 Filter press Building This building will be a two storied steel framed construction with
cover at roof and sides by trapezoidal profiled colour coated steel
sheet with RCC foundations. Ground floor will be of concrete. All
other floors will be of steel construction. Necessary supporting
arrangement for equipment supports needs to be provided. Proper
drainage arrangement needs to be considered for draining out storm
water
 STP Package Shelter This is a steel framed construction with cover at roof by trapezoidal
profiled colour coated steel sheet and supported on RCC
foundations. Ground floor shall have concrete grade slab.
Underground/over ground screen chamber, equalisation tank,
chlorine contact tank and sludge holding tank etc shall be of RCC
construction.
 Chlorination Plant Steel framed shed structure with cover at roof by trapezoidal
profiled colour coated steel sheet and supported on RCC
foundations. Maintenance facilities shall also be provided for pumps.
Ground floor shall have concrete grade slab. Pump foundation shall
also be provided
 SWI Pump Shelter RCC multi chamber tank below ground with sea water intake pipe
line entry, provisions for suction pump installation, band screen and
stop log facilities to be provided. Steel framed construction shed
structure with provision of EOT crane for pump maintenance &
cover at roof by trapezoidal profiled colour coated steel sheet shall
be supported from top of tank wall. Proper protection for concrete
work to be considered in sea water contact area. Suitable manhole
at RCC top slab for inspection and maintenance activity shall be
considered. Access facility shall be provided inside the tank with
Rung/ladder
 Intake Head Foundation Concrete Foundation with pilling (if any)
 Discharge Water Tank Foundation Concrete Foundation with pilling (if any)
 Discharge Water Pump Foundation Concrete Foundation with pilling (if any)
 Discharge Diffuser Head Foundation Concrete Foundation with pilling (if any)
 Chlorination Package Foundation Concrete Foundation with pilling (if any)
 Sea Water Strainer Foundation Concrete Foundation with pilling (if any)
 Electrolytic Cell Foundation Concrete Foundation with pilling (if any)
 Hypochlorite Storage Tank Concrete Foundation with pilling (if any)
Foundation
 Dilution Air Blower Foundation Concrete Foundation with pilling (if any)
 Hypochlorite Dosing Pump Concrete Foundation with pilling (if any)
Foundation
 Acid Tank Foundation Concrete Foundation with pilling (if any)
 Acid Cleaning Pump Foundation Concrete Foundation with pilling (if any)
 Sump Pump Foundation Concrete Foundation with pilling (if any)
 Cooling Tower Basin Foundation Concrete Foundation with pilling (if any)
 Chemical Dosing System Foundation Concrete Foundation with pilling (if any)
 Cooling Tower Recirculation Pump Concrete Foundation with pilling (if any)
Foundation
 Diesel Driven - Cooling Tower Concrete Foundation with pilling (if any)
Recirculation Pump Foundation
 Blowdown Water Transfer Pump Concrete Foundation with pilling (if any)
Foundation
 Filter Feed Pumps Foundation Concrete Foundation with pilling (if any)
 Side Stream Pressure Filter Concrete Foundation with pilling (if any)
Foundation
 Blower for Filter Foundation Concrete Foundation with pilling (if any)
 Filter Backwash Pumps Foundation Concrete Foundation with pilling (if any)
 Waste Backwash Transfer Pump Concrete Foundation with pilling (if any)
Foundation
 Plant water storage tank Foundation Concrete Foundation with pilling (if any)
 Plant water supply pump Foundation Concrete Foundation with pilling (if any)
 Potable Water Storage Tank Concrete Foundation with pilling (if any)
Foundation
 Potable Water Supply Pump Concrete Foundation with pilling (if any)
Foundation
 Potable Water Dosing Package Concrete Foundation with pilling (if any)
Foundation
 Sodium Hypochlorite Dosing Tank Concrete Foundation with pilling (if any)
Foundation
 Sodium Hypochlorite Dosing Pump Concrete Foundation with pilling (if any)
Foundation
 Potable Water Tank at Intake Station Concrete Foundation with pilling (if any)
Foundation
 Potable Water Pump at Intake Concrete Foundation with pilling (if any)
Station Foundation
 Emergency Water Tank Foundation Concrete Foundation with pilling (if any)
 Waste Water Collection Tank Concrete Foundation with pilling (if any)
Foundation
 Waste Water Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Acid Dosing Tank Foundation Concrete Foundation with pilling (if any)
 Acid Dosing Pump Foundation Concrete Foundation with pilling (if any)
 Alkali Dosing Tank Foundation Concrete Foundation with pilling (if any)
 Alkali Dosing Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Alkali Dosing Pump Foundation Concrete Foundation with pilling (if any)
 Coagulant Dosing Tank Foundation Concrete Foundation with pilling (if any)
