Professional Documents
Culture Documents
Reasons
Reasons
10 140
and 9
120
8
Cummulative amount ($M)
7 100
Claim amount ($M)
6
80
5
60
4
Changes in payment
For each unit new claim of $1, the first 3 40
entries of CR, CQR, CQ2R, and CQ 3R are 2
0, 0.669, 0.127 and 0, and these enter 20
1
the ‘Paid’ state in subsequent time pe-
riods. Thus the first claim of $95.0K (in 0
the first month) gives rise to payments 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41
of $0, $63.6K, $12.1K and $0 in subse- Claim number
quent months. Similarly, the second Figure 2: Claims data – case example B
100
of small claims, the cumulative claim
6 80 schedule of this project may require ap-
proximating by several segments.
60
4 Case example C: the construction of
40 a rural highway including earthworks,
drainage, pavements, road furniture
2
20 and traffic management. The 22 prog-
ress claims are shown in Figure 3. This
0 cumulative plot might be approximated
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
by several segments, or more severely
Claim number by one segment.
Figure 3: Claims data – case example C Case example D: the refurbishment
of a city building with total cost of ap-
10 60 proximately $60M and duration of ap-
proximately 20 months. The cumulative
9
claims given in Figure 4 might be ap-
50
8 proximated by two straight segments
either side of the middle of the project.
Cummulative amount ($M)
7
40 The number of straight-line seg-
Claim amount ($M)
6
ments assumed to represent cumula-
5 30 tive expenditure is at the discretion of
the contractor. Stylised assumptions, in
4
20 order to simplify the calculations, how-
3 ever might be in terms of:
2 XX One straight-line (constant slope) seg-
10
ment over the entire project.
1
XX Two straight-line segments where the
0 change occurs near project midpoint.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
XX Three straight-line segments with the
Claim number larger claims in the middle part of
Figure 4: Claims data – case example D the project.
1.5 Payment
1.0
0.5
Amount ($)
0.0
-0.5
-1.0
-1.5 Claim
-2.0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37
Time (months)
Figure 5: Case example A extension; payment-claim relationship based on unit claims for the first 9 and last 9 months,
and twice this for the middle 18 months
Nonlinear segments can also be 3 and 4 are $0, $0.669, $0.127 and $0, out the project. The mark-up of 17.6% is
assumed in place of linear segments, respectively. The payment-claim rela- not high enough to give a positive pres-
for example by using quadratic or ex- tionship is plotted in Figure 5. ent value as the contractor would like. The
ponential functions. Numerical experi- minimum mark-up that needs to be ap-
ments conducted by the authors show Present Value plied in order to have a non-negative pres-
that the difference in the results be- Let the net cash flow, the difference be- ent value is of interest to the contractor.
tween linear and nonlinear assumptions tween the payments and the expendi- Figure 6 shows a range of mark-
is negligible. In the steady state there ture at each time period, i = 0, 1, 2, ... ups and the associated present value
is almost no difference in the values be xi. The present value (PV) is the sum amounts. It is seen that the contractor
of the matrix NR or the vector CNR be- of the discounted xi, needs to adopt at least a 27% mark-up
tween the assumptions of linear or non- (value at the intersection of the present
linear segments. Accordingly the extra value plot and the horizontal axis) in or-
accuracy that might be thought possible der to have a non-negative present value.
through the use of nonlinear approxi-
mations is not there; as well, it comes Effect of delaying payments to creditors
with increased burdens of mathematical where r is the monthly discount rate on contractor’s cash flow
understanding and computational load. and m extends until the last payment In order to improve present value, the con-
is received. tractor may consider the option of delaying
Estimation for a Future Project Consider the values as in Figure 5. payments to creditors such as subcontrac-
– Case Example A Extension The steady state payment to the ‘Paid’ tors and suppliers. This delays cash out-
Assume that the owner payment practices state is $0.796. Since the actual cash flows. Different time lags in payments to
of case example A apply, but now add the outflow each month is 85% of each claim, creditors can be examined by shifting the
following new (future) project specifics. the contractor’s net cash flow in each of cash outflows to the right.
There are 36 monthly progress claims, the first 36 months is negative. The non- Consider the situation (in the same
where the first 9 claims, the next 18 claims discounted total payment is $42.98 while case example) in which the contractor de-
and the last 9 claims have ratios of 1:2:1. the non-discounted total expenditure is lays its cash outflow by one month, then
The claims submitted include a mark-up $45.90. Based on a monthly discount the present value for a 17.6% mark-up be-
(17.6%) to account for overheads; the ac- rate of 1%, the present value of the net comes -$2.50. To make the present value
tual spending of the contractor is 85% of cash flow is -$2.90. non-negative, a 26% mark-up is required.
what it is being claimed. The contractor Delaying cash outflow by a further month,
pays for the work as it is done irrespective Effect of mark-up on present a 25% mark-up is required to bring the
of getting any payment from the owner. value present value to a positive amount ($0.13).
For each unit or $1 claim, the change The above analysis shows that the contrac- This may assist the contractor’s bid to be
in payments in subsequent months 1, 2, tor has a negative net cash flow through- more competitive.
The above example shows the con- of total amount paid within a certain
Table 2 Average payment in 2-month
tractor the impact of mark-up choices and time frame, the time following the sub-
period following claim submission,
creditor payment policies on its finances. mission of the claim to the initial pay-
as a proportion of total claimed
This may assist, for example in being ment made, and the consistency in the
amount, of the six representative
more competitive at tendering time, or promptness in responding to each in-
owner types of Tran and Carmichael
in administering funds during a project. dividual claim.
(2013)