PT.

Truba Jaga Cita


Maintenace Project Job C - 1101
IKPP Perawang
SHUTDOWN MB#26
PERIODE : January 2022
DIRECT MANPOWER Rev. 00
MANPOWER
NO DESCRIPTION Supervisor REMARKS
MW FITTER HP GTAW SMAW RIGGER

A SCAFFOLDING DS NS DS NS DS NS DS NS DS NS
1 Install & Dismantle Scaffolding At Furnace Up To Roof
2 Install & Dismantle Scaffolding Outside Furnace
3 Install & Dismantle Scaffolding Return Leg to Loop Seal
4 Install & Dismantle Scaffolding At Big Opening L & R
5 Install & Dismantle Scaffolding At Cyclone
6 Install & Dismantle Scaffolding At Coal Feeder
7 Install & Dismantle Scaffolding At APH
8 Install & Dismantle Scaffolding At Economizer
9 Install & Dismantle Scaffolding At Vortex
10 Install & Dismantle Scaffolding At Sand Blow Out Deni Roni / Zulfahmi
11 Install & Dismantle Scaffolding At Second Pass
12 Install & Dismantle Scaffolding At Expantion Joint Big Opening
13 Install & Dismantle Scaffolding At PAF,SAF, IDF Outlet
14 Install & Dismantle Scaffolding At Drain Boliler
15 Install & Dismantle Scaffolding At Inside Widbox
16 Install & Dismantle Scaffolding At Pipe Main Steam
17 Install & Dismantle Scaffolding At Inside Windbox
18 Install & Dismantle Scaffolding At ESP

B MECHANICAL WORK
1 Repair Wall Tube Furnace
2 Repair Drain Boiler
3 Welding Fin Wall Tube
4 Welding Fin Tube Furnace
5 Bending Tube
6 Build up Wall Tube
ARIF SAPUTRO / 10 10
7 Repair Grid nozzle furnace
SUPARDI
8 Install Anti Abration Grid 2 2 4 4 10 10 80
9 Repair Sandblow Out Furnace To Windbox
10 Welding Sandblow Out Outside Furnace
11 Replace Valve Transmiter Main Steam

1 Repair Tube Eco After Inspection


2 Repair Superheater Tube
3 Repair Grid Nozzle Loop Seal
4 Repair Cover Shield Economizer Screen Tube
5 Replace Plate Vortex
6 Welding Plate Vortex AZHAR EFENDI /
8 8
7 Repair Plate Coal Feeder ZULFAHMI
8 Dismantle Plate Chute Coal Feeder
9 Repair Nozzle PAF,SAF inside Furnace
10 Replace Exp. Joint Big Opening

1 Repair Emitting ESP


2 Repair Hammer ESP
3 Repair Shaft Hammer ESP
4 Replace Valve Transmitter
FADLI MALINGTON
5 Fabrication For Replace Plate Shell Return Leg 8 8
MANIK / ESRON TT
6 Welding Plate Shell Ring & Stiffinner Return Leg
7 Repair Ext. Joint Superheater
8 Replace Manual Valve Sampling Floor 7
9 Repair Reducer Spray Water Line (3 Line)

SUB TOTAL 52 4 8 20 80

DIRECT MANPOWER AS PER CLASS 52 4 8 20 80

TOTAL DIRECT MANPOWER 164

DIRECT STAFF QTY INDIRECT MANPOWER QTY MANPOWER


SUPERVISOR
Site Manager 1 QC Checker 4 FITTER HP GTAW SMAW RIGGER Available Balance
Cont. Manager 0 Safetyman 3 Arif Saputro 10 3 -7
PCE 1 Formen Welder 2 Azhar Efendi 8 3 -5
Engineer 2 Helper Welder 2 Esron TT 8 3 -5
Superientendent 1 Whs & Matl 2 SUPARDI 10 2 -8
Mechanical Supervis 6 Electric 4 ZULFAHMI 8 4 -4
Rigger Supervisor 1 Security 3 FADLI M.M 8 6 -2
RED/Electric 1 Driver 5 Romi 4 8 20 5 -27
Welder Supervisor 1 Office Boy 2 Deni Roni 80 7 -73
QC Coordinator 1 Helper Safetyman 2
QC Inspector 2
Ware House & Matl 2 Total Per Class 52 4 8 20 80 33 -131
Safety Officer 1 Grand Total Manpower 213
TOTAL 20 TOTAL 29
270

16

#VALUE!
63 Other 45 hrs Apr 24 4:00 PM Apr 26 1:00 PM

64 452 Provide power supply 24 VDC for support maintenance 45 hrs Apr 24 4:00 PM Apr 26 1:00 PM
job and tube cleaning
65 452 Inspection , repair/replace part & cleaning motor terminal, 45 hrs Apr 24 4:00 PM Apr 26 1:00 PM
cooling fan/body motor
5 hrs Apr 24 4:00 PM Apr 26 1:00 PM Johan + Truba MPS

hrs Apr 24 4:00 PM Apr 26 1:00 PM Johan + Truba MPS