Commissioning Service Department

Commissioning Standard Test Formats


Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:1 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

1. GENERAL DATA AND INFORMATION:


Reference Panel D04 CT supervision setting 14V
REB650 MAIN-1
Under testing Panel GANTRY OUTDOOR CT BOX Bus Bar Relay
MICOM P142 MAIN-2
CT ratio 1200/1 Relay current setting 0.1 A
2. Series resistor 1500 Ω Shunt resistor 140 Ω
Relay voltage setting 150 V CT supervision time setting 5 SEC
STABILITY TEST : MAIN-1

Reference Panel (D04) Testing Panel (GANTRY OUTDOOR CT BOX)

Primary Location: XDBC4 Location: XCT1


Phase Current
(A) R:2 Y:4 B:6 N:7 R:2 Y:4 B:6 N:7

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 

R-E 300 A 252 -34 0 0 0 0 252 -214 253 -214 0 0 0 0 253 -34
300 A
Y-E 0 0 252 -34 0 0 251 -214 0 0 257 -214 0 0 255 -34
300 A
B-E 0 0 0 0 253 -34 252 -214 0 0 0 0 254 -214 254 -34

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:2 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

D04+R1 D04+R1
Primary Location:X1A Location:X1B
Phase Current
(A) R :1 Y: 3 B: 5 N: 7 R :1 Y: 3 B: 5 N: 7
I(mA) I(mA) I(mA) I(mA) I(mA) I(mA) I(mA) I(mA)
       

R-E 300 A 252 -34 0 0 0 0 252 -214 254 -214 0 0 0 0 253 -34

Y-E 300 A 0 0 253 -34 0 0 251 -214 0 0 257 -214 0 0 255 -34

B-E 300 A 0 0 0 0 254 -34 252 -214 0 0 0 0 255 -214 254 -34

D04+R1
Location: TS1

R :3B Y: 4B B: 5B N: 6B
I(mA) I(mA) I(mA) I(mA)

0 0 0 0

0 0 0 0

0 0 0 0

D04+R1 D04+R1
Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:3 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

D04+R1 D04+R1
Primary Location: Metrosil Location: Main Relay REB650
Phase Current
(A) R: R4 Y: R5 B: R6 R:X101:1 Y:X101:3 B:X101:5 N:X102:2
I(mA) V I(mA) V I(mA) V I(mA) I(mA) I(mA) I(mA)
R-E 300 A 0 0 0 0 0 0 0 0 0 0
Y-E 300 A 0 0 0 0 0 0 0 0 0 0
B-E 300 A 0 0 0 0 0 0 0 0 0 0

SENSITIVITY TEST :

SWAP IN (GANTRY CT BOX) (Rph=XCT1: 20 , 11 & Yph = XCT1: 21, 12 & Bph = XCT1: 22 , 13)

Phase Primary
Reference Panel (D04) Testing Panel (GANTRY OUTDOOR CT BOX)
Current
(A)
Location: XBDC4 Location: XCT1

R:2 Y:4 B:6 N:7 R:2 Y:4 B:6 N:7

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:4 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 

R-E 300 A 252 -34 0 0 0 0 252 -214 253 -34 0 0 0 0 253 -214
300 A
Y-E 0 0 252 -34 0 0 251 -214 0 0 256 -34 0 0 255 -214
300 A
B-E 0 0 0 0 253 -34 252 -214 0 0 0 0 255 -37 254 -214

D04+R1 D04+R1
Primary Location:X1A Location:X1B
Phase Current
(A) R :1 Y: 3 B: 5 N: 7 R :1 Y: 3 B: 5 N: 7

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 

R-E 300 A 252 -34 0 0 0 0 252 -214 253 -34 0 0 0 0 254 -214

Y-E 300 A 0 0 252 -34 0 0 251 -214 0 0 254 -34 0 0 255 -214

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:5 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

B-E 300 A 0 0 0 0 252 -34 252 -214 0 0 0 0 255 -37 254 -214

D04+R1
Location: TS1

R :3B Y: 4B B: 5B N: 6B

I(mA) I(mA) I(mA) I(mA)