 Coagulant Dosing Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Coagulant Dosing Pump Foundation Concrete Foundation with pilling (if any)
 Flocculant Dosing Tank Foundation Concrete Foundation with pilling (if any)
 Flocculant Dosing Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Flocculant Dosing Pump Foundation Concrete Foundation with pilling (if any)
 Waste Water Supply Pump Concrete Foundation with pilling (if any)
Foundation
 Flash Mixing Tank Foundation Concrete Foundation with pilling (if any)
 Mixer Foundation Concrete Foundation with pilling (if any)
 Thickener Foundation Concrete Foundation with pilling (if any)
 Thickener Underflow Pump Concrete Foundation with pilling (if any)
Foundation
 Sludge Holding Tank Foundation Concrete Foundation with pilling (if any)
 Sludge Holding Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Sludge Pump Foundation Concrete Foundation with pilling (if any)
 Filter Press Foundation Concrete Foundation with pilling (if any)
 Sludge Storage Foundation Concrete Foundation with pilling (if any)
 Treated Water Tank Foundation Concrete Foundation with pilling (if any)
 WWTP Reuse Pump Foundation Concrete Foundation with pilling (if any)
 Treated Water Pump Foundation Concrete Foundation with pilling (if any)
 Screen Chamber Foundation Concrete Foundation with pilling (if any)
 Grease Trap Foundation Concrete Foundation with pilling (if any)
 Equalization Tank Foundation Concrete Foundation with pilling (if any)
 Equalization Tank Transfer Pump Concrete Foundation with pilling (if any)
Foundation
 Disinfection Tank Foundation Concrete Foundation with pilling (if any)
 Disinfection Tank Agitator Concrete Foundation with pilling (if any)
Foundation
 Blower Foundation Concrete Foundation with pilling (if any)
 Sludge Tank Foundation Concrete Foundation with pilling (if any)
 Dosing Package for STP Foundation Concrete Foundation with pilling (if any)
 Hypochlorite Dosing Tank Concrete Foundation with pilling (if any)
Foundation
 Hypochlorite Dosing Pump Concrete Foundation with pilling (if any)
Foundation
 Treated Water Tank Foundation Concrete Foundation with pilling (if any)
 Treated Water Transfer Pump Concrete Foundation with pilling (if any)
Foundation
 Modular STP at Benete Bay Concrete Foundation with pilling (if any)
Foundation
 Blower Foundation Concrete Foundation with pilling (if any)
 Treated Water Tank Foundation Concrete Foundation with pilling (if any)
 Treated Water Transfer Pump Concrete Foundation with pilling (if any)
Foundation
 Vacuum Truck Foundation Concrete Foundation with pilling (if any)
 Storm Water Pond (Process Area) Concrete Foundation with pilling (if any)
Foundation
 Storm Water Pump (Process Area) Concrete Foundation with pilling (if any)
Foundation
 Storm Water Pond (Admin Complex) Concrete Foundation with pilling (if any)
Structure & Foundation
 Storm Water Pump (Admin Complex) Concrete Foundation with pilling (if any)
Foundation
 Dewatering Pump Foundation Concrete Foundation with pilling (if any)
 EDG Foundation Concrete Foundation with pilling (if any)
 Transformer 33 kv/11kv Foundation Concrete Foundation with pilling (if any)
 Transformer 33 kv/0.7kv Foundation Concrete Foundation with pilling (if any)

 Pipe Rack Structure & Foundation This will be open type steel structure to support overhead utility
pipes and cable trays and it will be supported on trestles & towers
with RCC foundation. In general, at bent locations four legged
towers shall be considered. Walkway along with access will be
provided only for maintenance of pipe racks (as required) and no
maintenance walkway required for cable trays
 Pipe Sleepers Foundation Concrete Foundation with pilling (if any)

Area 40
 DIESEL OIL TANK Foundation Concrete Foundation with pilling (if any)
 DIESEL OIL PUMP Foundation Concrete Foundation with pilling (if any)
 EDG Daily Tank Foundation Concrete Foundation with pilling (if any)
 Pipe Rack Structure & Foundation This will be open type steel structure to support overhead utility
pipes and cable trays and it will be supported on trestles & towers
with RCC foundation. In general, at bent locations four legged
towers shall be considered. Walkway along with access will be
provided only for maintenance of pipe racks (as required) and no
maintenance walkway required for cable trays

3 Area 50
 Pump house This shall be a steel framed construction with cover at roof and sides
by trapezoidal profiled colour coated steel sheet overlapped with
external brick/block wall. Provisions for crane supporting
arrangement needs to be provided. Ground floor shall be made of
concrete and necessary supports for pumps and associated
equipment shall be made of RCC. Proper drainage arrangement
needs to be considered for draining out storm water.
