13-09-2022 - AC Quote - Oftog Bussiness Solutions

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

13/09/2022

Oftog Bussiness Solutions


Hyderabad.

Dear Sir,

Sub: Daikin VRV Air conditioning offer for your Project – Commercial

With reference to the above subject, we are herewith forwarding our offer in the form of following
annexure being enclosed:

Annexure- I : Superior Features of DAIKIN VRV-XSystem


Annexure- II : Equipment Schedule
Annexure- III : Equipment Cost (Attached)
Annexure –IV : Low Side cost (Attached )
Annexure- V : General Terms & Conditions
Annexure- VI : Exclusions for Installation works

We hope our offer is in line with your requirements;should you need any additional details, please
feel free to contact us.

Thanking you & assuring you of our best attention always.

Yours truly,

Syed Vasiq
+919849049610
Airwell Engineering Pv. Ltd
8-2-602/D, opposite Hanging Gardens,
Road No.10, Banjara Hills, Hyd-34
ANNEXURE – I

DAIKIN
The world leader in air-conditioning

At Daikin we are leading innovator and provider of advanced, high-quality air conditioning solutions for
residential, commercial and industrial applications.

As World’s leading air conditioning company, we are committed to deliver air conditioning solutions
that enhance the quality of life all around the world.

Established in 1924 Daikin Industries Ltd., are a diverse multinational company, active in air
conditioning, chemicals and oil hydraulics with headquarters at Osaka, Japan, our Daikin family has
more than 67,000 members, working across 80 production base and 208 consolidated subsidiaries
worldwide.

As the World’s sole manufacturer that develops a long line of products from refrigerants to air
conditioners, we advocate comfortable living on the strength of advanced technologies.We are present
in USA, Europe and Russia, The middle East , Africa,Asia, Oceania and Middle-south America.We aim to
serve our customers in each of these markets by providing optimal air conditioning solutions.
BOD:

AREA SUGGESTED DAIKIN TOTAL


S.NO LOCATION QTY TYPE MODEL
(sqft) TR TR TR

1 FOUR SEATER CABIN 1


2 FOUR SEATER CABIN 2
3 FOUR SEATER CABIN 3
430 4.30 4.65 1 4.65 DUCTABLE FXMQ140PBV36
4 MGR CABIN 02
5 MGR CABIN 03
6 MGR CABIN 04
7 FOUR SEATER CABIN 4 86 0.96 0.83 1 0.83 HI WALL FXAQ25ARVE6
8 FOUR SEATER CABIN 5 86 0.86 0.83 1 0.83 HI WALL FXAQ25ARVE6
9 FOUR SEATER CABIN 6 80 0.67 0.61 1 0.61 HI WALL FXAQ20ARVE6
10 SIX SEATER CABIN 120 1.00 1.06 1 1.06 HI WALL FXAQ32ARVE6
11 FIVE SEATER CABIN 89 0.74 0.61 1 0.61 HI WALL FXAQ20ARVE6
12 THREE SEATER CABIN 01 75 0.63 0.61 1 0.61 HI WALL FXAQ20ARVE6
13 THREE SEATER CABIN 02 77 0.64 0.61 1 0.61 HI WALL FXAQ20ARVE6
14 MGR CABIN 01 59 0.49 0.61 1 0.61 HI WALL FXAQ20ARVE6
15 MGR CABIN 05 70 0.58 0.61 1 0.61 HI WALL FXAQ20ARVE6
16 5 & 3 POD STATION 160 1.33 1.32 1 1.32 HI WALL FXAQ40ARVE6
11 12.35

IDU TR IDU HP SUGGESTED ODU CONNECTIVITY

12.35 14.88 12 124.00%

DAIKIN - EQUIPMENT (HIGH SIDE)


S.No Description Unit Qty Rate Amount
1 Supply of Variable Refrigerant Volume outdoor
units comprising multiple high COP scroll
compressors with invertor drive, low noise
propellor type aero spiral fan, Condenser coil
with special acrylic pretreatment for improved
resistance to salt corrosion, refrigerant shut off
valves, safety devices, lead free PC boards
suitable for operation on R410a.

A
12HP OUTDOOR UNIT VRV S RXMQ12ARY16 Nos 1
223,725.00 223,725.00
B
DG KITS Nos 1
7,000.00 7,000.00
2 Supply of
indoor units compring with pre-filter,fan
section with low noise fan multi speed motor,
coil
section, insulation, pipe connections of various
capacities with refnet joint.WITH CORDLESS
REMOTE CONTROLLER.
C FXMQ140PBV36, 4.65TR, DUCTABLE Nos 1 72,750.00 72,750.00
D FXAQ40ARVE6, 1.32TR, HI WALL Nos 1 30,450.00 30,450.00
E FXAQ32ARVE6, 1.06TR, HI WALL Nos 1 28,575.00 28,575.00
F FXAQ25ARVE6, 0.83TR, HI WALL Nos 2 28,125.00 56,250.00
G FXAQ20ARVE6, 0.83TR, HI WALL Nos 6 27,750.00 166,500.00
SUB-TOTAL -I 585,250.00
GST@ 28% 163,870.00
TOTAL -I 749,120.00

LOW SIDE
Lifting,Shifting, Positioning &
Commissioning of the Units
1 Nos 1 15,000.00 15,000.00
(Out door units located same
level)

2 Lifting ,Shifting ,Positioning IDU

i Wall Mounted Nos 10 2,200.00 22,000.00


ii Ductable Nos 1 8,000.00 8,000.00

Supply & installation of copper


refrigerant piping the following
sizes duly insulated with nitrile
3
insulation of 19mm thick for
pipes above 1" dia and 13mm
thick for pipes below 1" dia.