504 0 0 504

0 507 0 506

0 0 507 503

Location: D04+R1 Location: D04+R1

Primary Location: SHUNT RESISTOR Location: SERIES RESISTOR


Phase Current
(A) R: SHR1 Y: SHR2 B: SHR3 R: R1 Y: R2 B: R3

I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V

R-E 300 A 457 64.2 0 0 0 0 42.1 64.2 0 0 0 0

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:6 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV
300 A
Y-E 0 0 456 64.1 0 0 0 0 41.9 64.2 0 0
300 A
B-E 0 0 0 0 547 64.2 0 0 0 0 42.1 64.2

D04+R1 D04+R1

Primary Location: Metrosil Location: Main relay REB650


Phase Current
(A) R: R4 Y: R5 B: R6 R:X101:1 Y:X101:3 B:X101:5 N:X102:2
I(mA) V I(mA) V I(mA) V I(mA) I(mA) I(mA) I(mA)

R-E 300 A 0 64.2 0 0 0 0 42.3 0 0 42.4

Y-E 300 A 0 0 0 64.2 0 0 0 42.3 0 42.3

B-E 300 A 0 0 0 0 0 64.2 `0 0 42.1 42.1

During ct supervision operated

D04+R1

Location: Main relay REB650

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:7 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

R:X101:1 Y:X101:3 B:X101:5 N:X102:2

I(mA) I(mA) I(mA) I(mA)

0 0 0 0

0 0 0 0

0 0 0 0

CT SUPERVISION WORKED @ INJECTED CURRENT 66A, 14.0 V

1. STABILITY TEST : MAIN-2

Reference Panel (D04) Testing Panel (GANTRY OUTDOOR CT BOX)


Primary Location: XDBC3 Location: XCT2
Phase Current
(A) R:2 Y:4 B:6 N:7 R:2 Y:4 B:6 N:7

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 


R-E 300 A 252 -34 0 0 0 0 252 -214 254 -214 0 0 0 0 254 -34

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:8 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

Y-E 300 A 0 0 254 -34 0 0 255 -214 0 0 255 -214 0 0 255 -34

B-E 300 A 0 0 0 0 253 -34 252 -214 0 0 0 0 254 -214 254 -34

D04+R1 D04+R1
Primary Location:X1C Location:X1D
Phase Current
(A) R :1 Y: 3 B :5 N: 7 R :1 Y: 3 R :5 Y: 7

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 


R-E 300 A 252 -34 0 0 0 0 254 -214 254 -214 0 0 0 0 255 -34
Y-E 300 A 0 0 255 -34 0 0 253 -214 0 0 256 -214 0 0 255 -34
B-E 300 A 0 0 0 0 255 -34 252 -214 0 0 0 0 255 -214 254 -34

D04+R1
Location: TS3
R :21 Y: 23 B: 25 N: 27
I(mA) I(mA) I(mA) I(mA)

0 0 0 0

0 0 0 0

0 0 0 0

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:9 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

Location: D04+R1 Location: D04+R1


Primary Location: MERTOSIL Location: SERIES RESISTOR
Phase Current
(A) R- B2:2 Y- B2:4 B- B2:6 R: R04 Y: R05 B: R06

I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V

R-E 300 A 0 0 0 0 0 0 0 0 0 0 0 0
300 A
Y-E 0 0 0 0 0 0 0 0 0 0 0 0
300 A
B-E 0 0 0 0 0 0 0 0 0 0 0 0

Phase Primary D04+R1 D04+R1


Current
(A) Location: Main relay MICOM P142
Location: SHUNT RESISTOR
R: RS4 Y: RS5 B: RS6 R:C3 Y:C6 B:C9 N:C11

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:10 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

I(mA) V I(mA) I(mA) V I(mA) I(mA) I(mA) I(mA) I(mA)

R-E 300 A 0 0 0 0 0 0 0 0 0 0

300 A
Y-E 0 0 0 0 0 0 0 0 0 0

300 A
B-E 0 0 0 0 0 0 0 0 0 0

SENSITIVITY TEST :

SWAP IN (GANTRY CT BOX) (Rph=XCT2: 20 , 11 & Yph = XCT2: 21, 12 & Bph = XCT2: 22 , 13)