 Fire Water Tank Foundation Concrete Foundation with pilling (if any)
 Fire Pump (Motor Driven) Concrete Foundation with pilling (if any)
Foundation
 Fire Pump (Engine Driven) Concrete Foundation with pilling (if any)
Foundation
 Diesel Tank (for fire pump engine Concrete Foundation with pilling (if any)
driver) Foundation
 Jockey Pump (Motor Driven) Concrete Foundation with pilling (if any)
Foundation

4 Area 80
 Weight Bridge Station RCC foundation for Weigh Bridge shall be provided. The weigh
bridge control room shall be steel framed building. The external &
internal partition wall shall be of brick/block masonry wall. The
building shall have glazed window on three sides facing the weigh
bridge. Ground floor shall have concrete grade slab. The control
room should have the provision of issuing weighment slip through a
separate window
 Emergency Water Tank Concrete Foundation with pilling (if any)
 Access Road For Site

5 Area 90
 Canteen Steel framed construction with cover at roof by insulated
cladding/sandwich panel & sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. Internal
partition wall shall be of brick/block masonry construction. Canteen
shall have kitchens with all utensils, storage facility for dry groceries
and cold storage, manager’s room, gas store, hand wash area &
toilets, dish wash area, dining facilities etc. with all plumbing &
sanitary fittings including furniture. Ground floor will be of concrete.
Roof drainage system will be provided along with down comers.
Surrounding drainage facilities shall be provided for draining out
storm water
 Car Park Steel framed construction with cover at roof by insulated
cladding/sandwich panel and supported on RCC foundations. Gable
ends shall be covered as required by insulated cladding. Sides will be
open. Flooring will be made of concrete with floor
hardener. Security provisions shall be kept for entry/exit of car. Roof
drainage system will be provided along with down-comers
 Multipurpose Hall Steel framed construction with cover at roof by insulated
cladding/sandwich panel & sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. Internal
partition wall shall be of brick/block masonry construction. This
building shall be equipped with all facilities for indoor games, stores,
office room, HVAC facilities, pantry, toilet blocks & washroom with
all plumbing facilities, sitting area, gymnasium, stage and other
access facilities, doors, windows with proper security provisions shall
be kept. Flooring and surrounding drainage facilities shall be
provided for draining out storm water. Roof drainage system will be
provided along with down-comers connected to surrounding
drainage system
 Change House Steel framed construction with cover at roof by insulated
cladding/sandwich panel & sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. This change
room shall be a single storey steel building with separate change
rooms for ladies and gents with locker facilities including showers,
Toilets, Laundry (Wash & Dry) and equipment room (heating/
Pumps) with all plumbing & sanitary fittings including furniture. Roof
drainage system will be provided along with down-comers
connected to surrounding drainage system
 Fire Station This shall be steel framed construction with RCC foundations. Roof
cover will be provided with insulated cladding/sandwich panel &
sides covered by brick/block masonry wall (as applicable). Internal
partition wall shall be of brick/block masonry construction. This
building shall be equipped with all facilities for fire equipment, office
room, HVAC facilities, pantry, toilet blocks & washroom with all
plumbing facilities including furniture, doors, windows etc. Flooring
and surrounding drainage facilities shall be provided for draining out
storm water. Roof drainage system will be provided along with
down-comers connected to surrounding drainage system
 Laboratory Building RCC framed construction with concrete slab at roof & sides covered
by brick/block masonry wall (as applicable) and supported on RCC
foundations. Internal partition wall shall be of brick/block masonry
construction. This building shall be equipped with all facilities for
testing as per process requirement along with rooms for laboratory
manager, chemist, meeting room, HVAC facilities, pantry, toilet
blocks & washroom with all plumbing facilities, doors, windows with
proper security provisions and furniture shall be kept. Flooring and
surrounding drainage facilities shall be provided for draining out
storm water. For roof drainage system, the roof will have screed
concrete with slope towards edge of building with down-comers
 Raw Material Laboratory Building Steel framed construction with cover at roof by insulated
cladding/sandwich panel & sides covered by steel sheet with foil
insulation overlapped with brick/block masonry wall (as applicable)
and supported on RCC foundations. The brick/block wall shall be of
certain height for external wall. Internal partition wall shall be of
brick/block masonry construction. Proper drainage system needs to
be considered
 Workshop The workshop is planned for daily repair/maintenance requirement
in the process plant area. This workshop building shall be of steel
framed construction with the provision of EOT crane for
maintenance purpose and supported on RCC foundation. Access
facilities as required to be provided. Roof and sides of this workshop
will be covered by insulated cladding/sandwich panel overlapped
with brick/block masonry wall (as applicable). Facilities like office,
tool store, pantry, locker room, washrooms with all plumbing
facilities including furniture to be provided. Flooring shall be of
concrete and surrounding drainage facilities shall be provided for
draining out storm water. Roof drainage system will be provided
along with downcomers connected to surrounding drainage system
 Admin Office Steel framed construction with cover at roof by insulated
cladding/sandwich panel & sides covered by brick/block masonry
wall (as applicable) and supported on RCC foundations. Internal
partition wall shall be of brick/block masonry construction. This
building shall have meeting rooms, conference room, training
rooms, induction room, HVAC, Security, prayer room, operation
director room, female room, pantry, server room, toilets with all
plumbing & sanitary fittings furniture, front lobby etc. Ground floor
will be of concrete. Roof drainage system will be provided along with
down-comers. Ground floor shall be made with concrete. Necessary
storm water drainage facility needs to be provided
 Mosque Steel framed construction with cover at roof & side by insulated
cladding/sandwich panel overlapped with external brick/block
masonry wall (as applicable) and supported on RCC foundations.
Internal partition wall shall be of brick/block masonry construction.
Mosque shall be facilitated with prayer hall, storage room, office,
foyer area, toilets etc with all plumbing & sanitary fittings including
furniture. Ground floor will be of concrete. Natural ventilation
system needs to be provided
 Clinic Steel framed construction with cover at roof and sides by insulated
cladding/sandwich panel overlapped with external brick/block
masonry wall (as applicable) and supported on RCC foundations.
Internal partition wall shall be of brick/block masonry construction.
This building shall have doctor room, waiting area, pharmacy,
patient room, nursing room, meeting rooms, conference room,
HVAC room, pantry, toilets with all plumbing & sanitary fittings
including furniture, etc. Ground floor will be of concrete. Roof
drainage system will be provided along with down-comers. There
shall be an Ambulance parking shed of steel construction with
necessary flooring system adjacent to clinic building.
 Warehouses for the plant These warehouses shall be of steel framed construction with cover
at roof by insulated cladding/sandwich panel and sides covered by
steel sheet with foil insulation overlapped with brick/block masonry
wall (as applicable) and supported on RCC foundations. Internal
partition wall shall be of brick/block masonry construction. Access
facilities as required to be provided. Facilities like office, rolling
shutter, doors, washrooms with all plumbing facilities including
furniture shall be provided. Flooring shall be of concrete and
surrounding drainage facilities shall be provided for draining out
storm water. Roof drainage system will be provided along with
down-comers connected to surrounding drainage system.
 Storage for Chemical and Oil This is a steel framed construction with cover at roof and sides by
trapezoidal profiled colour coated steel sheet and supported over
RCC foundations. The brick/block wall shall be of certain height for
external wall. Natural ventilation and natural lighting system shall be
provided by means of louvers with insect screen and translucent
sheets. Ground floor shall be of concrete and surrounding drainage
facilities shall be provided for draining out storm water. Roof
drainage system will be provided along with down-comers
connected to surrounding drainage system. Proper access to be
provided by man entry doors and for material entry rolling
shutter/steel door with suitable ramp shall be provided. Necessary
corrosion protection arrangement shall be considered
 Oil drum storage
 Substation 7 (for desal & intake) Building structure shall be of RCC framed construction with concrete
slab at roof & sides covered by brick/block masonry wall (as
applicable) and supported on RCC foundations. Internal partition
wall shall be of brick/block masonry wall construction. Suitable fire
barrier walls to be provided around transformer facility wherever
required. Flooring and surrounding drainage facilities shall be
provided for draining out storm water. For roof drainage system, the
roof will have screed concrete with slope towards edge of building
with down-comers. Lean to shed of steel construction with top cover
by insulated cladding/sandwich panel to be provided in transformer
area with all security facilities. All supports for necessary electrical
equipment shall be provided with RCC foundation
 Substation 8 Building structure shall be of RCC framed construction with concrete
slab at roof & sides covered by brick/block masonry wall (as
applicable) and supported on RCC foundations. Internal partition
wall shall be of brick/block masonry wall construction. Suitable fire
barrier walls to be provided around transformer facility wherever
required. Flooring and surrounding drainage facilities shall be
provided for draining out storm water. For roof drainage system, the
roof will have screed concrete with slope towards edge of building
with down-comers. Lean to shed of steel construction with top cover
by insulated cladding/sandwich panel to be provided in transformer
area with all security facilities. All supports for necessary electrical
equipment shall be provided with RCC foundation