Professional Documents
Culture Documents
New Microsoft Excel Worksheet
New Microsoft Excel Worksheet
DATE 19/12/2021
D-101B SURGE TANK
CONTRACT NUMBER : PROJECT TITLE :
MANPOWER : TOTAL : 21
PROJECT MANAGER 1
SITE MAGER 1 FABRICATOR : 2 DRIVER
SUPERVISOR / QA,QC 1 WELDERS: 2 ELECTRICIAN&CIVIL
SAFETY SUPERVISOR 1 PAINTER / BLASTER 2 HELPER
MECHANICAL FOREMAN 1 MECHANIC 3 ADMIN
VEHICLES AND EQUIPMENTS: TOTAL: 14
MILLER MACHINE(Gouging) 1 SPRAY PAINT MACHINE 0 WELDING MECHINE
PLASMA CUTTER 0 PICK UP 0 AIR COMPRESSOR
BLASTING EQUIPMENT 2 TRUCK 1 WATER TRUCK
JCB 1 DUMPER TRUCK 0
FORK LIFT-TRUCK LOADER 1 HI-UP 1
WORK SCOPE PROGRESS FOR TODAY : 19/12/2021
1) The bottom plate laying completed.
2) The stitch welding work completed.
3) The scaffolding installation work on going.
REMARKES:
ACTIVITIES
Precise soil compaction and bottom plate placement work completed.
The stitch welding work completed.
DATE: 19/12/2021
The stitch welding work completed today.
the scaffolding installation will be continues.
NK NO: D-101B
DRIVER 1
ELECTRICIAN&CIVIL 1
HELPER 6
ADMIN 1
TOTAL: 14
WELDING MECHINE 2
AIR COMPRESSOR 1
WATER TRUCK 1
AY : 19/12/2021
DAY 20/12/2021
PROGRESS%
OF COMPLETION
100%
100%
DATE:19/12/2021
Eng: abdalmonaem almorabet