Phase Primary Reference Panel (D04+R1) Testing Panel (GANTRY OUTDOOR CT BOX)

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:11 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

Location: XDBC3 Location: XCT2

Current
R:2 Y:4 B:6 N:7 R:2 Y:4 B:6 N:7
(A)
I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 

R-E 300 A 252 -34 0 0 0 0 252 -214 253 -34 0 0 0 0 255 -214
300 A
Y-E 0 0 252 -34 0 0 253 -214 0 0 253 -34 0 0 255 -214
300 A
B-E 0 0 0 0 254 -34 252 -214 0 0 0 0 255 -37 255 -214

D04+R1 D04+R1

Primary Location:X1C Location:X1D


Phase Current
(A) R :1 Y: 3 B: 5 N: 7 R :1 Y: 3 B: 5 N: 7

I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA)  I(mA) 

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:12 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

R-E 300 A 253 -34 0 0 0 0 255 -214 254 -34 0 0 0 0 256 -214
300 A
Y-E 0 0 255 -34 0 0 254 -214 0 0 255 -34 0 0 255 -214
300 A
B-E 0 0 0 0 254 -34 257 -214 0 0 0 0 255 -37 255 -214

D04+R1
Location: TS3
R :21 Y: 23 B: 25 N: 27
I(mA) I(mA) I(mA) I(mA)

506 0 0 505
0 509 0 507
0 0 508 507

Location: Shunt Resistor Location: Series Resistor


Primary
Phase Current R: RS4 Y: RS5 B: RS6 R: R04 Y: R05 B: R06
(A)
I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V I(mA) V

R-E 300 A 455 64.2 0 0 0 0 456 64.1 0 0 0 0

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:13 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV
300 A
Y-E 0 0 456 64.2 0 0 0 0 455 64.1 0 0
300 A
B-E 0 0 0 0 455 64.2 0 0 0 0 456 64.1

D04+R1 D04+R1

Primary Location: Metrosil Location: Main relay MICOM P142


Phase Current
(A) R- B2:2 Y- B2:4 B- B2:6 R:C3 Y:C6 B:C9 N:C11

I(mA) V I(mA) V I(mA) V I(mA) I(mA) I(mA) I(mA)

R-E 300 A 0 64.2 0 0 0 0 42.2 0 0 42.2

Y-E 300 A 0 0 0 64.2 0 0 0 42.1 0 42.1

B-E 300 A 0 0 0 0 0 64 0 0 42.3 41.9

During ct supervision operated

8TE.C0.1AB+R1
Location: Main relay MICOM P 142
Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:14 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV
R:C3 Y:C6 B:C9 N:C11
I(mA) I(mA) I(mA) I(mA)
0 0 0 0

0 0 0 0
0 0 0 0

CT SUPERVISION WORKED @ INJECTED CURRENT 66A, 13.99 V

CALCULATION

I total =600/1200 =0.5 A = 500 mA

R total = (1500*140) / (1500+140) = 128 Ω

V = I total * R total = 0.500*128 = 64 v

I sh =64/140 = 457.2 mA

I s = 64 /1500 = 42.6 mA

Test Equipment’s Used:

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: 132KV BUS DUCT PROTECTION STABILITY Record No.:
Panel Under Test: D04- FREE STANDING CT Drawing ref.: Sheet:15 of 15
Contractor: Al Babtain Contracting Contract no.: 4400011600 Substation No : DOWMAT AL-JANDAL 380/132/13.8KV

ITEM Description Make S/N Calib. Date Calib. Due Date


1 ODEN AT/35 Programa 1402314 16-JUL-2020 16-JUL-2021
2 MULTIMETER FLUKE 27430274 14-JUL-2020 14-JUL-2021
3 POWER QUALITY ANALYZER FLUKE 24183119 03-JUN-2020 03-JUN-2021
4 MINICLAMP Mini 05 N129211JFC 08-MAR-2021 08-MAR-2022

Tested ABC by: ENG. MOHAMED NASR BAB-070 Witnessed by: CSD-ENG. MOAMEN MOUSTAFA

Signature & Date: Signature & Date: