Professional Documents
Culture Documents
Estimate-1. Desilting GWD Canal in Nidadavolu City Limits
Estimate-1. Desilting GWD Canal in Nidadavolu City Limits
Estimate-1. Desilting GWD Canal in Nidadavolu City Limits
NAME OF WORK
Estimate Rs.2,01,06,000/-
SUPERINTENDING ENGINEER
IRRIGATION CIRCLE
Eluru
Report accompanying the estimate for “Desilting of Apparao Channel
from Km 2.00 to 3.60 and GWD Canal from KM 5.00 to KM 8.00 in City
limits of Nidadavolu in East Godavari District.”
The following irrigation canals are flowing through the Nidadavolu city along with
their lengths in the city limits proposed for beautifications are as follows.
These are a lifeline, a source of drinking water and irrigation needs for hundreds
of villages in the Godavari Western Delta. Originating from Godavari River in
Vijeswaram, the canals impact the lives of people of the city in various ways. For
administrators, canals and canal banks pose many challenges.
There are encroachments in the Nidadavolu city limits on both left and right
banks Canals viz., houses, temples, stalls, workshops, etc.
Hence there is a need to restore the canals for irrigation and navigation interest
of conservation, improving quality of life leading to wider social economic and
environmental regeneration in the areas neighbourhood of canals.
The aim for beautification of canals is to reclaim the canal banks as public asset,
improve its spatial structure based on current pattern of adjacent land use, habitat and
structural conditions for restoring the city’s relationship with canals.
ABSTRACT
Name of Work: Desilting of Apparao Channel from Km 2.00 to 3.60 and GWD Canal from
KM 5.00 to KM 8.00 in City limits of Nidadavolu in East Godavari District
Name of Work: Desilting of Apparao Channel from Km 2.00 to 3.60 and GWD Canal from KM 5.00 to
KM 8.00 in City limits of Nidadavolu in East Godavari District
Providing homogeneous embankment using soil from approved borrow area in layers of 25 to
IRR-
30 cm before compaction including cost of all materials, machinery, labour, all operations such
PMW- 1
as excavation, sorting out,transportation, spreading soil in layer of specified thickness, breaking
3-22
clods,sectioning,etc.,complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: Unit: 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1650.20 4455.54
Fuel / Energy charges Hour 2.70 1055.30 2849.31
2 Shovel 0.85 cum capacity Hour 8.00 1648.80 13190.40
Fuel / Energy charges Hour 8.00 1508.60 12068.80
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 436.30 17452.00
Fuel / Energy charges Hour 40.00 518.40 20736.00
Total hire charges of Machinery 70752.05
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 2.70 326.30 881.01
2 Crew for Shovel Hour 8.00 326.30 2610.40
3 Crew for Tipper Hour 40.00 244.70 9788.00
4 work inspector Day 1.00 685.00 685.00
5 mazdoor Day 2.00 525.00 1050.00
Total cost of Labour Rs: 15014.41
Add 20% Muncipal Area Allowance 3002.88
18017.29
labour component/unit qty 18.60
Add contractor's profit and overhead charges 13.615% 2.50
labour component/unit qty (including contractor's profit) 21.10
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 70752.05
C. Cost of Labour Rs: 15014.41
Total Rs: 85766.46
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 11677.10
Add 20% Muncipal Area Allowance on labour 3002.88
Total cost for 807.00 cum Rs: 100446.45
Rate
cum (A+B+C+D)/807 Rs: 124.47
per
D. add convayance charges (10 Kms) Rs: 132.00
256.47
or say 256.50
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
IRR-CAW- embankment, filter drains / catch water drains etc., including dressing bed and sides to
1- required level and profile, cost of all materials, machinery, labour, placing the excavated soil
1 neatly in dump area or for the formation of service road / embankment as directed
etc.,complete with initial lead upto 1 km and all lifts.
B. Machinery:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity hour 8.00 1648.80 13190.40
Fuel/ Energy charges hour 8.00 1508.60 12068.80
2 Tippers 5 cum capacity 6 Nos hour 48.00 436.30 20942.40
Fuel/ Energy charges hour 48.00 518.40 24883.20
Total in Rs. 71084.80
C. Labour:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel hour 8.00 326.30 2610.40
2 Crew for Tipper hour 48.00 244.70 11745.60
3 work inspector Day 1.00 685.00 685.00
4 Mazdoor Day 30.00 525.00 15750.00
Total in Rs. 30791.00
Add 20% Muncipal Area Allowance 6158.20
36949.20
labour component/unit qty 33.30
Add contractor's profit and overhead charges 13.615% 4.50
labour component/unit qty (including contractor's profit) 37.80
Abstract
a) Material Rs 0.00
b) Machinery Rs 71084.80
c) Labour Rs 30791.00
Total Rs 101875.80
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 13870.39
Add 20% Muncipal Area Allowance on labour 6158.20
Total cost for 240.00 cum Rs: 121904.39
Rate per
cum (A+B+C+D)/240.0 Rs. 131.79
Add Conveyance Charges(10 Kms) 132.00
Rate per Cum 263.79
or say 264.00