DAILY PROGRESS REPORT

SITE NAME : NC-115 STATION TANK NO: D-101B

DATE 19/12/2021
D-101B SURGE TANK
CONTRACT NUMBER : PROJECT TITLE :

MANPOWER : TOTAL : 21
PROJECT MANAGER 1
SITE MAGER 1 FABRICATOR : 2 DRIVER
SUPERVISOR / QA,QC 1 WELDERS: 2 ELECTRICIAN&CIVIL
SAFETY SUPERVISOR 1 PAINTER / BLASTER 2 HELPER
MECHANICAL FOREMAN 1 MECHANIC 3 ADMIN
VEHICLES AND EQUIPMENTS: TOTAL: 14
MILLER MACHINE(Gouging) 1 SPRAY PAINT MACHINE 0 WELDING MECHINE
PLASMA CUTTER 0 PICK UP 0 AIR COMPRESSOR
BLASTING EQUIPMENT 2 TRUCK 1 WATER TRUCK
JCB 1 DUMPER TRUCK 0
FORK LIFT-TRUCK LOADER 1 HI-UP 1
WORK SCOPE PROGRESS FOR TODAY : 19/12/2021
1) The bottom plate laying completed.
2) The stitch welding work completed.
3) The scaffolding installation work on going.

WORK SCOPE PLANNED FOR NEXT DAY 20/12/2021


the scaffolding installation will be continues.

REMARKES:

ACTIVITIES
Precise soil compaction and bottom plate placement work completed.
The stitch welding work completed.

DATE: 19/12/2021
The stitch welding work completed today.
the scaffolding installation will be continues.
NK NO: D-101B

D-101B SURGE TANK REPLACEMENT OF BOTTOM


PLATES

DRIVER 1
ELECTRICIAN&CIVIL 1
HELPER 6
ADMIN 1
TOTAL: 14
WELDING MECHINE 2
AIR COMPRESSOR 1
WATER TRUCK 1

AY : 19/12/2021

DAY 20/12/2021

PROGRESS%
OF COMPLETION
100%
100%

DATE:19/12/2021
Eng: abdalmonaem almorabet