Project:

South Negros BioPower


25 MW Power Plant La Carlota - Negros, Philippines

Owner: National Highway, Brgy. Cubay


La Carlota City
Negros Occidental
Philippines

Weekly Flash Activity Report


Report
Report Period: January 24 – January 30, 2019
No.: 0002
HSE:
1. No of Man Days Worked: 2,364
2. Total No. of Hours Worked (Normal +Overtime): 24,970
3. No of Fatality-free Days = 2,364
4. No incidents, work-stopping accidents or first aids event this report period.
5. Joint Site Walk-through Inspection conducted last January 25, 2019 with
most safety issues related on housekeeping, access, and stagnant waters
due to heavy rains the previous days.
6. General Toolbox Meeting conducted last January 25, 2019 facilitated by
San Carlos Construction Solutions, Inc. with a topic of Safe Driving.
7. Safety Briefing conducted to workers dealing with work at heights and
those involved with excavation and trench works.
8. Received one (1) unit brush cutter for site grass cutting activities.
9. Conducted meeting last January 25, 2019 with Contractors’ Safety Person-
nel regarding changes on site with the arrival of EBATECH & Tacophil.
Certain walkthrough inspections findings were also discussed.
10. Addressed past week safety issues on provision of safe access for workers
assigned at Area 13, Area 21, Area 17, and Area 01.

Company Name Manpower


Sinian International Corp. (SIC) Daily Average = 128 persons

San Carlos Construction Solutions ( SCCONS) Daily Average = 193 persons

South Negros BioPower, Inc. (SNBP) Daily Average = 13 persons

Taihei AllTech Const. Phils. Inc. (TACOPHIL) Daily Average = 19 persons

Energy & Building Applications


Daily Average = 14 persons
Technologies Corp. (EBATECH)

TOTAL Daily Average = 367 persons

SNBP Page | 1