3.01 41.1 mm dia / 19 mm Insulation Rmt.


3.02 34.9 mm dia / 19 mm Insulation Rmt.
3.03 28.6 mm dia / 19 mm Insulation Rmt.
3.04 22.2 mm dia / 19 mm Insulation Rmt. 90 1,450.00 130,500.00
3.05 19.1 mm dia / 19 mm Insulation Rmt.
3.06 15.9 mm dia / 13 mm Insulation Rmt.
3.07 12.7 mm dia / 13 mm Insulation Rmt.
3.08 9.5 mm dia / 13 mm Insulation Rmt.
3.09 6.4 mm dia / 13 mm Insulation Rmt.

Supply , Installation , Testing and


Commissioning of site fabricated
ducting as per IS:655: 2006
standard complete with fittings ,
4 22
flanges, supports , all accessories
and any other item required to
make the system complete.
(Rectangular Duct)

A 24 G Sqm 15.4 1,450.00 22,330.00


B 22 G Sqm 6.6 1,250.00 8,250.00

Supply, Fixing and Commissioning


D RFT 40 650.00 26,000.00
of Continous Grill ( size-

Supplying and Fixing of 9 mm


E Sqm 22 750.00 16,500.00
thickness Nitrile rubber

Supplying and fixing of acoustic


F Sqm 6.6 950.00 6,270.00
Insulation.

Supply installation of canvas


G No's 1 3,500.00 3,500.00
connection

Supply & Installation PVC drain


piping with suitable supports as
4
required & insulated with 9mm
thick Nitrile rubber insulation
32mm dia Rmt 40 150.00 6,000.00

Supply & Installation of


transmission wiring from
5 Rmt 180 150.00 27,000.00
indoor unit to outdoor unit
2CX1.0 Sq.mm

Pressure testing &


6 HP 12 2,000.00 24,000.00
Commisioning of total system
TOTAL = B 315,350.00
GST @ 18% 56,763.00
TOTAL LOW SIDE 372,113.00
(AIR CONDITIONING- VRV) GRAND TOTAL = A+B 1,121,233.00
NOTE: ABOVE LOW SIDE QUANTITIES ARE TENTATIVE, ACTUAL QUANTITIES WILL
MEASURE AFTER COMPLETION OF LOW SIDE WORK.

Note:
1.) Any variation in lowside will be as per measurements at the site.
2.) Civil platform for outdoor is not in our scope
3.) Core Cutting, Chipping, wall opening and any kind of civil works is excluded
4.) Scaffolding, Cable tray, Fabrication works is out of scope

ANNEXURE – V GENERAL TERMS & CONDITIONS

1. ORDER

a. Order: For Equipment & Indigenous Work: The order shall be placed on M/s. AIRWELL
ENGINEERING PVT LTD

2. PAYMENT TERMS

For high side and controls:

100% advance along with the order

For Low side equipment:

70% advance along with the order& 20% on copper piping & ducting work & balance 10% on
commissioning.

3. ESTIMATED DELIVERY PERIOD:

We shall complete supply of equipments and Installation work & commissioning work as per
following schedule

i. VRV Equipment-within 3-4 weeks up to Site.

ii. Site Commissioning - within 3-4 weeks after receipt of


Equipment at site.
4. WARRANTY

The system shall be warranted for 15 months from date of supply or 12 months from date of
commissioning whichever comes earlier.

5. VALIDITY
This Price Validity is valid till this month end.

AMC START at 2600/HP post warranty period of 18 months from commissioning. After that
5% escalation from 2nd year of AMC

Annexure-VI Exclusions:

We have not included the following works related to execution of low side activities and shall be
arranged by your appointed agencies as per requirement of the project:

1. All masonry work/civil works such as supports for the condensing units, cutting away and
making good of walls, floors slabs, making & closing of trenches etc.

2. Supply and installation of main power supply terminating at each outdoor unit (3 phase) and
near each indoor unit (single phase) with isolating MCB at both.

3. Any drain points in our scope of works & the same shall have to be arranged by civil contractor.

4. Any kind of false ceiling works, boxing work, wooden framework/carpentry work.

5. Provision of necessary drain points

6. Any under deck insulation, false ceiling insulation work.

7. Protected storage space at site.

8. Power for erection, testing & commissioning of the system.

9. Any kind of dismantling work.

10. Any other work, which is not agreed specifically.


NOTE:
• 3-Phase power supply is must for outdoor unit and if any phase reversal or any phase is
not available in the power supply then the outdoor unit shall not function.
We recommend the phase sequencer in case of phase reversal problem.
• The power supply for the indoor units & outdoor units shoulsd not be interrupted and
it shall be always ON. Any operation for ON/ OFF of the indoor units shall be through
remote controller only.
• Commissioning will be done on Permanent and stable power supply only.

Yours truly,
For AIRWELL ENGINEERING PVT. LTD.

Syed Vasiq
+919849049610

You might also like