:LSGD/CELSGD/EST/32006/2022_5_1_1 (Edit Id : 3)
(Dsor year : 2018,Cost Index (Place : Kottayam,Value : 136.44),GST : 18%
GENERAL ABSTRACT
Annual Plan-UBR-159/2022-23 ROAD-IMPROVEMENTS TO CHATHANMALA
KURISHUPALLI-CHERADI ROAD WARD-5 MGR-3,80,875-General Civil Work-
159310050000000060
DETAILED ESTIMATE
Annual Plan-UBR-159/2022-23 ROAD-IMPROVEMENTS TO CHATHANMALA
KURISHUPALLI-CHERADI ROAD WARD-5 MGR-3,80,875-General Civil Work-
159310050000000060
ABSTRACT ESTIMATE
Annual Plan-UBR-159/2022-23 ROAD-IMPROVEMENTS TO CHATHANMALA
KURISHUPALLI-CHERADI ROAD WARD-5 MGR-3,80,875-General Civil Work-
159310050000000060
DATA ANALYSIS
Annual Plan-UBR-159/2022-23 ROAD-IMPROVEMENTS TO CHATHANMALA
KURISHUPALLI-CHERADI ROAD WARD-5 MGR-3,80,875-General Civil Work-
159310050000000060
Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course
aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding
compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding
25mm , mixed in concrete mixer etc complete as perspecification
(i) Nominal mix (1:2:4)
Details of cost for 1 cum
Material M
M-081 Cement
tonne 0.33000 5032.24 1660.64 M1
M-348 Sand
cum 0.45000 1453.77 654.20 M2
M-359 20 mm Aggregate
cum 0.54000 1453.77 785.04 M3
M-360 10 mm Aggregate
cum 0.36000 1453.77 523.36 M4
Labour L
L-12
Mate
Day 0.08000 617.00 49.36 L1
L-11
Mason (1st class)
Day 0.10000 738.00 73.80 L2
L-29
Mazdoor (Unskilled)
Day 1.63000 558.00 909.54 L3
L-21
Bhisti
Day 0.27000 617.00 166.59 L4
Tools&Plants(Hire charges) T