ECVL 420

Construction Engineering and Management


Assignment #4: Basic Scheduling

Question 1:
The table below includes the description of a project. You are required to:
 Schedule the project using AON
 Calculate each activity’s early and late start and end dates
 Record project end date and critical path

Activity Duration (days) Predecessors


A 7 -
B 6 A
C 2 A
D 6 B
E 5 B
F 2 B, C
G 5 E, F
H 2 D
I 3 H, G

1 of 3
Question 2:
Represent the activities below with an AOA network.
Activity Predecessors
A -
B A
C A
D B, C
E B, C
F E
G D
H F, D

Question 3:
The table below includes the description of a project. You are required to:
 Schedule the project using AON
 Calculate each activity’s early and late start and end dates
 Record project end date and critical path
 For each activity, calculate all types floats

Activity Duration (days) Predecessors: Relation


A 7 -
B 6 -
C 2 A, B
D 6 B
E 5 C
F 2 C, E,
G 5 D
H 2 E, F, G
I 3 G. H

Assignment due on Wednesday, the 2nd of November 2022.


Make sure you are submitting a neat answer sheet.